Action Date |
Action |
Description |
DEC Staff |
7/15/1991 |
Update or Other Action |
(Old R:Base Action Code = SA1 - Phase I Site Assessment (General)). PAHs, heavy metals, and DRPH found at elevated levels. Building 601 Assessment (General)). Contaminated floor drain and drum storage area. |
Don Gibler |
7/15/1992 |
Preliminary Assessment Approved |
Phase I Site Assessment (General)). |
Don Gibler |
10/9/1992 |
Interim Removal Action Approved |
(Old R:Base Action Code = SA1R - Phase I SA Review (CS/LUST)). Building 601 Interim action required - discontinue use of floor drain, cap with removable seal, place drums on impermeable liner, place leaking drums in overdrums and dispose of at H.W. facility, follow 18.AAC 68. Do R.I. and prepare C.A.P. ASAP. |
Don Gibler |
10/9/1992 |
Update or Other Action |
Received the Environmental Compliance Investigation Report. |
Former Staff |
5/12/1993 |
Site Added to Database |
Lead, DRPH and PAH contamination. |
Former Staff |
5/15/1993 |
Site Ranked Using the AHRM |
Initial ranking. |
Former Staff |
6/29/1994 |
Update or Other Action |
(Old R:Base Action Code = RPL2 - Site Information Request Letter). Sent PRP-CS Database Notification Letter to RP requesting update and more environmental information concerning contaminated site. RP/Jackie for FAA Anchorage office responded to let me know she will be sending information on the facilities soon. Received information on 8-8-94. |
Jeff Peterson |
8/8/1994 |
Site Ranked Using the AHRM |
Reranked (Based on DDT contaminated soil in addition to CERCLA sources). |
Former Staff |
11/27/1995 |
Update or Other Action |
Summary of meeting on 11/8/1995 and proposed corrective action approaches. |
Kent Patrick-Riley |
1/17/1996 |
Update or Other Action |
Received Underground Fuel Storage Tank (UST) Decommissioning Assessment Report for tank: 9-C-5 at Building 601. |
Former Staff |
7/29/1996 |
Update or Other Action |
Received the Site Cleanup and Investigation Report documenting sampling at Buildings 300 and 601. |
Former Staff |
7/8/2002 |
Update or Other Action |
Adjusted priority and site location to reflect data provided in reports. |
Elizabeth Stergiou |
7/9/2002 |
Site Number Identifier Changed |
Workplan changed from 09 to 01 to reflect no presence of hazardous substances above cleanup levels. Sequence Number changed from 04 to 01. |
Elizabeth Stergiou |
7/16/2002 |
Update or Other Action |
Rec'd Memorandum from FAA consultant titled "Product Baildown Tests and Groundwater Sampling Near Yukon River at FAA Tanana Site, Alaska". |
Eileen Olson |
9/18/2002 |
Update or Other Action |
Sent letter requesting groundwater monitoring for all existing wells on site, monitoring of the in-situ system, and monitoring of the landspread soil, with a schedule of monitoring to be submitted by March 31, 2003 and the monitoring to be complete by June 30, 2003. |
Elizabeth Stergiou |
9/19/2002 |
Update or Other Action |
Sent general letter requesting the following documents be submitted by 10/1/02: status of groundwater monitoring and all groundwater monitoring reports since February 12, 1997, status of the in-situ remediation system and associated soil sand groundwater and all associated reports since February 12, 1997, status of the land spread treatment cell and associated soils and groundwater and all associated reports since February 12, 1997, and status of all contaminated sites at the station. |
Elizabeth Stergiou |
11/21/2005 |
Update or Other Action |
Building 601 UST 9-C-5: Closed. Tank 9-C-5, a 1000 gallon diesel tank, was removed along with 25 cubic yards of petroleum-contaminated soil. Six confirmation samples were collected and showed that the petroleum hydrocarbon concentrations were below default cleanup levels. In the Site Cleanup and Investigation Report, dated 1996, the removal of 1/2 cubic yard of petroleum-contaminated soil is documents to have occurred on the east side of the shed. Field screening results showed that all of the petroleum hydrocarbons in that area were removed. In these areas, ADEC has determined that no further action is required. Closure approval letter dated November 21, 2005. |
Anne Marie Palmieri |
11/21/2005 |
Cleanup Complete Determination Issued |
November 21, 2005 Closure letter
|
Anne Marie Palmieri |
8/31/2006 |
Site Characterization Workplan Approved |
Incinerator: site characterization workplan approved this date. Fieldwork is set to begin 9/7/06. |
Anne Marie Palmieri |
4/24/2007 |
Site Characterization Report Approved |
The Final Site Investigation Report Federal Aviation Administration Former Incinerator Area Near Building 300, Fort Yukon, Alaska , March 14, 2007 was approved. |
Debra Caillouet |
4/24/2007 |
Site Closure Approved |
Based on the Final Site Investigation Report Federal Aviation Administration Former Incinerator Area Near Building 300, Fort Yukon, Alaska , March 14, 2007, closure of the incinerator was approved. There are three additional sites within the Quarters facility requiring action and three requiring documentation of ICs to achieve conditional closure. |
Debra Caillouet |
4/10/2009 |
Site Added to Database |
A new site has been added to the database |
Mitzi Read |
9/24/2025 |
Update or Other Action |
Database actions reviewed and corrected. Historic actions are preserved in the file. |
AJ Hytry |