Action Date |
Action |
Description |
DEC Staff |
2/2/1992 |
Site Added to Database |
Petroleum contamination. |
Former Staff |
9/8/1992 |
Update or Other Action |
(Old R:Base Action Code = RPL2 - Site Information Request Letter). ADEC sent PRP-CS Database Notification letter to RP requesting update and more environmental information concerning contaminated site. Jim Levine\COE called 10-5-92 and responded by returning updated DECRPTs. |
Jeff Peterson |
3/16/1993 |
Meeting or Teleconference Held |
Pre-construction conference at Corps of Engineers Fairbanks Resident Engineer Office. |
Bob Couch |
9/10/1993 |
Update or Other Action |
(Old R:Base Action Code = CORR - Correspondence (General)). 9/10/93 letter sent responding to 9/1/93 letter that proposed remediation levels. |
Bob Couch |
10/25/1993 |
Update or Other Action |
Scope of work received. |
Bob Couch |
11/19/1993 |
Update or Other Action |
(Old R:Base Action Code = CORR - Correspondence (General)). Letter commented on public notice dated October 22, 1993, and stated that ADEC had not agreed on alternate clean-up levels that had been discussed, and that are included in the Corps project documents. |
Bob Couch |
3/1/1994 |
Update or Other Action |
(Old R:Base Action Code = RAPR - Remedial Action Plan Review (CS)). Work Plan and Quality Control Plan were submitted 3/1/94, and on 3/7/94 learned that the Corps had returned both plans to the Contractor for revision. |
Bob Couch |
4/1/1994 |
Update or Other Action |
(Old R:Base Action Code = RAPR - Remedial Action Plan Review (CS)). Received Contractor's revised Work Plan and Quality Control Plan. |
Bob Couch |
8/16/1994 |
Site Ranked Using the AHRM |
Initial ranking. |
Former Staff |
3/18/1995 |
Update or Other Action |
(Old R:Base Action Code = RARR - Remedial Action Report Review (CS)). Completed review of Draft Remedial Action Report Addendum - 1995 Work Season. Upon receipt of final report, this site should be evaluated for possible closure. |
Tamar Stephens |
5/11/1995 |
Update or Other Action |
(Old R:Base Action Code = RD - Remedial Design). Final Remedial Action Report and supporting documentation received. |
Tamar Stephens |
9/11/1995 |
Meeting or Teleconference Held |
(Old R:Base Action Code = PUBP - Public Participation)). Clint Adler attended public meeting in Nome in which USACE informed public of work completed, and upcoming work on Nome sites. |
Clint Adler |
1/18/1996 |
Meeting or Teleconference Held |
ADEC staff, Tamar Stephens and Clint Adler, met with USACE representatives, James Baker, Robert Haviland, Gus Olson, John Jacobson, Curtis King, Ron Pflum, and IT representative Keith Walker, for update on status of Nome sites. 2 biovents are in active use. Significant problems with logistics of getting to site; safety issues in working adjacent to a slough where barrels and contamination found. |
Tamar Stephens |
3/6/1996 |
Update or Other Action |
(Old R:Base Action Code = RAPR - Remedial Action Plan Review (CS)). Received "Draft Remedial Action Report", Addendum 1, 1995 Work Season. |
Tamar Stephens |
6/28/1996 |
Update or Other Action |
Supporting Documentation, Davidson's Landing Site, Addendum 1, 1995 Work Season, Part I, Analytical Data, and Part II, Supplemental Documentation, Nome Area Sites Project, Seward Peninsula, Alaska, Contract Number DACW1-89-D0133, Delivery Order Number 15, received 8/5/1996. |
Tamar Stephens |
6/28/1996 |
Update or Other Action |
(Old R:Base Action Code = RA - Remedial Action). Remedial Action Report, Davidson's Landing Site, Addendum 1 1995 Work Season, Nome Area Sites Project, Seward Peninsula, Alaska, Contract Number DACW1-89-D0133, Delivery Order Number 15, received 8/5/1996. |
Tamar Stephens |
8/26/1996 |
Update or Other Action |
ADEC staff Stephens and Himmelbauer met with James Baker of COE to scope out closure procedures and risk assessment needs for Nome area FUDS project sites. |
Tamar Stephens |
3/20/1997 |
Update or Other Action |
Site updated by Shannon and Wilson, based on the FUDS Site Summary dated 2/21/96. |
S&W |
7/29/1998 |
Site Characterization Report Approved |
