| AQ0231TVP05A | Trident Seafoods | Akutan Seafood Processing Facility | Klina, Joshua | Drafting ORL section associated with recent addendum.
10/22/2025 | 2021|11|17 |  |  |  |  |  |  |  | TV Renewal |  | 698 |  | Awaiting Applicant Response 05/02/2024 | In-house | 
                    
                        | AQ0231MSS04A | Trident Seafoods | Akutan Seafood Processing Facility | Klina, Joshua | Drafting permit and TAR. | 2022|02|24 | 2022|06|17 |  |  |  |  |  |  | Minor Modification | 18 AAC 50.508(6) | 655 |  | In Completeness Review 06/17/2022 | In-house | 
                    
                        | AQ0231MSS03P | Trident Seafoods | Akutan Seafood Processing Facility | Klina, Joshua | Drafting | 2024|10|10 |  |  |  |  |  |  |  | Install Rain Cap on EU ID 30 |  | 386 | Joshua Klina |  | In-house | 
                    
                        | AQ0489TVP03A | ConocoPhillips Alaska, Inc. | Alpine Central Processing Facility | Faber, Scott | Pre-public notice review / Public notice | 2020|07|31 | 2020|07|31 |  |  |  |  |  |  | TV Renewal |  | 0 |  | Supervisor Review 12/08/2022 | In-house | 
                    
                        | AQ0624TVP05A | Municipality of Anchorage | Anchorage Regional Landfill | Saengsudham, Peter | 10/10/25 Peter S. - Initial review for completeness | 2025|10|02 |  |  |  |  |  |  |  | TVP Renewal |  | 29 |  |  | In-house | 
                    
                        | AQ0062TVP05A | Hilcorp Alaska, LLC | Anna Platform | Rea, Jonathon | Draft permit sent for technical review | 2024|10|18 |  |  |  |  |  |  |  | TVP Renewal |  | 362 |  |  | In-house | 
                    
                        | AQ0062MSS02A | Hilcorp Alaska, LLC | Anna Platform | Rea, Jonathon | Draft permit sent for technical review | 2024|10|18 |  |  |  |  |  |  |  |  |  | 362 | James Renovatio |  | In-house | 
                    
                        | AQ0208TVP06A | Alaska Electric Light & Power | Auke Bay Standby Generation Station | Faber, Scott | EPA 45-Day Review | 2025|02|27 | 2025|02|27 |  |  | 2025|08|01 | 2025|09|01 |  |  | TVP Renewal |  | 246 |  | EPA Review End 11/30/2025 | In-house | 
                    
                        | AQ0417TVP04A | Savant Alaska LLC | Badami Development Facility | Boyden, Zachary | 10/24/24 On Hold for OOOOb decision | 2023|03|09 | 2023|03|10 |  |  | 2024|07|03 | 2024|08|02 |  |  | Renewal |  | 593 |  | Public Notice End 08/02/2024 | In-house | 
                    
                        | AQ0106TVP05A | Chugach Electric Association | Beluga River Power Plant | Faber, Scott | Supervisor review / Public notice | 2025|01|02 | 2025|01|02 |  |  |  |  |  |  | TVP Renewal |  | 302 |  | Supervisor Review 03/07/2025 | In-house | 
                    
                        | AQ0942MSS02P | Hilcorp Alaska, LLC | Beluga River Unit | Leibert, Adam | Second Public Notice Terminated due to technical inaccuracies. NN 10.29.2025 | 2024|03|08 |  |  |  | 2025|10|03 | 2025|10|29 |  |  | POGO Project | 18 AAC 50.508(6) | 602 | Zachary Boyden | Public Notice End 10/29/2025 | In-house | 
                    
                        | AQ0942TVP02A | Hilcorp Alaska, LLC | Beluga River Unit | Leibert, Adam | Second Public Notice Terminated due to technical inaccuracies. 
NN 10.30.2025 | 2018|07|09 |  |  |  | 2024|02|06 | 2024|03|07 |  |  | TVP Renewal |  | 834 |  | 2nd Public Notice End 03/07/2024 | In-house | 
                    
                        | AQ0086TVP05A | Alaska Electric and Energy Cooperative | Bernice Lake Combustion Turbine (BCT) Plant | Hasan, Ibnul | EPA-45 day review | 2024|12|10 |  |  |  | 2025|08|08 | 2025|09|08 |  |  | TV Renewal |  | 325 |  | EPA Review End 12/12/2025 | In-house | 
                    
                        | AQ0064TVP05A | Hilcorp Alaska, LLC | Bruce Platform | Saengsudham, Peter | 3/20/25 Peter S. - Informal application complete. Drafting permit. | 2025|01|21 | 2025|03|20 |  |  |  |  |  |  | TVP Renewal |  | 225 |  | In Completeness Review 03/20/2025 | In-house | 
                    
                        | AQ0166MSS02A | Hilcorp North Slope, LLC | Central Compressor Plant (CCP) | Application, On Hold | Permti on hold. EPA rejected proposed footnote revision. | 2013|10|28 |  |  |  |  |  |  |  | Revision of Terms and Conditions of AQ0166CPT04 |  | 0 |  |  | In-house | 
                    
