Action Date |
Action |
Description |
DEC Staff |
3/1/1991 |
Update or Other Action |
(Old R:Base Action Code = SA1R - Phase I SA Review (CS/LUST)). Thomas - draft. |
Ben Thomas |
6/10/1991 |
Site Added to Database |
|
Former Staff |
6/1/1992 |
Update or Other Action |
(Old R:Base Action Code = SA2 - Phase II Site Assessment (General)). This report was combined with SA1 and was done by Ecology and Environment for the AK COE on behalf of the Army. |
Former Staff |
6/1/1992 |
Preliminary Assessment Approved |
(Old R:Base Action Code = SA1 - Phase I Site Assessment (General)). RPCON for ADCOE on behalf of Army is Ecology and Environment. Report based on 8 USTs removed in 1991 and sampling surrounding area where 24 USTs removed in 1990. |
Former Staff |
8/26/1992 |
Site Ranked Using the AHRM |
Initial ranking. |
Former Staff |
8/27/1992 |
Update or Other Action |
(Old R:Base Action Code = NOR - Notice of Release Letter (LUST)). Sent letter to acknowledge release(s). Request investigation schedule. |
Ben Thomas |
10/1/1992 |
Site Ranked Using the AHRM |
Reranked. |
Former Staff |
1/25/1993 |
Update or Other Action |
(Old R:Base Action Code = RELR - Release Investigation Review (LUST)). Reviewed and referred to Gibler from QA/QC review, as it appeared technically questionable. GW impacted and contamination widespread. All 8 MWs had at least one contaminant which exceeded state or federal MCLs. Corrected re-review sent 3-1-93. |
Eleanor Hung |
3/12/1993 |
Update or Other Action |
(Old R:Base Action Code = SI - Site Investigation). Closure report by Brown and Root/Nortech for Tank #356 at Birch Hill. ADEC concurs. Closure OK. DRO at 12ppm is the only detected analyte. Report information for #355 recommends removal and/or treatment of contaminated soils. ADEC concurs. Soils levels at bottom of excavation exceed 2,000 ppm TPH after removal of approximately 200 yards. BTEX and GRO not tested for. |
Ronan Short |
5/20/1993 |
Meeting or Teleconference Held |
C. Fosbrook to draft letter addressing separation of site from 2-party Agreement. Bottom of hill will be takenover by OU-3. Contaminated soil will be washed to reduce lead content prior to incineration, pipeline to be drained (as removal unfunded), sampling for metals in GW by low volume pump(unfiltered) to be tried this summer. |
Eleanor Hung |
6/14/1993 |
Update or Other Action |
(Old R:Base Action Code = RECN - Site Reconnaissance (CS)). ADEC Thomas and Hung inspected site. |
Ben Thomas |
7/29/1993 |
Update or Other Action |
(Old R:Base Action Code = SA2 - Phase II Site Assessment (General)). Final Release Investigation Received. Staff member is Short as of 12/1/93. Site Assessment Received 9/1/93. |
Ronan Short |
9/1/1993 |
Leaking Underground Storage Tank Corrective Action Underway |
Removed last two of the 34 USTs summer of 1993. Remedial investigation to determine presence and extent of petroleum based contaminants in soil and ground water in progress. Propose contaminated soil be thermally treated after lead reduced by washing. |
Eleanor Hung |
10/11/1993 |
Site Ranked Using the AHRM |
Reranked using new modification to AHRM. |
Former Staff |
1/12/1994 |
Meeting or Teleconference Held |
Removed 2 remaining USTs #355 and #356 9/93. Found one more UST. Will be removed summer 1994. All piping north of road to be removed 1994 and south of road will remain due to wetland issue. Pipes have broken due to freeze-thaw conditions over the years. Will screen areas where pipe breaks are with OVM and take samples with high readings. Site closure fall 1994. |
Eleanor Hung |
5/16/1994 |
Update or Other Action |
(Old R:Base Action Code = RPL2 - Site Information Request Letter). Sent PRP-CS Database Notification Letter to Cristal Fosbrook requesting update/confirmation of information concerning the contaminated site. |
Jeff Peterson |
9/26/1994 |
Update or Other Action |
(Old R:Base Action Code = SI - Site Investigation). Workplan for Release Investigation at site of former tank #355. Area also includes former pipelines and CVP #369. DRO, GRO and BTEX in excess of MCLs were found in previous investigation at adjacent sites (E&E 1992). |
Ronan Short |
10/26/1994 |
Site Characterization Report Approved |
(Old R:Base Action Code = SI - Site Investigation). Final SI for Birch Hill Tanks. Report submitted for files. |
Ronan Short |
3/30/1995 |
Update or Other Action |
(Old R:Base Action Code = RELR - Release Investigation Review (LUST)). Draft Release Investigation report received this date. Analyses indicate site meets matrix level D levels. One GW sample of 2,000ppb TRPH at AP5847 is attributable to tank farm gathering lines and not tank #355 and its piping. |
Ronan Short |
6/6/1995 |
Update or Other Action |
(Old R:Base Action Code = RAPR - Remedial Action Plan Review (CS)). RA Plan recommends further remedial actions at some locations at this site. Former UST location 346 had highest GRO of approximately 2,000ppm after excavation. 40 yards removed. |
Ronan Short |
7/3/1995 |
Update or Other Action |
(Old R:Base Action Code = RELR - Release Investigation Review (LUST)). E&E RI Report received closure. Site meets matrix level D. Contamination in well AP5847=(2,000ppb) TRPH not attributable to UST site. Well is 350 feet SW of site. Tank closure recommended. ADEC concurs. |