Approved final Field Investigation Report to support removal action. |
Tamar Stephens |
8/28/1998 |
Meeting or Teleconference Held |
Public meeting in Teller. Corps of Engineers discussed plans for further investigation and cleanup at Davidson's Landing. |
Tamar Stephens |
12/15/1998 |
Update or Other Action |
Reviewed draft Field Investigation Report to support a removal action for petroleum contaminated soil at former biovents and landfarm. |
Tamar Stephens |
12/22/1998 |
Meeting or Teleconference Held |
Review conference with Corps of Engineers on Field Investigation Report. |
Tamar Stephens |
12/30/1998 |
Update or Other Action |
ADEC peer review to evaluate proposed soil cleanup levels for removal action. |
Tamar Stephens |
2/9/1999 |
Update or Other Action |
Reviewed draft EE/CA (Engineering evaluation / cost analysis) for proposed removal action at former biovents and landfarm. |
Tamar Stephens |
4/5/1999 |
Update or Other Action |
Reviewed, concurred with Environmental Assessment that proposed removal action at former biovents and landfarm would not significantly affect the environment. |
Tamar Stephens |
4/26/2000 |
Update or Other Action |
Review of draft Work Plan for Davidson’s Landing by Tamar Stephens. Additional information requested. Action added by Sarah Riddle. |
Tamar Stephens |
6/27/2000 |
Update or Other Action |
Contacted Tamar Stephens and asked if she knew anything about the Landowner of this site. She said that the owner died and property transfer to heir not settled yet. She said that she would contact me when new information was available. |
Former Staff |
10/2/2003 |
Interim Removal Action Approved |
Reviewed and approved final closure report for removal of petroleum contaminated soil. Report describes excavation and removal of approximately 15-cubic yards of petroleum-contaminated soil at a former biovent location at Davidson’s Landing. Work was performed in summer of 2000, but DEC did not receive report until Sept. 2003. The biovent, located adjacent to an un-named slough off of the Kaviruk River, was in operation during a cleanup action during 1994 through 1996 and was designated as Biovent #1. Elevated levels of diesel and residual range organics remained in Biovent #1 soil at the end of 1996 cleanup activities. During the 2000 removal action, the soil was excavated to permafrost, a depth of three to four feet, and transported off site for treatment and disposal. Confirmation sampling showed maximum levels of 23 mg/kg diesel range organics and 89 mg/kg residual range organics at the bottom of the excavation. Benzene, toluene, ethylbenzene, xylenes, and semivolatile organic compounds were not detected. Based on this information, no further cleanup is required at the Biovent #1 location |
Tamar Stephens |
12/8/2003 |
GIS Position Updated |
Used file to find approximate location of site. Good site map was unavailable. |
Torsten Ernst |
12/16/2005 |
Update or Other Action |
Telephone conversation with Corps of Engineers project manager: intent is to write a decision document to close out the site as soon as funding is available. |
Tamar Stephens |
3/28/2008 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed. |
Tamar Stephens |
7/14/2008 |
Site Characterization Workplan Approved |
Approved work plan to conduct confirmation sampling at two locations, former Biovent No. 2 and a former landfarm area, where the Corps of Engineers conducted treatment of petroleum-contaminated soil during 1994-1996; to assess for the presence of 55-gallon drums in the un-named slough,;and collect surface water and sediment samples in the slough. |
Tamar Stephens |
10/3/2008 |
Document, Report, or Work plan Review - other |
Reviewed draft Davidson’s Landing Formerly Used Defense Site Remedial Action Technical Memorandum and sent comment letter. |
Tamar Stephens |
4/14/2009 |
Document, Report, or Work plan Review - other |
Reviewed and sent approval letter for Underwater Debris Survey Work Plan. In response to past reports of drums in the slough, the Corps of Engineers will conduct and underwater survey of the slough with an undewater video camera to determine the presence of 55 gallon drums or other metallic debris. Field work is scheduled for late August, 2009. |