                        | AQ0166TVP02A | Hilcorp North Slope, LLC | Central Compressor Plant (CCP) | Application, On Hold | Working RTC and EPA/45 version.  Footnote issue. | 2008|03|06 | 2008|05|30 |  | 2008|07|23 | 2013|09|13 | 2013|10|29 | 2013|09|09 |  | TVP Renewal |  | 2230 |  | Public Notice End 10/29/2013 | In-house | 
                    
                        | AQ0166TVP01P | Hilcorp North Slope, LLC | Central Compressor Plant (CCP) | Jones, David | On hold - application is related to footnote issue. | 2024|11|26 |  |  |  |  |  |  |  | Update Table 5 - Emission Factors |  | 0 |  |  | In-house | 
                    
                        | AQ0270TVP01P | Hilcorp North Slope, LLC | Central Gas Facility (CGF) | Jones, David |  | 2020|04|21 |  |  |  |  |  |  |  | Minor Modification |  | 902 |  |  | In-house | 
                    
                        | AQ0270TVP01P | Hilcorp North Slope, LLC | Central Gas Facility (CGF) | Jones, David | On hold - application is related to footnote issue. | 2022|06|30 |  |  |  |  |  |  |  | Admin Amendment |  | 0 |  |  | In-house | 
                    
                        | AQ0270TVP02A | Hilcorp North Slope, LLC | Central Gas Facility (CGF) | Application, On Hold | PN draft sent to JNU admin.
Footnote issue. | 2008|03|06 | 2008|05|06 |  | 2013|05|17 | 2013|08|29 | 2013|10|15 | 2013|08|27 |  | TVP Renewal |  | 2254 |  | Public Notice End 10/15/2013 | In-house | 
                    
                        | AQ0270MSS02A | Hilcorp North Slope, LLC | Central Gas Facility (CGF) | Application, On Hold | Permti on hold. EPA rejected proposed footnote revision. | 2013|10|15 |  |  |  |  |  |  |  | Minor Amendment |  | 0 |  |  | In-house | 
                    
                        | AQ0315TVP05A | Aurora Energy LLC | Chena Power Plant | Leibert, Adam |  | 2024|07|05 |  |  |  |  |  |  |  | TVP Renewal |  | 483 |  |  | In-house | 
                    
                        | AQ0267TVP02A | ConocoPhillips Alaska, Inc. | CPF 1, Kuparuk Central Production Facility #1 | Faber, Scott | 5/7/2025 Updating permit documents | 2007|11|19 |  |  | 2011|06|17 | 2012|11|29 | 2012|12|31 | 2011|06|27 |  | TV Renewal |  | 2423 |  | Awaiting Applicant Response 07/03/2014 | In-house | 
                    
                        | AQ0267TVP01P | ConocoPhillips Alaska, Inc. | CPF 1, Kuparuk Central Production Facility #1 | Application, On Hold | 3.13.23 On hold for footnote issue. | 2019|09|24 |  |  |  |  |  |  |  | CPF1 Minor Mod |  | 2229 |  |  | In-house | 
                    
                        | AQ0273TVP01P | ConocoPhillips Alaska, Inc. | CPF 2, Kuparuk Central Production Facility #2 | Application, On Hold | 3.13.23 On hold due to footnote issue | 2018|01|22 |  |  |  |  |  |  |  | non-applicability of NSPS Subpart Kb |  | 2839 |  |  | In-house | 
                    
                        | AQ0273TVP02A | ConocoPhillips Alaska, Inc. | CPF 2, Kuparuk Central Production Facility #2 | Application, On Hold | Footnote issue. | 2007|06|25 |  |  |  |  |  |  |  | Renewal |  | 2570 |  | Begin Work 04/04/2008 | In-house | 
                    
                        | AQ0171TVP02A | ConocoPhillips Alaska, Inc. | CPF 3, Kuparuk Central Production Facility #3 | Application, On Hold | App Addendum for renewal application received.  Footnote issue. | 2007|07|03 |  |  | 2010|12|06 |  |  |  |  | Renewal |  | 2562 |  | Draft to Super. 12/06/2010 | In-house | 
                    
                        | AQ0171TVP01P | ConocoPhillips Alaska, Inc. | CPF 3, Kuparuk Central Production Facility #3 | Application, On Hold | include in renewal (on hold due to footnote issue) - see review notes | 2018|01|22 |  |  |  |  |  |  |  | non-applicability to NSPS Subpart Kb |  | 2839 |  |  | In-house | 
                    
                        | AQ0265TVP04A | Hilcorp North Slope, LLC | Crude Oil Topping Unit (COTU) | Faber, Scott | Supervisor review of response to comments / EPA review | 2023|07|03 | 2023|07|03 |  |  | 2024|07|10 | 2024|08|09 |  |  | Crude Oil Topping Unit |  | 851 |  | Supervisor Review 10/09/2024 | In-house | 
                    
                        | AQ0494TVP05A | Copper Valley Electric Association | CVEA Cogeneration Project | Leibert, Adam | Initial permit assignment. Next step: completeness review | 2025|09|17 |  |  |  |  |  |  |  | TVP Renewal |  | 44 |  |  | In-house | 
                    
                        | AQ0060TVP05A | Hilcorp Alaska, LLC | Dolly Varden Platform | Saengsudham, Peter | 9/4/25 Peter S. - Technical review copy received by Permittee. Reviewing suggested edits. | 2024|10|18 | 2024|12|17 |  |  |  |  |  |  | TVP Renewal |  | 310 |  | In Completeness Review 12/17/2024 | In-house | 
                    
