Site Report: ADOTPF - Peger Road Maintenance Bldg


Site Name: ADOTPF - Peger Road Maintenance Bldg
Address: 2301 Peger Road, Fairbanks, AK 99701
File Number: 102.26.120
Hazard ID: 24637
Status: Active
Staff: Jim Fish, 9074512117 james.fish@alaska.gov
Latitude: 64.826290
Longitude: -147.770070
Horizontal Datum:

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

Maintenance Building also known as M & O bldg. Is separate area from State Equipment Fleet (SEF) Shop.

Action Information

Action Date Action Description DEC Staff
3/1/1991 Underground Storage Tank Site Characterization or Assessment SA1; Basketfield: Tighteness tested 10,000 gal. diesel tank at Maintainence Bldg. failed test due to electrical-type coupling that were leaking. * Not Assigned
12/7/1992 Release Investigation RELR; Basketfield: Reviewed Shannon & Wilson 8-26-92 report "UST Site Assessment and Closure., NTP-1, 2301 Peger Rd, FBKS, AK". * Not Assigned
1/8/1993 Update or Other Action CORR; Basketfield: Sent letter to Jim Little, ADOT Northern Region, discussing Shannon & Wilson's site assessment and further actions at the site. * Not Assigned
2/23/1993 Update or Other Action RPL2; Peterson sent PRP-CS Database Notification Letter to RP requesting update and more environmental information concerning contaminated site. DOT/Clarke Milne will respond in month or two, but as of this complete date have rec'd no response! * Not Assigned
9/21/1995 Underground Storage Tank Site Characterization or Assessment 10,000-gallon & 3,000-gallon diesel UST removed with soil and grd water impact. * Not Assigned
9/21/1995 Leaking Underground Storage Tank Cleanup Initiated - Petroleum entered by JC * Not Assigned
5/24/1996 Update or Other Action UPD; USTs removed 9/95. Approx. 240 cu. yds. contam. soil thermally treated. Approx. 700 cu. yds. contam. soil still remain under/around dispenser area. Passive air venting system for soils installed. 5/96 quart. monitoring grd. water, Benzene @ MW 7 still high. Other MWs frozen @ 14 ft. bgs, no samples taken. * Not Assigned
8/19/1997 Leaking Underground Storage Tank Corrective Action Underway Still high Benzene levels. (3) MWs sampled three times '96, twice '97, last sampling date 8/19/97. Upgradient MW=2.79 ppb Benzene. Two downgradient MWs 118 ppb & 10,400 ppb Benzene. Passive soil venting system indicates PID reading 280 ppm as of 8/97. Grd water movement carrying contam towards Davis Rd. poss moved beyond ADOT boundary. Lack of funding to continue cleanup * Not Assigned
9/2/1998 Leaking Underground Storage Tank Release Confirmed - Petroleum LUST Site created in CSP for source area ID 78100 (Added by zt_qryAddLustStatus) * Not Assigned
9/2/1998 Site Added to Database * Not Assigned
1/28/2004 Update or Other Action Transferred DEC staff lead from John Carnahan Cynthia Pring-Ham
7/7/2008 Exposure Tracking Model Ranking Intitial Ranking Complete for Source Area: 78100 (Autogenerated Action)
8/7/2012 Update or Other Action Site transferred to Jim Fish. Janice Wiegers
6/28/2013 Site Characterization Report Approved Recieved Vapor intrusion Assessment FY12 Report - SSD systems functioning in Materials Lab and Maintenance & Operations Building; see Peger Rd Facility (102.38.098). Jim Fish
9/3/2015 Update or Other Action Met with ADOT Design staff & Environ Analyst for discussion of plans to construct Traffic Operation Center at the current M&O Building; discussed groundwater & soil gas contamination, and suggested installation of SSD & SVE system during construction. Jim Fish
3/15/2016 Meeting or Teleconference Held Met with Design Alaska engineer and ADOT to discuss possible SVE system installation as part of M&O Building addition construction. Jim Fish
11/29/2016 Update or Other Action Received an Environmental Assessment and Work Plan for excavation sampling and stockpile management for the proposed ADOT&PF Traffic Operations Center, as a building addition to the M&O Building. Jim Fish
3/3/2017 Update or Other Action Met with consultant/designer for SSD system installation regarding environmental work plan review (prepared by subcontractor). DEC will provide comments for soil handling and disposal consideration; anticipate coordination with EPA RCRA program. Jim Fish
5/9/2017 Update or Other Action Final sampling and analysis plan received and approved today. Jim Fish
7/25/2017 Offsite Soil or Groundwater Disposal Approved Approx. 20 CU yd of DRO-contaminated soils approved for transport to OIT Jim Fish

Contaminant Information

Name Level Description Media Comments

Control Type

Type Details

Requirements

Description Details

There are no documents for this site report.

Missing Location Data

Because the GIS location data for this site has not been entered, we cannot direct you to its position on the map. Click "Continue" to proceed to the Contaminated Sites Web Map or "Close" to return to the site report.
Continue     Close