Site Report: AKARNG Toksook Bay FSA

Site Name: AKARNG Toksook Bay FSA
Address: Sunny Street, Toksook Bay, AK 99637
File Number: 2450.38.001
Hazard ID: 2455
Status: Cleanup Complete
Staff: No Longer Assigned, 9074655229 dec.icunit@alaska.gov
Latitude: 60.531204
Longitude: -165.110443
Horizontal Datum:WGS84

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

Petroleum contamination at site.

Action Information

Action Date Action Description DEC Staff
2/21/1996 Site Added to Database Site added to database. Bill Wright
2/22/1996 Site Ranked Using the AHRM Site ranked. Bill Wright
3/11/1996 Update or Other Action Received January 1996 Site Investigation Report prepared by CH2MHill. Bill Wright
7/29/1997 Update or Other Action Received July 1997 Phase II Site Investigation Report, prepared by CH2MHill. Scott Pexton
9/9/1997 Site Ranked Using the AHRM Site reranked. Changed GW Usage Value from 0.8 to 1; and SW Usage Value from 0.2 to 0.5. Former score was 32. Scott Pexton
6/2/1999 Update or Other Action Received Draft Corrective Action Plan prepared by Clearwater Environmental, Inc. Scott Pexton
7/27/1999 Update or Other Action Letter sent with comments on draft corrective action plan Scott Pexton
8/5/1999 Cleanup Plan Approved Approved July 1999 corrective action plan prepared by Clearwater Environmental, Inc. to excavate approximately 130 cubic yards of petroleum contaminated soil for thermal treatment. Scott Pexton
7/20/2000 Update or Other Action ADEC approved request to transport petroleum-contamianted soil from Toksook Bay Federal Scout Armory to the Alaska Soil Recyling (ASR) facility in Anchorage. The soil will be barged to the Port of Anchorage by Brice, Inc. and then trucked to ASR. Scott Pexton
9/23/2000 Update or Other Action The Alaska Soil Recycling (ASR) faciltiy sent a letter to Clearwater Environmental that indicated that ASR received 188.08 tons of petroleum impacted soil from the Tooksok Bay site and that the soil had been treated. Post-treatment analysis indicated the treated soil met Level A cleanup levels. Scott Pexton
9/27/2000 Update or Other Action Received draft Interim Removal Action report, prepared by Clearwater Environment, Inc. Scott Pexton
7/26/2001 Update or Other Action Received Interim Removal Action Report (Volumes 1 and 2) prepared by Clearwater Environmental, Inc. A total of approximately 150 cubic yards of DRO contaminated soil was removed and stored in 55-gallon drums for transport to the Alaska Soil Recycling thermal treatment facility in Anchorage. Confirmation soil samples collected from the excavated areas were reported with DRO concentrations in five samples ranging from 4,800 to 12,000 mg/kg. Scott Pexton
7/31/2003 Update or Other Action ADEC sent letter to Norman Straub of Anchorage Army National Guard (AKARNG) with comments regarding Draft Alternative Cleanup Level Demonstration Project dated December, 2002. Beatrice Egbejimba
8/20/2003 Update or Other Action ADEC sent letter to Norman Straub of Anchorage Army National Guard (AKARNG) with approval of Alternative Cleanup Level Demonstration Project workplan dated August, 2003. Beatrice Egbejimba
4/12/2004 Update or Other Action File number assigned: 2450.38.001. Sarah Cunningham
10/19/2005 Update or Other Action Staff drafted a comment letter on the draft Alternative Cleanup Level report. There are significant issues with the report that need to be addressed. Debra Caillouet
4/8/2008 Exposure Tracking Model Ranking Initial ranking with ETM completed. Debra Caillouet
4/15/2008 Site Characterization Report Approved The report does provide additional characterization data for the Tununak FSA and is approved under 18 AAC 75.335. As explained in the comments on the draft of this report, the samples analyzed for total organic carbon are not representative of the soil where the contamination was detected. To be able to calculate an alternative cleanup level (ACL), the soil properties must be determined in an uncontaminated area that has similar soil properties. DEC can not approve an ACL based on this data. Debra Caillouet
2/3/2010 Meeting or Teleconference Held Staff participated in the Installation Action Plan meeting. Debra Caillouet
11/30/2010 Document, Report, or Work plan Review - other Staff reviewed and sent comment to the Alaska Army National Guard on the Draft Work Plan for Site Characterization at 21 Alaska Federal Scout Readiness Centers, November 2010, including the Site Specific Plans for Akiak, St. Mary’s and Tuntutuliak. Debra Caillouet
4/19/2011 Document, Report, or Work plan Review - other Draft Site Specific Work Plans, Fort Yukon, Kwethluk, Nightmute, Savoonga, and Toksook Bay, Federal Scout Armories, March 2011 Debra Caillouet
5/23/2011 Site Characterization Workplan Approved Final Work Plan for Site Characterization at 21 Alaska Federal Scout Readiness Centers, April 2011 approved. Debra Caillouet
4/5/2013 Document, Report, or Work plan Review - other Draft Toksook Bay Federal Scout Readiness Center, Data Gap Investigation Report, March 2013 Similar to other recent DGI reports, this report misapplies the EPH/VPH from multiple source areas. The report presents risk for the old diesel release based on data from the new Jet A release. Cleanup levels for each source area must be calculated and presented separately. Please have this report reviewed by the contractor and resubmitted with all data and appropriate use of the data. Debra Caillouet
5/3/2013 Site Characterization Report Approved Final Toksook Bay Federal Scout Readiness Center, Data Gap Investigation Report, April 2013 The report recommends alternative soil cleanup levels based on the aliphatic/aromatic split determined by the Washington EPH/VPH methods. The total DRO based on this is 10,962 mg/kg for the main source area and 10,621 mg/kg for the 2011 source area. These values are calculated from the ingestion cleanup levels of 4100 mg/kg DRO aromatic and 10,000 mg/kg DRO aliphatic. ADEC has no objection to the use of these cleanup levels. Confirmation sampling will be necessary to show all three levels,(total DRO by AK102, DRO Aromatic and DRO Aliphatic) are met for each site. Debra Caillouet
6/4/2013 Cleanup Level(s) Approved DRO Aliphatic 10,000 mg/kg, DRO Aromatic 4100 mg/kg, DRO AK102 10,962 mg/kg Debra Caillouet
6/10/2013 Exposure Tracking Model Ranking A new updated ranking with ETM has been completed for source area 73432 Spills/leaks. Debra Caillouet
3/5/2014 Document, Report, or Work plan Review - other The draft Remedial Action Plan was reviewed. Debra Caillouet
5/1/2014 Cleanup Plan Approved Petroleum contaminated soil will be excavated this summer. Debra Caillouet
1/12/2015 Document, Report, or Work plan Review - other Draft Remedial Action Report, Federal Scout Readiness Center, Toksook Bay, Alaska January 9, 2015 Debra Caillouet
2/9/2015 Cleanup Complete Determination Issued Removal Action in 2014 met ROD cleanup goals. Debra Caillouet

Contaminant Information

Name Level Description Media Comments
DRO Between Method 2 Migration to Groundwater and Human Health/Ingestion/Inhalation Soil

Control Type

Type Details
No ICs Required

Requirements

Description Details
Advance approval required to transport soil or groundwater off-site.
Movement or use of contaminated material (including on site) in a manner that results in a violation of the water quality standards is prohibited (18 AAC 70)

No associated sites were found.