                        | AQ1552TVP01A | ConocoPhillips Alaska, Inc. | Doyon 26 Extended Reach Drilling (ERD) Rig | Unassigned, Permit Application |  | 2024|06|03 |  |  |  |  |  |  |  | Doyon 26 Drill Rig POGO |  | 515 |  |  | In-house | 
                    
                        | AQ0237TVP04A | Doyon Utilities, LLC | DU-JBER-Electric, Gas, Drinking Water and Sanitary Services | Boyden, Zachary | Public Notice | 2025|05|29 |  |  |  | 2025|10|16 | 2025|11|17 |  |  | TVP Renewal |  | 155 |  | Public Notice End 11/17/2025 | In-house | 
                    
                        | AQ0264TVP03A | US Air Force (Eielson) | Eielson Air Force Base | Boyden, Zachary | 10/13/25 Awaiting FCE Response | 2017|10|16 |  |  |  |  |  |  |  | Renewal |  | 2122 |  | Awaiting Applicant Response 10/13/2025 | In-house | 
                    
                        | AQ0264MSS07A | US Air Force (Eielson) | Eielson Air Force Base | Boyden, Zachary | 10/13/25 Awaiting FCE Response | 2025|02|21 |  |  |  |  |  |  |  | 2025 EAFB Minor Permit Rev. |  | 252 |  | Awaiting Applicant Response 10/13/2025 | In-house | 
                    
                        | AQ1086TVP02P | Matanuska Electric Association, Inc | Eklutna Generation Station | Rea, Jonathon | Drafting permit | 2025|05|01 |  |  |  |  |  |  |  | Integrated Review with AQ1086TVP03 Rev 1 |  | 183 |  |  | In-house | 
                    
                        | AQ1086MSS03P | Matanuska Electric Association, Inc | Eklutna Generation Station | Rea, Jonathon | Drafting permit | 2025|05|01 |  |  |  |  |  |  |  | Eklutna Generation Station |  | 183 | Zachary Boyden |  | In-house | 
                    
                        | AQ0181TVP03A | Hilcorp Alaska, LLC | Endicott Production Facility (END) | Application, On Hold | BACT table contains footnote on full-load. | 2017|07|14 |  |  |  |  |  |  |  | Renewal |  | 0 |  |  | In-house | 
                    
                        | AQ0167TVP03A | Hilcorp North Slope, LLC | Flow Station #1 (FS 1) | Application, On Hold | PN draft ready for supervisor review.  No further work till the BACT full load issue is resolved.
Footnote issue. | 2017|04|19 | 2017|04|28 |  |  |  |  |  |  | Renewal |  | 0 |  | In Completeness Review 04/28/2017 | In-house | 
                    
                        | AQ0268TVP02A | Hilcorp North Slope, LLC | Flow Station #2 (FS 2) | Application, On Hold | Withdrawing from EPA/45 to solve PSD BACT. Footnote issue. | 2008|06|11 |  |  | 2012|11|30 | 2013|05|20 | 2013|06|19 | 2013|05|08 |  | TVP renewal |  | 2218 |  | Awaiting Applicant Response 04/16/2014 | In-house | 
                    
                        | AQ0268TVP01P | Hilcorp North Slope, LLC | Flow Station #2 (FS 2) | Jones, David |  | 2022|06|30 |  |  |  |  |  |  |  | Admin Amendment |  | 0 |  |  | In-house | 
                    
                        | AQ0269TVP01P | Hilcorp North Slope, LLC | Flow Station #3 (FS 3) | Jones, David | On hold - application is related to footnote issue. | 2024|10|24 |  |  |  |  |  |  |  | Update Table 5 - Emission Factors |  | 0 |  |  | In-house | 
                    
                        | AQ0269TVP02A | Hilcorp North Slope, LLC | Flow Station #3 (FS 3) | Application, On Hold | Withdrawing from EPA/45 to solve PSD BACT. Footnote issue. | 2007|10|02 |  |  | 2009|02|18 | 2013|06|11 | 2013|07|11 | 2013|06|04 |  | FS #3 TV Renewal |  | 2471 |  | Awaiting Applicant Response 04/16/2014 | In-house | 
                    
                        | AQ0238TVP05A | US Army (Fort Greely) | Fort Greely  Real Estate - Garrison | Faber, Scott | Supervisor review / EPA review | 2025|03|06 |  |  |  | 2025|09|05 | 2025|10|06 |  |  | TVP Renewal |  | 239 |  | Supervisor Review 10/09/2025 | In-house | 
                    
                        | AQ0236TVP05A | US Army (Fort Wainwright) | Fort Wainwright | Rea, Jonathon | Drafting permit | 2024|12|10 |  |  |  |  |  |  |  | TVP Renewal |  | 325 |  |  | In-house | 
                    
                        | AQ1121TVP03A | Doyon Utilities, LLC | Fort Wainwright (Privatized Emission Units) | Application, On Hold | withdrawn from EPA - permit on hold until we solve the serious SIP issue | 2019|05|03 |  |  |  | 2021|04|22 | 2021|05|25 |  |  | TVP Renewal |  | 951 |  | EPA Review End 12/13/2021 | In-house | 
                    
