Site Report: Kukak Bay Refueling Site - Katmai
We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.
Problems/Comments
Exxon used this site as a temporary refueling station during the cleanup of the Exxon Valdez oil spill cleanup. The site was deactivated by Exxon in late 1989. A site assessment was performed in 1990, two areas of contamination were found the highest concentration of TPH was 30,600 mg/kg. Exxon returned to the site in 1991 and 1992 to do further excavation.
Action Information
Contaminant Information
Name |
Level Description |
Media |
Comments |
Control Type
Requirements
There are no documents for this site report.
No associated sites were found.