Action Date |
Action |
Description |
DEC Staff |
10/24/1991 |
Site Ranked Using the AHRM |
Initial ranking. |
Mehrdad Nadem |
12/2/1991 |
Site Characterization Workplan Approved |
(Old R:Base Action Code = SA1R - Phase I SA Review (CS/LUST)). A site assessment plan was submitted to the department for approval. PRP - Frontier Equipment Co., 2393 Adams Street, Fairbanks 99701. |
Mehrdad Nadem |
4/16/1992 |
Update or Other Action |
Site sampling and analysis plan submitted to ADEC by AG Midland Co. for Frontier Equipment Co. |
Mehrdad Nadem |
4/26/1993 |
Update or Other Action |
(Old R:Base Action Code = SA2R - Phase II SA Review (CS)). Site Assessment Progress Report submitted by A.G. Midland CO., Inc. and received by ADEC on this date. Soil samples indicate TPH up to 5000 mg/Kg and Arsenic up to 15 mg/Kg Borings advanced throughout pad. No base map and sample location map to identify exact location of samples. All sample submitted to laboratory for TPH analysis exceeded ADEC cleanup criteria. Contamination appears to extent to the base of the gravel pad. Seven areas of contamination were identified. No water samples were collected. |
Mehrdad Nadem |
1/6/1995 |
Site Number Identifier Changed |
Old region = 40. |
Scott Rose |
10/15/1997 |
Update or Other Action |
Environmental Investigation report submitted by Oil Spill Technology, Inc dated and recieved on this date. Visual inspection of area indicate potential areas of contamination around fueling area and the fuel storage area as well as 15 minor soil stains around perimeter of gravel pad. 44 test holes, three to six feet deep, were screened with PID. The 8 highest were sent to the lab for analysis. Lab results indicate DRO up to 4220 mg/Kg, GRO up to 341 mg/Kg, and total BTEX up to 59.2 mg/Kg. |
Grant Lidren |
1/10/2000 |
Update or Other Action |
File forwarded to Fairbanks office for review. |
Jim Frechione |
5/1/2002 |
Update or Other Action |
Workplan for additional site characterization in area of "aboveground fuel storage" submitted for review. |
Renee Evans |
5/4/2002 |
Update or Other Action |
Action sheet from Kay Rawlings - regarding not to proceed with cost recovery at this time, see file for hard copy. |
Jim Frechione |
5/6/2002 |
Update or Other Action |
Letter dated May 5, 2002 review of: Workplan for Investigation and Remediation at the "Old Frontier Pad" - Prudhoe Bay, AK "In summary, the fuel product and containment area removal task should be completed prior to site characterization activities. The site characterization activity shall identify the nature and extent of contamination in the fuel storage area and that information shall be submitted to the ADEC for review prior to determining additional work under the Site Cleanup Agreement and Release document." |
Jim Frechione |
8/21/2003 |
Update or Other Action |
Letter from FESCO attorney (Susan Reeves) regarding difficulties gaining access to the site from the lessee (Bernie Karl). FESCO has reportedly spent $81,362 to date on their $200,000 obligation. They propose to submit the balance ($118,638) to the State (DNR or DEC) in order to fulfill the commitment in the 2001 agreement. AG Cam Leonard will draft a response proposing FESCO submit $$ to DNR. DEC could then work with DNR to ensure the site investigation continues. |
Jim Frechione |
11/13/2006 |
Update or Other Action |
Remaining funds were submitted to DNR and are being held in case lease is terminated. |
Bill O'Connell |
11/20/2006 |
Meeting or Teleconference Held |
ADEC (Frechione) and ADNR (Menefee; Fogels and Menge) met with Bernie Karl to discuss cleanup of the Frontier Equipment Pad. It was agreed that the fuel storage area to be addressed under the FESCO agreement should continue. There is $118,000 remaining from the agreement to be used for cleanup. All parties agreed that the tanks need to be moved; the soil sampled and impacted soil excavated and treated. Mr Karl indicated he could do the work cheaper than others and wanted to discuss how this could be accomplished. ADNR will evaluate contractual requirements prior to a decision. |
Jim Frechione |
12/1/2006 |
Update or Other Action |
Letter sent from ADNR to Bernie Karl detailing the agreement made during the 11/20/06 meeting. The activities noted above; tank removal, cleaning, excavation and treatment of contaminated soils are the focus of the agreement and are considered Phase I of the cleanup. Phase I will focus on the former fuel storage area and additional characterization will proceed as needed following Phase I. |
Bill O'Connell |
1/14/2008 |
GIS Position Updated |
Position verified |
Grant Lidren |
1/14/2008 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed. |
Grant Lidren |
9/10/2009 |
Site Visit |
Site visit on 9/2/09. Moderate to heavy sheen noted on surface water along the northern and western pad edges when sediments were disturbed. |
Bill O'Connell |
1/6/2010 |