                        | AQ1524CPT02A | 8 Star Alaska LLC | Gas Treatment Plant (GTP) | Klina, Joshua | Application received | 2025|02|10 |  |  |  |  |  |  |  | Alaska LNG |  | 263 | Zachary Boyden |  | In-house | 
                    
                        | AQ0182TVP02A | Hilcorp North Slope, LLC | Gathering Center #1 (GC 1) | Application, On Hold | Footnote issue. | 2008|05|21 | 2009|04|28 |  | 2011|11|02 | 2012|04|19 | 2012|06|18 | 2012|04|09 |  | TV Renewal |  | 1897 |  | Public Notice End 06/18/2012 | In-house | 
                    
                        | AQ0182TVP01P | Hilcorp North Slope, LLC | Gathering Center #1 (GC 1) | Jones, David |  | 2019|04|23 |  |  |  |  |  |  |  | Well Pad Disaggregation |  | 1266 |  |  | In-house | 
                    
                        | AQ0182TVP01P | Hilcorp North Slope, LLC | Gathering Center #1 (GC 1) | Jones, David |  | 2020|06|02 |  |  |  |  |  |  |  | Minor Modification |  | 860 |  |  | In-house | 
                    
                        | AQ0182TVP01P | Hilcorp North Slope, LLC | Gathering Center #1 (GC 1) | Jones, David |  | 2022|06|30 |  |  |  |  |  |  |  | Admin Amendment |  | 0 |  |  | In-house | 
                    
                        | AQ0183TVP01P | Hilcorp North Slope, LLC | Gathering Center #2 (GC 2) | Jones, David | *App amendment in attachments 5.19.20 | 2018|12|27 |  |  |  |  |  |  |  | Minor Modification |  | 1383 |  |  | In-house | 
                    
                        | AQ0183TVP01P | Hilcorp North Slope, LLC | Gathering Center #2 (GC 2) | Jones, David |  | 2022|06|30 |  |  |  |  |  |  |  | Admin Amendment |  | 0 |  |  | In-house | 
                    
                        | AQ0183TVP02A | Hilcorp North Slope, LLC | Gathering Center #2 (GC 2) | Application, On Hold | Footnote issue. | 2008|05|28 |  |  | 2011|11|02 | 2012|04|19 | 2012|06|04 | 2012|04|09 |  | TV Renewal |  | 2232 |  | Public Notice End 06/04/2012 | In-house | 
                    
                        | AQ0184TVP01P | Hilcorp North Slope, LLC | Gathering Center #3 (GC 3) | Jones, David |  | 2019|08|14 |  |  |  |  |  |  |  | Dissagregation of Well Pads |  | 1153 |  |  | In-house | 
                    
                        | AQ0184TVP01P | Hilcorp North Slope, LLC | Gathering Center #3 (GC 3) | Jones, David | App. Received | 2020|06|09 |  |  |  |  |  |  |  | Minor Modification |  | 853 |  |  | In-house | 
                    
                        | AQ0184TVP01P | Hilcorp North Slope, LLC | Gathering Center #3 (GC 3) | Jones, David |  | 2022|06|30 |  |  |  |  |  |  |  | Admin Amendment |  | 0 |  |  | In-house | 
                    
                        | AQ0184TVP02A | Hilcorp North Slope, LLC | Gathering Center #3 (GC 3) | Application, On Hold | Working PN2 draft. Footnote issue. | 2008|07|01 | 2008|08|07 |  | 2011|11|02 | 2012|04|19 | 2012|05|21 | 2012|04|09 |  | TVP Renewal |  | 2161 |  | Public Notice End 05/21/2012 | In-house | 
                    
                        | AQ0203TVP05A | Chugach Electric Association | George Sullivan Plant Two | Hasan, Ibnul | Public Notice | 2024|12|17 |  |  |  | 2025|10|06 | 2025|11|06 |  |  | TVP Renewal |  | 293 |  | Public Notice End 11/06/2025 | In-house | 
                    
                        | AQ0287TVP06A | Copper Valley Electric Association | Glennallen Diesel Plant | Jurado, Victoria | Public Notice - S. Mahmuda | 2025|06|05 | 2025|08|29 |  |  | 2025|10|22 | 2025|11|24 |  |  | TV Renewal |  | 43 |  | Public Notice End 11/24/2025 | In-house | 
                    
                        | AQ0066TVP05A | Hilcorp Alaska, LLC | Granite Point Platform | Hasan, Ibnul | EPA 45-Day Review | 2025|04|16 |  |  |  | 2025|07|14 | 2025|08|14 |  |  | TVP Renewal |  | 198 |  | EPA Review End 10/24/2025 | In-house | 
                    
                        | AQ0069CPT02A | Hilcorp Alaska, LLC | Grayling Platform | Faber, Scott | 7/29/24 reviewing RFI response | 2023|12|04 |  |  |  |  |  |  |  | Fuel Gas H2S Increase |  | 697 | Zachary Boyden |  | In-house | 
                    
                        | AQ0173TVP04A | Golden Valley Electric Association | Healy Power Plant | Klina, Joshua |  | 2023|06|26 |  |  |  |  |  |  |  | TVP Renewal |  | 858 |  |  | In-house | 
                    
                        | AQ0173MSS03A | Golden Valley Electric Association | Healy Power Plant | Klina, Joshua |  | 2025|04|03 |  |  |  |  |  |  |  | Healy Power Plant |  | 179 |  |  | In-house | 
                    
