Division of Spill Prevention and Response

Breadcrumbs

Site Report: Haines-Fairbanks Pipeline MP 544 - Timber Pump Station


Site Name: Haines-Fairbanks Pipeline MP 544 - Timber Pump Station
Address: Richardson Highway Mile 276, Timber Pump Station, Delta Junction, AK 99737
File Number: 900.38.001
Hazard ID: 4481
Status: Active
Staff: Danielle Duncan, 9074655207 danielle.duncan@alaska.gov
Latitude: 64.189194
Longitude: -145.892417
Horizontal Datum:NAD83


We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.


Problems/Comments

Previous investigations suggest that soil and groundwater contamination exceeding ADEC cleanup levels is limited to the Burn Pit area. 4/10/17: The zone of soil contamination has been adequately delineated. The highest concentration of Diesel range organics (DRO) measured at the burn pit was 12,000 mg/kg at 3-4 feet below ground surface (bgs). Contamination exists near the surface and extends to groundwater which is at about 22 feet bgs. The estimated volume of unsaturated contaminated soil is 4,000 cubic yards (y3). Below the ground water table, an additional 5,800 y3 of contaminated soil exists. The contamination within the smear zone appears to conflict with groundwater flow direction. There was no product in the groundwater but some had sheens (MW8 and MW11) and/or odor (MW6, MW8, MW11). Two groundwater monitoring wells located within the burn pit and southwest of the burn pit (MW3 and MW11) had COCs above ADEC cleanup levels.