Ronan Short |
4/22/1996 |
Update or Other Action |
RI Report and CAP. All piping and valve pits removed by Fall 1995. ACL proposed for site visitors/industrial scenario. No compounds exceed 1x10-5 ACL. |
Ronan Short |
6/1/1996 |
Update or Other Action |
(Old R:Base Action Code = RELR - Release Investigation Review (LUST)). Release Investigation Report / Corrective Action Plan, Abandoned Birch Hill Underground Storage Tank Farm Sites, Fort Wainwright, Alaska, Facility ID Number 0-001314, Contract Number DACA85-93-D-0009, Delivery Order Number 19, received 7/5/1996. |
Ronan Short |
6/1/1996 |
Cleanup Plan Approved |
(Old R:Base Action Code = CAPA - Corrective Action Plan). Release Investigation Report / Corrective Action Plan, Abandoned Birch Hill Underground Storage Tank Farm Sites, Fort Wainwright, Alaska, Facility ID Number 0-001314, Contract Number DACA85-93-D-0009, Delivery Order Number 19, received 7/5/1996. |
Ronan Short |
8/14/1996 |
Update or Other Action |
Insert pages for Table 4-10, RIR/CAP for the Birch Hill Abandoned UST Sites, OU-1, Fort Wainwright, Alaska, received 8/19/1996. |
Ronan Short |
3/26/1997 |
Update or Other Action |
Site updated by Shannon and Wilson, based on the Army Defense Site Environmental Restoration Tracking System Worksheet dated 11/8/96. The worksheet indicates 25 ppb benzene in groundwater and 100 ppm benzene in soil. |
S&W |
4/9/1999 |
Record of Decision |
This site was closed in the OU5 ROD on 4/9/99. Any contamination remaining at this site is being addressed as part of the OU3 Birch Hill Tank Farm. Please see OU3 Birch Hill Tank Farm for future actions and updates. |
Sharon Richmond |
12/12/2001 |
Institutional Control Record Established |
1. All organizations conducting activities on United States Army Alaska (USARAK) controlled land are responsible for complying with established institutional controls (ICs). ICs are administrative, procedural, and regulatory measures to control human access to and usage of property. They are applicable to all known or suspected contaminated sites where contamination has been left in place. 2. These controls have been established to implement the selected remedial actions agreed upon by the U.S. Army (Army), the U.S. Environmental Protection Agency (USEPA), and the Alaska Department of Environmental Conservation (ADEC) in accordance with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) as amended by the Superfund Amendment Reauthorization Act (SARA). These controls also apply to remedial actions agreed upon under Two-Party Compliance Agreements. These agreements are concluded between USARAK and ADEC and apply to petroleum/oil/lubricants- (POL) contaminated sites. 3. ICs such as limitations on access, water use, excavations, and property transfers will supplement engineering controls as appropriate for short-term and long-term management to prevent or limit human and environmental exposure to hazardous substances, pollutants, or contaminants. Specific ICs include, among other things: limitations on the depth and location of excavations, prohibition of or restrictions on well drilling and use of ground water, requirements for worker use of personal protective equipment, site monitoring, and prohibition of certain land uses, types of vehicles, etc. 4. Organizational units, tenants, and support/contractor organizations must obtain an Excavation Clearance Request (ECR) for all soil disturbing activities impacting soils six inches or more below the ground surface. The review process for approval of an ECR begins with the identification of the current status (known or suspected hazardous waste site or “clean” site) of a work location. ECR’s for work in known or suspected hazardous waste sites: a. will include specific limitations and controls on such work; b. will include specific IC procedures, and notification, monitoring, reporting, and stop work requirements; c. may include procedures for management, characterization, and disposal of any soil or groundwater encountered or removed; d. will identify “project managers” for both the unit/contractor requesting the work and DPW Environment Resources. 5. The DPW project manager will conduct on-site inspections of each work site (at which ICs apply) to determine continued compliance with the terms and conditions of the approved ECR. DPW has the authority to revoke ECR approval if the specified terms and conditions are not being met. ECR forms are available at the Customer Service Desks at: a. Building 730 at Fort Richardson; b. Building 3015 at Fort Wainwright; c. Building 605 at Fort Greely. 6. USARAK has negotiated (with USEPA and/or ADEC) decision documents and/or Records of Decision (RODs) that mandate the implementation of ICs USARAK Directorate of Public Works, Environmental Resources Department (PWE), maintains copies of all decision documents and RODs requiring ICs in its real property files. PWE provides regularly updated post maps showing all areas affected by ICs. These maps can easily be accessed by using an approved intranet mapping interface application. Copies of these maps will be available to each directorate, activity, and tenant organization. To ensure the effectiveness of ICs, all organizational units and tenant activities will be informed on an annual basis of ICs on contaminated soils and groundwater in effect near their facilities. 7. ICs are enforceable by the U.S. Environmental Protection Agency (USEPA) and the Alaska Department of Environmental Conservation (ADEC). Failure to comply with an IC mandated in a decision document or ROD will violate the USARAK Federal Facility Agreement and may result in stipulated fines and penalties. This does not include the costs of corrective actions required due to violation of an established IC. |