Meeting or Teleconference Held |
Meeting with ADNR and Mr. Bernie Karl. Mr. Karl is interested in moving forward with investigation/remediation at the site and ADEC will work with ADNR and DOL to prepare a COBC outlining Mr. Karl's responsibilities at the site. Mr. Karl will be hiring a consultant with the objective of investigating contamination at the former drum storage area, removing contaminated soil from former fuel storage areas and installing a vertical barrier liner to inhibit ongoing transport of contaminants off site to the surrounding tundra. |
Bill O'Connell |
1/22/2010 |
Meeting or Teleconference Held |
Meeting today with Bernie Karl and associates. Topics discussed include the technical approach to characterizing the former drum storage area, excavation of soil from former fuel storage areas and the placement of a vertical barrier liner in areas where contamination is migrating to the tundra. |
Bill O'Connell |
7/22/2010 |
Update or Other Action |
Compliance Order by Consent from ADEC and Memorandum of Agreement from ADNR mailed to Frontier Equipment. |
Bill O'Connell |
8/3/2010 |
Meeting or Teleconference Held |
Teleconference between Frontier Equipment, ADNR, DOL, Weston Solutions, and ADEC to discuss COBC and MOA. The results of the teleconference are that Frontier has 30 days to submit a CAP (by Sept. 2) and based on the schedule recommended by Weston, the CAP time frame will be adjusted as necessary. |
Bill O'Connell |
9/2/2010 |
Update or Other Action |
Deadline for submission of CAP extended to October 4, 2010. |
Bill O'Connell |
10/4/2010 |
Update or Other Action |
Draft Corrective Action Plan submitted on this date. |
Bill O'Connell |
12/2/2010 |
Cleanup Plan Approved |
ADEC submitted comments to the Draft Corrective Action Plan for Frontier Base Camp which were addressed in the Final, submitted December 2, 2010. Corrective action at the site will include the installation of a vertical barrier liner (VBL) around the perimeter of the pad, excavation and landfarming of approximately 35,000 cy of contaminated soil from 5 areas, and additional characterization at locations identified during previous investigations. The VBL will be installed in Spring 2011 prior to commencement of excavation activities. The five planned excavation areas A-E correspond with areas found to be contaminated during previous investigations. Excavated soil will be landfarmed on the eastern portion of the pad and then used as backfill in open excavations once it has been treated and DRO concentrations are below 500 mg/kg. It is anticipated that excavation will proceed to the maximum recommended depth of 0.5 feet below tundra grade after which composite confirmation samples will be collected from the floor and sidewalls. It is also anticipated that it will take 2-3 years to complete the excavation and landfarming effort. |
Bill O'Connell |
12/30/2010 |
Update or Other Action |
Revised COBC emailed to Mr. Karl. |
Bill O'Connell |
5/12/2011 |
Update or Other Action |
Based on schedule proposed by Alaska Frontier Construction, the date for the installation of the vertical barrier liner has been extended from June 30, 2011 to December 30, 2011. The liner will be installed in two phases beginning in June 2011. Excavation and landfarming are anticipated to begin in 2012 after equipment is removed from the pad. |
Bill O'Connell |
3/13/2013 |
Document, Report, or Work plan Review - other |
Reviewed 2012 Frontier Pad Field Summary Report. Activities conducted in 2012 included excavating and landfarming soil from Area E, excavating test pits at Area E to evaluate the extent of contamination, and segregating and landfarming soil generated during the installation of the vertical barrier liner. Area E is located to the east of the Former Fueling area and Former Fuel Storage Area. Surface soil in portions of Area E to a depth of approximately 1 foot bgs was determined to be clean and was stockpiled for sampling and potential reuse as backfill. Contaminated soil was then excavated to the pad/tundra interface at approximately 5 feet bgs resulting in the removal of approximately 1,250 cy of contaminated soil which was landfarmed just to the west on top of Area D. Confirmation samples contained DRO up to 5,640 mg/kg and GRO up to 885 mg/kg in a sidewall sample from 18 inches bgs. Bottom samples contained DRO up to 1,960 mg/kg at 5 feet bgs. In an effort to evaluate the extent of contamination at Area E, three test pits were excavated to the north, south, and east of Area E. Test pit samples indicated DRO contamination above the Method One cleanup level of 500 mg/kg was present to the east of Area E and to a lesser extent to the north. Samples collected from landfarmed soil contained DRO up to 1,610 mg/kg. |
Bill O'Connell |
5/22/2013 |
Meeting or Teleconference Held |
Teleconference with consultants and contractors to discuss scope of work for 2013 landfarming activities. |
