Plan Review Fees (18 AAC 72.955)
| (1) Domestic wastewater system with a daily peak capacity measurement, in gpd, 1 of |
Fee (in dollars) |
| (A) 0-500 |
270 |
| (B) 501-1,500 |
340 |
| (C) 1,501-2,500 |
360 |
| (D) 2,501 - 15,000 |
730 |
| (E) 15,001 -50,000 |
1,200 |
| (F) 50,001 - 100,000 |
2,370 |
| (G) 100,001 - 250,000 |
2,960 |
| (H) 250,001 and over |
3,510 |
| (2) Modification to an existing or approved domestic wastewater system that increases daily peak capacity by |
| (A) less than 20% |
20% of the fee applicable to the pre-modification daily peak capacity measurement |
| (B) at least 20% but less than 50% |
a percentage of the fee applicable to the pre-modification daily peak capacity measurement, with the amount of that percentage to be equal to the percentage increase in capacity |
| (C) 50% or more |
100% of the fee applicable to the pre-modification daily peak capacity measurement |
| (3) Waivers or modifications under 18 AAC 72.060 |
| (A) Any number of waivers or modifications that the department considers under one plan review under this chapter for a single-family home or a duplex |
300, regardless of number of waivers or modifications |
| (B) Each waiver or modification that the department considers under one plan review under this chapter for a project other than a single-family home or duplex |
250 per waiver or modification |
| |
| (4) Nondomestic wastewater systems for discharges that do not include stormwater runoff |
| 1. Passive treatment 2
|
| (i) for one or two treatment methods |
440 |
| (ii) for each additional passive treatment method above two |
90 |
| 2. Complex treatment 3 |
| (i) for one or two treatment methods |
940 |
| (ii) for each additional treatment method above two |
190 |
| (5) Nondomestic wastewater systems for discharges that include stormwater runoff for engineering plans required by 18 AAC 72.600(a) for projects |
| (A) of less than one acre |
100 |
| (B) that are at least one acre but less than five acres |
300 |
| (C) that are at least five acres but less than 20 acres |
600 |
| (D) that are 20 acres or more |
1,000 |
| (6) Domestic and nondomestic sewer main extensions or replacements |
| (A) up to 1,000 feet |
310 |
| (B) for each additional 1,000 feet, or fraction of that amount, over the first 1,000 feet |
160 |
1If the domestic wastewater system is a waste stabilization pond that discharges seasonally, the department will consider the gpd measurement, for purposes of determining the amount of the fee, to be the total discharge into the stabilization pond in a calendar year, divided by 365.
2“Passive treatment” means physical treatment with no chemical additions; “passive treatment” includes check dams, sediment lagoons, ion exchange water softeners, cartridge filters, and ultraviolet disinfection.
3“Complex treatment” means biological, chemical, or physical treatment with chemical additives.
|
|