April 10, 2012 (final update) -- Spill responders from Alaska Clean Seas (ACS), Penco and CCI used heavy equipment, such as loaders, excavators, trimmers, skid-steers, hydraulic hammers and snow machines with trailers, to remove the spill material from the heaviest contaminated zones. Hand tools were used to recover drilling mud from the areas of lightest contamination. Cleanup crews removed approximately 6,286 cubic yards of spilled material from the snow-covered tundra. In addition, 2,402 cubic yards of down-hole material and 116,928 gallons of water-based mud and freshwater from the steam units were recovered from the drilling pad during the initial response.
Repsol hired a surveying contractor to assist in calculating the off-pad impacted area and the volume of the material released to the tundra. The contractor estimated that 21,114 bbls of down-hole material were released to the tundra during the initial blow-out. In addition, they calculated the total impacted area as 23.75 acres. An area of 16.76 acres of lightly-misted material was determined to be unrecoverable, and no cleanup occurred in this zone.
On April 1, 2012, a group from the Kuukpikmiut Subsistence Oversight Panel, Inc. (KSOP) and from the village of Nuiqsut visited the site to see how the cleanup had progressed. The group was satisfied with the work that had been done and said that they did not believe that any further cleanup needed to be performed.
On April 5, 2012, the final site inspection team, composed of representatives from the North Slope Borough, KSOP, ADEC, ADNR and Repsol, made the final site inspection. The team agreed that no further cleanup actions were required.
ADEC's field monitors were demobilized from the site on April 6, 2012.
>>Full Chronology
>>Final Situation Report
|