Bill O'Connell |
12/17/2013 |
Document, Report, or Work plan Review - other |
Reviewed 2013 Frontier Pad Field Summary Report. The objective of the 2013 work was to delineate and excavate contaminated soil from the east side of Area E, located near the Former Fueling Area and to evaluate remedial progress at the landfarm area known as Cell 2. Cell 1 was sampled in 2012 and did not contain contaminants above cleanup levels. Samples from Cell 2 collected in July 2013 contained DRO up to 1,140 mg/kg, so landfarm tilling continued in July and August. The landfarm was sampled again in August 2013 and DRO was detected up to 825 mg/kg. Due to the slow attenuation of soils during 2013, no additional excavation was conducted in Area E. |
Bill O'Connell |
2/26/2015 |
Document, Report, or Work plan Review - other |
Reviewed 2014 Frontier Pad Field Summary Report. Cell #2 was reportedly tilled during July and August 2014 and soil samples were collected at the end of July. DRO was detected in the three samples at concentrations ranging from 661 mg/kg to 784 mg/kg. |
Bill O'Connell |
4/2/2015 |
Meeting or Teleconference Held |
Meeting today with Bernie Karl to discuss progress at Frontier pad |
Bill O'Connell |
9/2/2015 |
Site Visit |
Site visit with ADNR. |
Bill O'Connell |
4/4/2016 |
Document, Report, or Work plan Review - other |
Soil samples collected from Cell 2 in September 2015 contained DRO ranging from 277 mg/kg to 428 mg/kg, all below the cleanup level of 500 mg/kg. |
Bill O'Connell |
6/9/2016 |
Document, Report, or Work plan Review - other |
Reviewed Pilot Study Work Plan for Area E. Prior to beginning remediation activities, test trenches will be excavated to the pad/tundra interface along the boundaries of Area E to confirm the area that requires remediating. Trenches will be placed every 100 feet along the boundary of Area E and soil samples will be collected from one-foot intervals for field screening using a PID with approximately one sample per trench submitted for laboratory analysis for DRO, GRO, RRO, and BTEX. Following the additional characterization, baseline soil samples will be collected on 50-foot centers across the area proposed for remediation and the five soil samples with the highest PID results will be submitted for laboratory analysis for DRO, GRO, RRO, BTEX, and PAHs. The objective of the baseline sampling is to document contaminant concentrations in Area E prior to remediation. Surface water and sediment samples will be collected from three locations, one along each of the North, East, and South sides of the pad and shovel sheen testing will be conducted at 25 foot intervals where surface water is present adjacent to the pad. Surface water and sediment samples will be analyzed for DRO, GRO, RRO, BTEX, and PAHs. Remediation at Area E will be conducted via in-situ landfarming using a Rockwheel attachment that will till the soil from the surface to the 6 inches below tundra grade. Tilling will occur weekly from June to September. Progress soil samples will be collected at the end of each season in the same manner as the baseline samples however progress soil samples will consist of soil increments from one foot intervals composited into a single sample. Debris removal will be conducted on an ongoing basis based on availability of backhauls. Final confirmation sampling frequency will be determined at a later date |
Bill O'Connell |
7/6/2016 |
Site Visit |
S. Schlichting conducted a joint site visit with DNR staff, P. Burns and S. Willison of Division of Land Mining and Water out of Fairbanks and T. DeRuyter, Northern Alaska Region Manager for Prevention, Preparedness and Response, SPAR. Advance notice was provided to the responsible party and environmental consultant.
The site visit is detailed a site visit report found in the site electronic file and provided to the RP and his consultant. The visit consisted of a walkthrough of the property including the pad and the surrounding surface water to inspect source areas of contamination previously identified in the March 15, 2016 Corrective Action Plan and determine whether site preparation had occurred for the work outlined in the May 23, 2016 Area Pilot Study Work Plan, scheduled for implementation in June of 2016. Based on the site inspection, contamination from the pad appears to have impacted adjacent surface water and sediments based on presence of sheens along much of the pad's perimeter, and no work has commenced in Area E in accordance with the approved work plan for the pilot study.
|
Sally Schlichting |
8/2/2016 |
Update or Other Action |
Email from Bernie Karl indicating that corrective action would not be conducted in 2016. |
Bill O'Connell |
9/9/2016 |
Enforcement Action |
Notice of Violation issued to Mr. Bernie Karl for failure to comply with regulatory requirements for site cleanup and investigation. |
Bill O'Connell |