                        | AQ0353TVP03A | North Slope Borough | Kaktovik Power Plant | Rea, Jonathon | Public Notice | 2024|04|17 | 2024|04|25 |  |  | 2025|10|03 | 2025|11|03 |  |  | TVP Renewal |  | 462 |  | Public Notice End 11/03/2025 | In-house | 
                    
                        | AQ0090TVP04A | Tesoro Alaska Company, LLC | Kenai Liquefied Natural Gas (LNG) Plant | Hirsch, Brian |  | 2024|04|23 |  |  |  |  |  |  |  | TVP Renewal |  | 556 |  |  | In-house | 
                    
                        | AQ0035TVP03P | Tesoro Alaska Company, LLC | Kenai Refinery | Hirsch, Brian | In supervisor review. 10/13/2025 | 2025|06|24 |  |  |  |  |  |  |  | TVP Revision 3 |  | 129 |  |  | In-house | 
                    
                        | AQ0982MSS11P | Furie Operating Alaska, LLC | Kitchen Lights Unit | Saengsudham, Peter |  | 2025|10|23 |  |  |  |  |  |  |  | Minor Modification under 18 AAC 50.508(6) | 18 AAC 50.508(6) | 8 |  |  | In-house | 
                    
                        | AQ0172TVP03A | ConocoPhillips Alaska, Inc. | Kuparuk Seawater Treatment Plant (STP) | Application, On Hold | BACT table contains footnotes on full load. No further work expected till footnote issue is resolved. | 2013|08|29 | 2013|09|20 |  | 2014|08|28 |  |  |  |  | TVP Renewal |  | 291 |  | Draft to Super. 08/28/2014 | In-house | 
                    
                        | AQ0741MSS03P | Cook Inlet Energy, LLC | Kustatan Production Facility | Jurado, Victoria | Initial permit assignment. Next step: completeness review | 2025|09|09 |  |  |  |  |  |  |  | Request to Rescind VOC Limit VOC Limit to Avoid Classification as PSD Major Source for EU IDs |  | 52 |  |  | In-house | 
                    
                        | AQ0741TVP04P | Cook Inlet Energy, LLC | Kustatan Production Facility | Jurado, Victoria | Initial permit assignment. Next step: completeness review | 2025|09|09 |  |  |  |  |  |  |  | Request to Rescind VOC Limit to Avoid Classification as PSD Major Source for EU IDs |  | 52 |  |  | In-house | 
                    
                        | AQ1727MSS03A | Harvest Alaska, LLC | Liquefied Natural Gas (LNG) Facility Prudhoe Bay Unit | Hirsch, Brian | pre-notice technical review Next step: revision and/or public notice | 2025|08|04 |  |  |  |  |  |  |  | Liquefied Natural Gas Facility |  | 74 | Brian Hirsch |  | In-house | 
                    
                        | AQ1727TVP01A | Harvest Alaska, LLC | Liquefied Natural Gas (LNG) Facility Prudhoe Bay Unit | Hirsch, Brian |  | 2025|07|07 |  |  |  |  |  |  |  | Initial TVP |  | 27 |  |  | In-house | 
                    
                        | AQ0272TVP03A | Hilcorp North Slope, LLC | Lisburne Production Center (LPC) | Application, On Hold | Sent draft PN permit to supervisor for review 11/1/16.  Held up by footnote issues | 2016|08|01 | 2016|08|01 |  |  |  |  |  |  | Renewal |  | 0 |  | In Completeness Review 08/01/2016 | In-house | 
                    
                        | AQ0272MSS04A | Hilcorp North Slope, LLC | Lisburne Production Center (LPC) | Saengsudham, Peter | 10/22/25 Sadia M. - Public Notice | 2024|07|02 |  |  |  | 2025|10|22 | 2025|11|24 |  |  | Power Export Project | 18 AAC 50.508(6) | 486 | James Renovatio | Public Notice End 11/24/2025 | In-house | 
                    
                        | AQ0881TVP01A | Hilcorp Alaska, LLC | MGS Onshore Facility | Application, On Hold | on hold pending EPA guidance for reclass of CISWI
7/12/2021 MWJ: see " Hold Periods (2) Notes"
8/8/2025 MWJ: see "Hold Period (3) Notes" | 2018|02|16 |  |  |  |  |  |  |  | Initial for incinerator |  | 79 |  |  | In-house | 
                    
                        | AQ1527MSS03P | Hilcorp Alaska, LLC | Milne Point L-Pad | Hasan, Ibnul | Public Notice | 2025|04|28 |  |  |  | 2025|08|07 | 2025|09|08 |  |  | Milne Point Unit L-Pad |  | 186 |  | Public Notice End 09/08/2025 | In-house | 
                    
                        | AQ1527TVP01P | Hilcorp Alaska, LLC | Milne Point L-Pad | Hasan, Ibnul | EPA-45 day review | 2025|04|28 |  |  |  |  |  |  |  | Integrated Review with AQ1527MSS03 Rev 1 |  | 186 |  | EPA Review End 10/31/2025 | In-house | 
                    
                        | AQ1559TVP02A | Hilcorp Alaska, LLC | Milne Point Unit C-Pad | Rea, Jonathon |  | 2025|02|10 |  |  |  |  |  |  |  | TVP Renewal |  | 263 |  |  | In-house | 
                    
