Action Date |
Action |
Description |
DEC Staff |
8/8/1994 |
Site Visit |
RECN; |
Former Staff |
8/9/1994 |
Site Visit |
RECN; |
Former Staff |
8/10/1994 |
Site Visit |
RECN; |
Former Staff |
8/11/1994 |
Leaking Underground Storage Tank Release Confirmed - Petroleum |
LUST Site created in CSP for source area ID 76410 ADD; |
Former Staff |
8/11/1994 |
Site Added to Database |
|
Former Staff |
8/12/1994 |
Leaking Underground Storage Tank Cleanup Initiated - Petroleum |
LCAU; LUST corrective action underway. : LCAU date changed DB conversion |
Former Staff |
8/31/1994 |
Release Investigation |
RELR; |
Former Staff |
8/31/1994 |
Underground Storage Tank Site Characterization or Assessment |
SA1R; |
Former Staff |
8/31/1994 |
Update or Other Action |
NOR; |
Former Staff |
9/6/1995 |
Update or Other Action |
CAPR; Reviewed files. |
Former Staff |
11/20/1997 |
Update or Other Action |
ADEC sends Notification of Intent to Cost Recover Letter to Current Owner: GERIK INC DBA RIDE N SHINE |
Former Staff |
1/3/2001 |
Update or Other Action |
copy of 15 Nov 2000 Proposal given to Lynne Bush for review and comment. |
Lynne Bush |
1/3/2001 |
Update or Other Action |
Letter sent to Gerik regarding the 15 nov 2000 Proposal (oilRiskConsultants) sent to Linda Nuechterlein. Reminder to send a work plan for me to review. |
Lynne Bush |
2/28/2001 |
Update or Other Action |
E-mail to Brailey asking for revision to proposal, asking for revised WP. |
Lynne Bush |
12/21/2001 |
Update or Other Action |
Site transferred from Bush to Sundet |
Lynne Bush |
1/21/2003 |
Long Term Monitoring Established |
Long term monitoring established. |
Todd Blessing |
3/24/2003 |
Underground Storage Tank Site Characterization or Assessment |
Spring Site Assessment Workplan reviewed and approved by Rich Sundet. |
Scott Pexton |
4/1/2003 |
Update or Other Action |
UST Cleanup Grant #15218632 awarded to fund eligible project costs for workplan approved March 24, 2003. |
Scott Pexton |
9/4/2003 |
Update or Other Action |
Site Transferred from Sundet to Blessing |
Scott Pexton |
8/10/2004 |
Conditional Closure Approved |
Record of Decision submitted to Mike Gerik which outlines the Departments decision to grant a NFRAP contingent on the implementation of institutional controls and the signing of a notice of contamination which is due on October 8, 2004. |
Todd Blessing |
8/10/2004 |
Institutional Control Record Established |
Institutional controls established are as follows: 1. Any proposal to transport soil and/or groundwater off site requires ADEC approval in accordance with 18 AAC 75.325(i)
2. A groundwater monitor plan will be required that provides periodic monitoring to ensure contamination is declining and not migrating beyond the Ride n Shine and Holiday Station #5001 properties
3. An institutional control will be required that identifies the nature and extent of the contamination remaining on the site. It will also notify future owners/operators of the property of the environmental status of the site and any conditions that apply to future management of the contamination 4. The attached Notice of Environmental Contamination will need to be recorded (in the State of Alaska’s Recorders Office) as an institution control measure in accordance to 18 AAC 75.375(b)(3). In addition, a statement will be included in the DEC database regarding the environmental status of the site. |
Todd Blessing |
10/29/2004 |
Long Term Monitoring Established |
Approved of Restoration Science and Engineering's Long Term Groundwater Monitoring Plan to collect groundwater samples from MW-5 every two years. Collected groundwater samples will be analyzed for volatile organic compounds. |
Todd Blessing |
8/17/2005 |
Update or Other Action |
Mike Gerik has requested to remove the fuel from his underground storage tanks for a period of 5 years after which he would remove the tanks and attempt to receive a tank closure determination from the Department. The Department approved of the request as long as Mike does not sell his property and abides by the institutional controls established in the Record of Decision signed in August of 2004. |
Todd Blessing |
5/28/2008 |
Update or Other Action |
DEC staff issued a letter on May 28, 2008 requesting that Mr. Gerik conduct a groundwater monitoring event. DEC has not received any groundwater monitoring results since 2004. DEC approved of a long term groundwater monitoring plan in 2004. Groundwater monitoring was scheduled to be initiated in May 2005. |
Todd Blessing |
11/10/2008 |
Update or Other Action |
DEC staff reviewed RSE's "Ride n Shine 2008 Groundwater Monitoring Event" report, dated November 6, 2008. The report documented the sampling and analysis of groundwater collected from MW-5. Groundwater samples were analyzed for GRO, DRO, RRO, and VOCs according to DEC approved methods. No contaminants of concern were detected in samples that exceeded cleanup levels established in 18 AAC 75.345 Table C. |
Todd Blessing |
6/30/2011 |
Update or Other Action |
Transferred Project Manager to IC Unit
|
Bianca Reece |
11/9/2011 |
Institutional Control Compliance Review |
IC review conducted and tickler system updated. Will look on the Recorder's Office website to find deed notice. |
Evonne Reese |
8/1/2012 |
Institutional Control Update |
Found recorded deed notice on the Recorder's Office database and uploaded in the Attachments section of this database. |
Evonne Reese |
12/6/2012 |
Institutional Control Update |
An IC reminder letter was issued to the responsible party on this date (12/6/2012). |
Kristin Thompson |
12/18/2012 |
Institutional Control Update |
Telephone conversation with the responsible party. Another groundwater monitoring event will be scheduled by the consultant in the near future. |
Evonne Reese |
2/28/2013 |
Document, Report, or Work plan Review - other |
DEC staff reviewed Restoration Science & Engineering, LLC's "2013 Groundwater Monitoring Results". Groundwater samples MW-5 and MW-X were non-detect (ND) or below ADEC Table C cleanup levels. Concentrations of GRO (0.0867 mg/L), benzene (0.00190 mg/L), toluene (0.000970 mg/L), 2-butanone or MEK (0.0309 mg/L), and dichlorodifluoromethane (0.00112 mg/L) were detected below ADEC Table C cleanup levels. Tetrachloroethylene (PCE) was not detected. Investigate future groundwater sampling requirement removal.
|
Kristin Thompson |
2/28/2013 |
Institutional Control Update |
Future groundwater monitoring requirements have been removed. Other institutional controls will still apply. |
Evonne Reese |
5/16/2013 |
Long Term Monitoring Complete |
Administrative action added during a quality control check. |
Kristin Thompson |
9/3/2013 |
Institutional Control Update |
DEC received verification that the groundwater monitoring wells have been decommissioned. |
Evonne Reese |
3/2/2016 |
Institutional Control Update |
IC reminder letter was issued to the responsible party on this date. |
Nathan Maxwell |
6/8/2022 |
Institutional Control Record Removed |
On this date, ADEC Cleanup Complete determination was issued. ADEC found that soil was below ingestion and human health cleanup levels under 18 AAC 75.341 Method 2 Tables B1 and B2, and below cleanup levels for groundwater under 18 AAC 75.345, Table C. Institutional control record has been removed, standard conditions still apply. |
Brandi Tolsma |