| Action Date |
Action |
Description |
DEC Staff |
| 5/31/1990 |
Preliminary Assessment Approved |
America North Inc., hired by Wilson, summarized that large amounts of waste oil was drained into large pits on property, free oil has been reported near surface excavation on Eyak property. No near surface contamination exists on Wilson property indicating off-site source of groundwater contamination. |
Former Staff |
| 9/20/1990 |
Preliminary Assessment Approved |
Ecology and Environment sent in report. Priority assessment: no further investigative action under CERCLA is recommended because no direct human targets are suspected to be affected by contaminant migration from site. Subsurface contamination is present at site and is likely to be heavy metals, VOCs, and PAH (polyaromatic hydrocarbons). Contaminated groundwater could discharge to Eyak Lake a water supply for Cordova. |
Former Staff |
| 10/25/1990 |
Site Added to Database |
Solvents, waste oils, greases, creosote and potential heavy metals/pesticides. |
Former Staff |
| 8/13/1991 |
Site Ranked Using the AHRM |
New information from Jane Tonkin caused site to get reranked. |
Former Staff |
| 6/15/1993 |
Site Characterization Workplan Approved |
BP submitted the "Cordova Roundhouse Site Assessment Workplan" dated June 1993, prepared by Montgomery Watson. |
John Halverson |
| 12/20/1993 |
Update or Other Action |
BP submitted the "Cordova Roundhouse Site Assessment Report - Draft" dated December 1993, by Montgomery Watson. The report concluded that an area of ~30,000 square feet was contaminated with a heavy petroleum product from depths around six to twelve feet below ground surface, which extended below the shallow water table. A localized area of solvent contamination was found in the NE corner of the site. Groundwater impacts were localized with the soil contamination. |
John Halverson |
| 1/27/1994 |
Preliminary Assessment Approved |
(Old R:Base Action Code = SA1 - Phase I Site Assessment (General)). Review of draft site assessment report conducted by district and regional staff. |
Former Staff |
| 2/4/1994 |
Update or Other Action |
BP submitted a "Cordova Roundhouse Qualitative Human Health Risk Assessment" report dated, January 1994, by Montgomery Watson. It concluded that risk to humans was well below the EPA criteria of a hazard index of 1 or carcinogenic risk of 1E-6. |
John Halverson |
| 2/15/1994 |
Update or Other Action |
(Old R:Base Action Code = CORR - Correspondence (General)). ADEC requested cleanup plan. |
Former Staff |
| 4/18/1994 |
Update or Other Action |
BP submitted a "Proposed Corrective Action Program for the Cordova Roundhouse" dated April 1994. It summarized the site history, existing assessment data and possible cleanup alternatives. Data gaps and details still needed to be addressed. |
John Halverson |
| 4/18/1994 |
Update or Other Action |
(Old R:Base Action Code = CORR - Correspondence (General)). |
Former Staff |
| 5/3/1994 |
Update or Other Action |
(Old R:Base Action Code = RAPR - Remedial Action Plan Review (CS)). Several remediation methods are being considered. |
Former Staff |
| 2/10/1995 |
Update or Other Action |
Corps of Engineers submitted a "Site Operations and Ownership History Report - Cordova Railroad Yard Formerly Used Defense Site (FUDS) Cordova, Alaska" dated December 8, 1994, by DPRA Inc. The report was prepared under the Corps FUDS program as part of the Potentially Responsible Party (PRP) project to evaluated Department of Defense responsibilities for cleanup. It is a detailed site history report. |
John Halverson |
| 8/31/1995 |
Site Characterization Report Approved |
BP submitted the "Cordova Roundhouse Spring 1995 Field Activities Summary of Field Results" dated August 1995, by Montgomery Watson. The report describes additional site characterization including installation of soil borings and monitoring wells, sampling and analysis, an aquifer test. It further defined the extent of residual product and groundwater contamination. |
John Halverson |
| 3/26/1996 |
Cleanup Level(s) Approved |
ADEC approved the soil cleanup levels of 2190 mg/kg DRO and 2,000 mg/kg RR0. |
John Halverson |
| 5/16/1996 |
Cleanup Plan Approved |
(Old R:Base Action Code = RAPA - Remedial Action Plan Approval). Reviewed and approved a GW Treatment System Plan. |
Mike Krieber |
| 5/16/1996 |
Update or Other Action |
(Old R:Base Action Code = RAU - Remedial Actions Underway (General)). Remedial action underway. |
John Halverson |
| 6/1/1996 |
Update or Other Action |
ADEC approved BP's "Soil Remediation Plan (Revised) for Cordova Roundhouse Cleanup" dated May 1996. |
John Halverson |
| 6/24/1997 |
Update or Other Action |
ADEC sent landowners at the site letters documenting the no further investigation or cleanup is necessary. |
John Halverson |
| 7/10/1997 |
Update or Other Action |
BP submitted preliminary laboratory data from confirmation samples at the limits of site excavations and thermally treated soil. Approximately 17,500 cubic yards of petroleum contaminated soil and 1,500 cubic yards of other oily debris were excavated and treated or disposed off off-site. |
John Halverson |
| 9/15/1997 |
Update or Other Action |
BP submitted a "Cordova Roundhouse Groundwater Monitoring Report" dated September 1997. It documented that groundwater at the site met applicable cleanup levels and recommended the wells be properly decommissioned. |
John Halverson |
| 8/27/2002 |
Site Closure Approved |
Based on a review of all site data, soil and groundwater at the site meet approved cleanup levels. No final report was submitted, however, all cleanup work was completed during 1997. No further investigation or cleanup are planned unless new information becomes available the demonstrates a need for further work. |
John Halverson |