Action Date |
Action |
Description |
DEC Staff |
11/1/1992 |
Leaking Underground Storage Tank Release Confirmed - Petroleum |
LUST Site created in CSP for source area ID 76182 ADD; |
Former Staff |
11/1/1992 |
Site Added to Database |
|
Former Staff |
2/8/1993 |
Update or Other Action |
NOR; Gibler: Failed TTT not accounted for to DEC. NORL sent by Gibler to Michael Tinker, Reginoal Envir. Coordinator for ADOT/PF. |
Former Staff |
2/23/1993 |
Update or Other Action |
RPL2; Peterson sent PRP-CS Database Notification Letter to RP requesting update and more environmental information concerning contaminated site. DOT/Clarke Milne will respond in month or two, but as of this complete date have rec'd no response! |
Former Staff |
10/11/1993 |
Leaking Underground Storage Tank Cleanup Initiated - Petroleum |
LCAU; Kalu - reviewed and concurred with remedial action plan for both stockpile and contaminated. |
Former Staff |
6/6/1994 |
Update or Other Action |
CORR; Wingerter sent letter informing RP of their financial liability under new ADEC cost recovery policy. State is authorized, under Section 9003(h) of the Resource Conservation and Recovery Act to take action on this LUST facility. |
Former Staff |
10/13/1995 |
Update or Other Action |
Correspondence from NORTECH states that detectable benzene and toluene, below the MCLs. A 1992 sampling event by EPA 602 indicated ND for HC analyses. |
Former Staff |
1/22/1999 |
Underground Storage Tank Site Characterization or Assessment |
Additional tanks removed (Tank ID no. 2) and impacted soil was identified and stockpiled. |
Former Staff |
8/15/2001 |
Update or Other Action |
JBC - reviewed and approved a stockpile closure report. Soils to be spread at their convenience as appropriate. |
John Carnahan |
1/28/2004 |
Update or Other Action |
Transferred DEC staff lead from John Carnahan |
Cynthia Pring-Ham |
12/1/2004 |
Document, Report, or Work plan Review - other |
Report received 2/28/03, Contractor recommends further well water monitoring and instalation of a monitoring well. |
Kim DeRuyter |
9/12/2005 |
Document, Report, or Work plan Review - other |
August 19, 2005 report, Results of Water Well Sampling, ADOT&PF Eagle Maintenance Station received 9-7-05, contains well water results from July, 2005. No analytes were detected above labortatoy practical quantitation limits. This is the 4th clean sample from the DW well since sampling began in 2002, no analytes have been detected above the PQL. |
Kim DeRuyter |
3/13/2006 |
Update or Other Action |
Brief file review. Update GIS using TopoZone Pro. Update problem statement and legal description. |
Kim DeRuyter |
5/25/2006 |
Document, Report, or Work plan Review - other |
DW well sample results received from Analytica - all results were non-detect. |
Kim DeRuyter |
1/11/2007 |
Institutional Control Record Established |
A Notice of Environmental Contamination will be listed on the ADEC Contaminated Sites Database identifying the nature and extent of contamination remaining on site.
In accordance with 18 AAC 78.274(b), the transport of soil or groundwater from this site requires ADEC review and approval prior to any transport. |
Kim DeRuyter |
1/11/2007 |
Conditional Closure Approved |
In 1993, four soil borings were drilled near the former gasoline tank and dispenser island. The results indicated that GRO and DRO contamination extended 25 to 40 feet bgs. Benzene was detected at 0.304 mg/kg at 39 feet; GRO at 6,580 mg/kg at 19 feet, and DRO at 2,670 mg/kg at 17 feet. |
Kim DeRuyter |
12/20/2011 |
Update or Other Action |
Site management staff changed to IC Unit.
|
Evonne Reese |
12/20/2011 |
Institutional Control Compliance Review |
IC review conducted, need to find a copy of the closure document, reminder system updated. |
Evonne Reese |
8/12/2014 |
Institutional Control Record Removed |
The conditions at this site meet the 2009 closure policy, therefore ICs can be removed. The default requirement of no offsite transport of soil or groundwater will still apply. In accordance with 18 AAC 78.276(f)(2), ADEC may require additional site assessment, monitoring, remediation, and/or other necessary actions at this facility should new information become available that indicates contamination at this site may pose a threat to human health or the environment. A letter to ADOT was sent this date that documents this decision.
|
Evonne Reese |