                        | AQ0067TVP04A | Hilcorp Alaska, LLC | Monopod Platform | Klina, Joshua | Received comments from Hilcorp for technical review. | 2024|01|30 | 2024|01|30 |  |  |  |  |  |  | TVP Renewal |  | 365 |  | In Completeness Review 01/30/2024 | In-house | 
                    
                        | AQ0325MSS03A | US Ecology Alaska LLC (Formerly NRC Alaska) | Moose Creek Facility | Hasan, Ibnul | Waiting on MCF's response on increased PM PTE. | 2025|04|28 |  |  |  |  |  |  |  | Moose Creek Facility |  | 112 |  |  | In-house | 
                    
                        | AQ1328ORL01A | Mustang Holding LLC | Mustang Pad | Saengsudham, Peter | 4/7/25 Peter S. - Awaiting signed ORL. 
5/1/25 Peter S. - Currently under PL2 of annual limit of 500,000 gal (between the C9s and C15s) | 2024|02|23 | 2024|03|05 | 2024|02|26 |  | 2024|04|29 | 2024|05|29 |  |  | ORL | 18 AAC 50.225 | 71 |  | Public Notice End 05/29/2024 | In-house | 
                    
                        | AQ1564TVP01A | Oil Search Alaska, LLC, a Subsidiary of Santos Limited | Nanushuk Drillsite B | Saengsudham, Peter | 8/6/25 Peter S. - Form B4 received for EU ID 111. Reviewing and integrating into TVP. | 2024|02|12 | 2024|04|18 |  |  |  |  |  |  | Initial TVP |  | 531 |  | In Completeness Review 04/18/2024 | In-house | 
                    
                        | AQ1661TVP01A | Oil Search Alaska, LLC, a Subsidiary of Santos Limited | Nanushuk Operations Pad | Boyden, Zachary | 10/13/25 Response to Comments | 2023|11|10 |  |  |  | 2025|09|12 | 2025|10|13 |  |  | Nanushuk Ops Pad - Title V Permit |  | 388 |  | Public Notice End 10/13/2025 | In-house | 
                    
                        | AQ0923TVP03A | Hilcorp Alaska, LLC | Nikaitchuq Development | Faber, Scott | Pre-PN technical review | 2024|07|22 |  |  |  |  |  |  |  | TVP Renewal |  | 466 |  | Supervisor Review 11/19/2024 | In-house | 
                    
                        | AQ0110TVP05A | Golden Valley Electric Association | North Pole Power Plant | Leibert, Adam |  | 2024|10|03 |  |  |  |  |  |  |  | TVP Renewal |  | 393 |  |  | In-house | 
                    
                        | AQ0503TVP04A | Hilcorp Alaska, LLC | Northstar Production Facility (NOR) | Boyden, Zachary | Supervisor review 10/28/25 | 2024|12|05 | 2025|02|03 |  |  |  |  |  |  | TVP Renewal |  | 270 |  | Supervisor Review 10/28/2025 | In-house | 
                    
                        | AQ0083CPT08A | Nutrien US LLC (formerly Agrium US Inc.) | Nutrien Kenai Nitrogen Operations | Saengsudham, Peter | 9/5/2025 Peter S. - Initial review. 3rd PSD extension letter transmitted [CPT07 Revision 1]. | 2025|08|07 |  |  |  |  |  |  |  | Nutrien Kenai Nitrogen Operations |  | 85 | Zachary Boyden |  | In-house | 
                    
                        | AQ0180TVP05A | Kodiak Electric Association | Nyman Power Plant | Rea, Jonathon | EPA 45 day Review | 2023|12|14 | 2024|02|08 |  |  | 2025|07|22 | 2025|08|22 |  |  | TVP Renewal |  | 623 |  | EPA Review End 10/25/2025 | In-house | 
                    
                        | AQ1854MSS02A | Hilcorp North Slope, LLC | Omega Pad | Klina, Joshua |  | 2025|09|05 |  |  |  |  |  |  |  | Omega Pad |  | 56 |  |  | In-house | 
                    
                        | AQ0221TVP05A | Cordova Electric Cooperative | Orca Power Plant | Saengsudham, Peter | 9/8/25 Peter S. - First review | 2024|06|12 | 2024|07|26 |  |  |  |  |  |  | TV Renewal |  | 462 |  | Supervisor Review 09/08/2025 | In-house | 
                    
                        | AQ0186TVP04A | Hilcorp North Slope, LLC | PBU Central Power Station (CPS) | Faber, Scott | Supervisor review of response to comments | 2021|08|09 |  |  |  | 2024|03|08 | 2024|04|08 |  |  | TVP Renewal |  | 1544 |  | Supervisor Review 06/20/2024 | In-house | 
                    
                        | AQ0186TVP03P | Hilcorp North Slope, LLC | PBU Central Power Station (CPS) | Application, On Hold | Application to be withdrawn on or before the effective date of AQ0186TVP04 | 2017|11|03 |  |  |  |  |  |  |  | Update emissions unit inventory |  | 1502 |  |  | In-house | 
                    
                        | AQ1683TVP01A | Oil Search Alaska, LLC, a Subsidiary of Santos Limited | Pikka Development Nanushuk Processing Facility (NPF) | Klina, Joshua |  | 2024|12|19 |  |  |  |  |  |  |  | Nanushuk Processing Facility |  | 293 |  |  | In-house | 
                    