Action Information

Action Date Action Description DEC Staff
7/17/2007 Site Characterization Workplan Approved Workplan approved this date. Anne Marie Palmieri
10/22/2007 Site Added to Database Site added to the database. Mitzi Read
4/29/2008 Site Characterization Workplan Approved USACE ROST workplan approved this date. Anne Marie Palmieri
9/4/2008 Site Characterization Report Approved 2007 fieldwork report approved. Petroleum contamination was found in the soil and groundwater at the site. Additional investigation is needed. Anne Marie Palmieri
3/5/2009 Exposure Tracking Model Ranking Initial ranking with ETM completed for source area id: 75468 name: auto-generated pm edit Haines-Fairbanks Pipeline MP 543 Anne Marie Palmieri
9/29/2010 CERCLA SI 2008 ROST SI report approved this date. 40 probes were installed. One soil sample was collected which showed significant contamination -- DRO 17,000 mg/kg, GRO 740 mg/kg, PAHs, VOCs, and arsenic. Groundwater wells were samples with exceedences noted for DRO of 13 mg/L and GRO 9 mg/L and PAHs. Additional investigation needed in 2010-11. Anne Marie Palmieri
2/4/2013 Update or Other Action project manager changed from Palmieri to Morris. Anne Marie Palmieri
8/25/2015 Meeting or Teleconference Held The ADEC and USACE participated in a scoping meeting regarding this site, however the project has been delayed because right of entry was not granted by the landowner. Jessica Morris
12/17/2015 Update or Other Action Staff changed to Danielle Duncan and hard file transferred to the Juneau office. Kristin Brown
3/14/2016 Update or Other Action The RP is developing the scope of work for Timber Pump Station. They are proposing to remove everything outside of the building that may hold petroleum (pipes, tanks, valves, etc.) and remove any other potential contaminant sources except for the burn pit. Pipelines inside the building would be emptied and decommissioned. The burn pit requires additional investigation. Borings and monitoring wells would be installed as part of the planned effort to determine the nature and extent of contamination from the burn pit. Danielle Duncan
6/14/2016 Report or Workplan Review - Other Rec'd the Draft Work Plan Environmental Investigation Timber Pump Station this date. Danielle Duncan
6/23/2016 Site Characterization Workplan Approved Approved the Draft Work Plan Environmental Investigation Timber Pump Station this date. The objective of the work plan is to delineate the extent of soil and groundwater contamination at and around the burn pit only. The work plan outlines the following: Sampling of the 5 groundwater monitoring wells on site, advance 20 soil borings into the ground using Direct Push Technology - Soil samples will be collected from the borings and field screened using a PID, 6 of the borings will be completed as groundwater monitoring wells and sampled. Danielle Duncan
6/24/2016 Update or Other Action Requested that testing for PCP in soil and groundwater be added to the work plan via email. Danielle Duncan
8/2/2016 Site Visit Joint site visit by ADEC, DNR, USACE, and FES. There are some buildings (SHPPO eligible) containing old piping, tanks, and other equipment that will be removed in the future (contract has been awarded and work should commence next summer). The tanks may have lead based paint. The current scope of work is to investigate the burn pit only. Danielle Duncan
8/15/2016 Report or Workplan Review - Other Provided responses to comments via email this date. Danielle Duncan
8/26/2016 Site Characterization Workplan Approved Approved the final work plan this date - no changes were made to the draft plan. Danielle Duncan
9/27/2016 Meeting or Teleconference Held Meeting with the USACE and their consultant. There is a drinking water well on site that the USACE would like to decommission - I let them know to contact the DEC drinking water program on that as the well has nothing to do with historical contamination. Additionally, there are septic system injection wells in the area that also need decommissioning and I directed the USACE to discuss this with the water program and they already had plans to discuss with EPA. Danielle Duncan
10/24/2016 Update or Other Action The brush clearing has been completed and the contaminated soil removal action will occur in summer/fall 2017. Danielle Duncan
1/23/2017 Update or Other Action Provided comments on the draft environmental investigation. One noted comment is that the lab MDLs and LOQs are greater than the cleanup levels for soil – either use an alternative laboratory or an alternative analysis method. Drinking water methods tend to be more sensitive and Method 5030 is also acceptable. ADEC agrees that there appears to be elevated and naturally occurring chromium in the soils – chromium VI results are generally ND with a few low level exceptions. The ADEC also agrees that arsenic is likewise naturally occurring. Danielle Duncan
1/25/2017 Update or Other Action Provided comments on the draft work plan for Scottie Creek, Birch Lake, and Timber Pump Station. Danielle Duncan
2/16/2017 Update or Other Action Accepted responses to my comments this date. Danielle Duncan
3/16/2017 Site Characterization Report Approved Approved the Final Report Environmental Investigation Timber Pump Station this date. The burn pit only was investigated. The zone of soil contamination has been adequately delineated. The highest concentration of DRO measured at the burn pit was 12,000 mg/kg at 3-4 feet below ground surface (bgs). Contamination exists near the surface and extends to groundwater which is at about 22 feet bgs. The estimated volume of unsaturated contaminated soil is 4,000 cubic yards (y3). Below the ground water table, an additional 5,800 y3 of contaminated soil exists. The contamination within the smear zone appears to conflict with groundwater flow direction. There was no product in the groundwater but some had sheens (MW8 and MW11) and/or odor (MW6, MW8, MW11). Two groundwater monitoring wells located within the burn pit and southwest of the burn pit (MW3 and MW11) had COCs above ADEC cleanup levels. Danielle Duncan
3/16/2017 Exposure Tracking Model Ranking A new updated ranking with ETM has been completed for source area 75468 auto-generated pm edit Haines-Fairbanks Pipeline MP 543. Danielle Duncan
3/23/2017 Update or Other Action Approved the work plan this date for removal of tanks, piping, etc. and some petroleum contaminated soil. Danielle Duncan
3/28/2017 Report or Workplan Review - Other Approved the UIC work plan this date. Danielle Duncan
7/6/2017 Update or Other Action Bristol is currently performing the removal work at Timber and have removed the two ASTs, the two USTs, and a portion of the buried pipelines. They have not found significant amounts of soil containing petroleum contamination at this point. This work may be completed by July 14th or sooner. Danielle Duncan

Contaminant Information

Name Level Description Media Comments


Control Type

Type Details


Requirements

Description Details

There are no documents for this site report.