Sharon Richmond |
4/10/2003 |
Update or Other Action |
Staff attended teleconference with Army, Corps of Engineers, and their contractors to discuss the Petroleum, Oil, and Lubricants (POL) Source Removal- Work Plan, Sampling Analysis Plan, and Environmental Protection Plan. The project entailed removing an abandoned fuel pipeline which runs from the tank farm to the airfield approximately 13,000 feet. Sections of the line have been removed in the past. The plan is to remove all remaining pipe except under roads, railroad tracks, airfields, and through areas with active remedial systems. It is estimated that 250 cubic yard of contaminated soil will be removed. Contaminated soils will be segregated and taken to OIT for treatment. Staff sent a comment letter on 4/8/03. |
Patrice Buck |
7/16/2003 |
Meeting or Teleconference Held |
Fort Wainwright Restoration Advisory Board held it's last meeting on July16, 2003. |
Patrice Buck |
3/16/2015 |
Site Reopened |
The Army has decided to perform a Remedial Investigation |
Debra Caillouet |
3/16/2015 |
Document, Report, or Work plan Review - other |
Draft Work Plan Environmental Investigations various Sites, Fort Wainwright Alaska January 2015 was reviewed. This this work plan addresses 17 sites at Fort Wainwright. The plan was written in UFP-QAPP but has major deficiencies requiring a complete rewrite of the document. Detailed comment was sent to the Army. |
Debra Caillouet |
6/15/2015 |
Update or Other Action |
The Army was sent a review of the response to comment that was provided for the comments sent in March on the draft work plan. There are remaining concerns for the Conceptual Site Model, site specific DQO's and providing site history. |
Debra Caillouet |
8/26/2015 |
Update or Other Action |
Transfer to Fairbanks |
Susan Carberry |
1/13/2016 |
Meeting or Teleconference Held |
A Restoration Project Managers (RPM) meeting was held in Anchorage Alaska. The upcoming 2016 site restoration work and monitoring was discussed. Fort Wainwright institutional control policies and procedures were also discussed. |
Dennis Shepard |
12/13/2016 |
Meeting or Teleconference Held |
A two day Federal Facilities Agreement (FFA) and Stakeholders meeting was held on December 13 & 14, 2016. The main focus of the meeting was to develop a site discovery and site intake process that would satisfy requirements of the Fort Wainwright FFA, RCRA Permit, and two party agreements. The Army, EPA and DEC committed to a flowchart of the preliminary source evaluation process. Timelines were established for scoping a land use control implementation plan (LUCIP) and developing a contracting schedule for Fort Wainwright contaminated site investigations and remedial actions. Seven sites were proposed for inclusion into the FFA (three party agreement) by the Army and the RPMs documented the assignment of the regulatory path for these sites using a newly developed and agreed to signature form. |
Dennis Shepard |
1/1/2017 |
Document, Report, or Work plan Review - other |
DEC approved the 2015 Annual Institutional Controls Report, Fort Wainwright, Alaska (August 2016). |
Dennis Shepard |
11/29/2017 |
Update or Other Action |
DEC approved the Final Data Gap Analysis Report, Birch Hill UST Farm. The report indicates that approximately 555 cubic yards (CY) of contaminated soil remain at the former UST346 location and excavation of this residual petroleum soil contamination is recommended. The estimate may be low due to incomplete delineation.
Localized “hot spot” locations (UST-371, UST-372, and UST-381) upgradient of the former FEP
and Milepost (MP 2.7 & 3.0) sites have been delineated laterally and vertically. Contamination at these areas is localized, does not appear to be migrating, and is not an identified source of contamination for the MP sites or area along Birch Hill Loop Road. Further delineation of soil contamination, cleanup and soil removal actions are ongoing and conducted under Site: Fort Wainwright (OU-3) FE Pipeline MP2.7/3.0 FTWW-084, Hazard ID 1673, File Number 108.38.002.02. |
Dennis Shepard |
11/29/2017 |
Cleanup Complete Determination Issued |
This site was closed in the OU5 ROD on 4/9/99. For additional information, see the CS database for Fort Wainwright - Abandoned Birch Hill Tanks SP-7, Hazard ID 24218. Further delineation of soil contamination, cleanup and soil removal actions are ongoing and conducted under Site: Fort Wainwright (OU-3) FE Pipeline MP2.7/3.0 FTWW-084, Hazard ID 1673, File Number 108.38.002.02. |
Dennis Shepard |