                        | AQ1683MSS01P | Oil Search Alaska, LLC, a Subsidiary of Santos Limited | Pikka Development Nanushuk Processing Facility (NPF) | Klina, Joshua |  | 2025|09|29 |  |  |  |  |  |  |  | Title I Permit Revision |  | 32 |  |  | In-house | 
                    
                        | AQ0084TVP05A | Hilcorp Alaska, LLC | Platform A | Leibert, Adam | Supervisor review complete. Next step: Pre-notice courtesy technical review by Applicant | 2023|12|14 | 2025|02|12 |  |  |  |  |  |  | TVP Renewal |  | 261 |  | In Completeness Review 02/12/2025 | In-house | 
                    
                        | AQ0085TVP05A | Hilcorp Alaska, LLC | Platform C, Middle Ground Shoal, Cook Inlet | Hasan, Ibnul |  | 2025|09|09 |  |  |  |  |  |  |  | TVP Renewal |  | 52 |  |  | In-house | 
                    
                        | AQ0486TVP04A | Providence Health System | Providence Alaska Medical Center | Faber, Scott | Supervisor review / EPA review | 2024|01|31 |  |  |  | 2025|09|08 | 2025|10|08 |  |  | TVP Renewal |  | 620 |  | Supervisor Review 10/09/2025 | In-house | 
                    
                        | AQ0274TVP03A | Hilcorp North Slope, LLC | Prudhoe Bay Operations Center / Main Construction Camp (PBOC/MCC) | Faber, Scott | EPA 45 day review | 2015|06|26 | 2015|06|26 |  |  | 2023|08|02 | 2023|09|01 |  |  | Renewal |  | 0 |  | EPA Review End 11/17/2025 | In-house | 
                    
                        | AQ0271TVP03A | Hilcorp North Slope, LLC | Prudhoe Seawater Treatment Plant | Application, On Hold | footnote issue | 2017|04|14 | 2017|04|14 |  |  |  |  |  |  | Renewal |  | 0 |  | In Completeness Review 04/14/2017 | In-house | 
                    
                        | AQ0072TVP05A | Alyeska Pipeline Service Company | PS #01, TAPS Pump Station | Jurado, Victoria | Permit writer assigned. NEXT STEP: application completeness review | 2025|07|23 | 2025|09|22 |  |  |  |  |  |  | TVP Renewal |  | 39 |  | In Completeness Review 09/22/2025 | In-house | 
                    
                        | AQ0074TVP05A | Alyeska Pipeline Service Company | PS #03, TAPS Pump Station | Faber, Scott | Preparing draft permit | 2025|07|29 | 2025|07|29 |  |  |  |  |  |  | TVP Renewal |  | 94 |  | In Completeness Review 07/29/2025 | In-house | 
                    
                        | AQ0075TVP05A | Alyeska Pipeline Service Company | PS #04, TAPS Pump Station | Hasan, Ibnul | Public Notice | 2025|07|29 |  |  |  | 2025|10|27 | 2025|11|27 |  |  | TVP Renewal |  | 81 |  | Public Notice End 11/27/2025 | In-house | 
                    
                        | AQ0290TVP04A | Teck Alaska, Inc. (Teck) | Red Dog Mine | Leibert, Adam |  | 2024|07|23 |  |  |  |  |  |  |  | TVP Renewal |  | 465 |  |  | In-house | 
                    
                        | AQ0290MSS16A | Teck Alaska, Inc. (Teck) | Red Dog Mine | Boyden, Zachary | 7/29/25 Awaiting TVP Renewal; Incorporate by Reference | 2025|05|19 |  |  |  |  |  |  |  | Rescind MI-3 & MD-11 Limits |  | 165 |  |  | In-house | 
                    
                        | AQ0232TVP05A | Trident Seafoods | Sand Point Facility | Klina, Joshua | Writing pre-PN draft. | 2024|09|30 | 2024|09|30 |  |  |  |  |  |  | TVP Renewal |  | 396 |  | In Completeness Review 09/30/2024 | In-house | 
                    
                        | AQ0170TVP03A | Hilcorp North Slope, LLC | Seawater Injection Plant East (SIPE) | Application, On Hold | PN draft ready for supervisor review.  No further work until the BACT full load issue is resolved. Footnote issue. | 2014|11|12 | 2014|11|12 |  | 2015|10|23 |  |  |  |  | Renewal |  | 0 |  | Supervisor Review 10/23/2015 | In-house | 
                    
                        | AQ0210TVP05A | Nome Joint Utility System | Snake River Power Plant | Klina, Joshua |  | 2024|12|23 |  |  |  |  |  |  |  | TVP Renewal |  | 312 |  |  | In-house | 
                    
                        | AQ1938MSS01A | Hilcorp Alaska, LLC | Spurr Platform | Jurado, Victoria | Initial assignment of permit writer and ambient demonstration reviewer. NEXT STEP: application completeness review. | 2025|07|02 | 2025|09|26 |  |  |  |  |  |  | Spartan 151 Drilling Project | 18 AAC 50.508(5),18 AAC 50.502(c)(2) | 18 | Zachary Boyden | In Completeness Review 09/26/2025 | In-house | 
                    
                        | AQ0319TVP05A | City of Saint Paul | St. Paul Power Plant | Saengsudham, Peter | 10/22/25 Peter S. - MSS application to avoid PSD and Title V in the works. Application anticipated around late November. | 2024|09|16 | 2024|11|05 |  |  |  |  |  |  | TVP Renewal |  | 322 |  | Supervisor Review 09/22/2025 | In-house | 
                    
                        | AQ0009TVP05A | Hilcorp Alaska, LLC | Steelhead Platform | Klina, Joshua | Updating draft after supervisor's review | 2024|07|24 | 2024|07|24 |  |  |  |  |  |  | TVP Renewal |  | 464 |  | Awaiting Applicant Response 11/08/2024 | In-house | 
                    
                        | AQ0009MSS05A | Hilcorp Alaska, LLC | Steelhead Platform | Application, On Hold | Permit on hold due to BACT footnote issue. | 2014|08|19 |  |  | 2014|09|11 |  |  |  |  | Revise and Rescind changes to BACT limit footnotes from MSS04 | 18 AAC 50.508(6) | 846 |  | Draft to Super. 09/11/2014 | In-house | 
                    
                        | AQ0059MSS01A | Hilcorp Alaska, LLC | Swanson River Field | Hasan, Ibnul |  | 2025|02|10 |  |  |  |  |  |  |  | Swanson River Field |  | 263 |  |  | In-house | 
                    
                        | AQ0059TVP04A | Hilcorp Alaska, LLC | Swanson River Field | Hasan, Ibnul |  | 2025|01|06 |  |  |  |  |  |  |  | TVP Renewal |  | 298 |  |  | In-house | 
                    
                        | AQ0058TVP03A | Hilcorp Alaska, LLC | Trading Bay | Application, On Hold | on hold pending EPA guidance for reclass of CISWI | 2018|02|16 |  |  |  |  |  |  |  | Initial |  | 79 |  |  | In-house | 
                    
                        | AQ0091TVP03A | Hilcorp Alaska, LLC | Tyonek Platform | Saengsudham, Peter | 5/13/25 Peter S. - Reviewing comments and drafting RTC. | 2013|09|27 | 2013|10|08 |  |  | 2025|04|11 | 2025|05|12 |  |  | TVP Renewal |  | 4023 |  | Public Notice End 05/12/2025 | In-house | 
                    
                        | AQ0091MSS03P | Hilcorp Alaska, LLC | Tyonek Platform | Saengsudham, Peter | 5/13/25 Peter S. - Reviewing comments and drafting RTC. | 2022|12|21 |  |  |  | 2025|04|11 | 2025|05|12 |  |  | Crane Replacement Project | 18 AAC 50.508(6) | 993 |  | Public Notice End 05/12/2025 | In-house | 
                    
                        | AQ0241TVP06A | Westward Seafoods, Inc. | Unalaska Seafood Processing Facility | Rea, Jonathon | Drafting permit | 2024|09|04 |  |  |  |  |  |  |  | TVP Renewal |  | 422 |  |  | In-house | 
                    
                        | AQ0316TVP03P | University of Alaska | University of Alaska Fairbanks Campus | Jones, David |  | 2024|07|30 |  |  |  |  |  |  |  | PM2.5 Nonattainment Area BACT Requirements |  | 458 |  |  | In-house | 
                    
                        | AQ0286TVP06A | Copper Valley Electric Association | Valdez Diesel Power Plant | Faber, Scott | Supervisor review | 2025|07|23 |  |  |  |  |  |  |  | TVP Renewal |  | 100 |  | Supervisor Review 10/02/2025 | In-house | 
                    
                        | AQ0082TVP03A | Alyeska Pipeline Service Company | Valdez Marine Terminal | Application, On Hold | On hold pending EPA reconsideration of 40 CFR 63 Subpart EEEE (SFaber, 7/5/23) | 2016|07|14 | 2016|07|14 |  |  | 2017|05|31 | 2017|06|30 |  |  | Renewal |  | 2532 |  | Supervisor Review 07/18/2017 | In-house | 
                    
                        | AQ0082TVP03A | Alyeska Pipeline Service Company | Valdez Marine Terminal | Application, On Hold | On hold pending EPA reconsideration of 40 CFR 63 Subpart EEEE (SFaber, 7/5/23) | 2019|02|06 |  |  |  |  |  |  |  |  |  | 1595 |  |  | In-house | 
                    
                        | AQ0082MSS04A | Alyeska Pipeline Service Company | Valdez Marine Terminal | Application, On Hold | On hold pending EPA reconsideration of 40 CFR 63 Subpart EEEE (SFaber, 7/5/23) | 2019|02|06 |  |  |  |  |  |  |  | Revisions to construction permit 082CP05 | 18 AAC 50.508(6) | 1595 |  |  | In-house | 
                    
                        | AQ1690MSS02A | Hilcorp North Slope, LLC | Z-PAD | Jurado, Victoria | Reviewing modeling protocol and drafting permit and modeling report. | 2025|07|25 | 2025|09|23 |  |  |  |  |  |  | Z-Pad T-130 Power Expansion |  | 38 | Brian Hirsch | In Completeness Review 09/23/2025 | In-house | 
                    
                        | AQ1865MSS01P | ABC | ZZZ |  |  | 1900|01|01 |  |  |  |  |  |  |  | Test - PTE Calc |  | 45959 |  |  | In-house |