Tamar Stephens |
2/9/2010 |
Document, Report, or Work plan Review - other |
Reviewed draft Underwater Debris Survey Report and sent comments letter. |
Tamar Stephens |
12/2/2011 |
Document, Report, or Work plan Review - other |
Reviewed and sent approval letter for final Underwater Debris Survey Report. Concurred with report recommendation to remove drum fragments found in slough and remove four intact drums found in vegetation near shoreline. |
Tamar Stephens |
12/2/2011 |
Document, Report, or Work plan Review - other |
Reviewed and sent approval letter for final Remedial Action Technical Memorandum. The report presents the results of sampling in 2008 of former Biovent No. 2 and the former Landfarm where petroleum contaminated soil was treated during a 1994 through 1996 cleanup at the site. The report also presents results of sediment and surface water sampling of the slough. Concur with report conclusions that no further cleanup is needed at Biovent No. 2 or at the Landfarm. Concur that sample results show no violations of Alaska Water Quality Standards of the slough. (Field work was conducted in 2008, but final report was sent to DEC in November 2011.) |
Tamar Stephens |
2/11/2013 |
CERCLA Proposed Plan |
DEC approved the Corps of Engineers Proposed Plan for Davidson's Landing. The plan calls for removal and off-site disposal of the remaining 55-gallon drums or partial drums and petroleum contaminated soil that is along the west bank of an unnamed slough. The Corps scheduled a public meeting on the Proposed Plan for February 13, 2013. |
John Halverson |
7/3/2013 |
Update or Other Action |
DEC reviewed and commented on a draft decision document that calls for removal of drums (intact and partial, some of which are submerged in a slough)and petroleum contaminated soil (estimated to be ~ 5 cubic yards in volume) from the site. Several recommendations/clarifications were requested. |
John Halverson |
1/2/2014 |
Update or Other Action |
Site transferred from Shepard to Savage |
Rebecca Bryan |
2/4/2014 |
Update or Other Action |
Recieved Draft 2014 Removal Action Work Plan,Davidson's Landing FUDS. Proposed for the 2014 field season is the removal and disposal of 4-5 drums from within the Unnamed Slough, 4 drums from the west bank of the slough and any associated contaminated soil. Fluids from the drums will also be collected and analyzed. |
Meredith Savage |
4/4/2014 |
Document, Report, or Work plan Review - other |
April 4, 2014- ADEC provided comments on Work Plan and asked for the addition of sediment sampling around the submerged drums if a hydrocarbon sheen is observed during removal. |
Meredith Savage |
5/23/2014 |
Update or Other Action |
Draft Addendum One to the Removal Action Work Plan received; the work plan addendum covered sediment sampling activity to be conducted if a hydrocarbon sheen is observed during drum removal from the slough at the Davidson's landing site. |
Meredith Savage |
6/4/2014 |
Document, Report, or Work plan Review - other |
Removal Action Work Plan accepted as final. |
Meredith Savage |
6/17/2014 |
Update or Other Action |
ADEC requests that sediment samples be analyzed for Semi Volatile Organic Compounds (SVOCs) metals, and Polychlorinated Biphenyls (PCBs). |
Meredith Savage |
6/30/2014 |
Update or Other Action |
After discussion with RP/RP contractor, ADEC amends comments letter regarding the draft Addendum One to the Removal Action Work Plan to request that sediment samples be taken from within or around the drums regardless of presence or absence of a hydrocarbon sheen; sample analyses should include DRO, RRO, BTEX, PAH, metals, and PCB. |
Meredith Savage |
7/17/2014 |
Update or Other Action |
Final Addendum One to the Removal Action Work Plan received; work plan addendum includes the requested sediment sampling and sampling analysis. |
Meredith Savage |
8/4/2014 |
Document, Report, or Work plan Review - other |
Final approval given for Addendum One to the Removal Action Work Plan. |
Meredith Savage |
10/2/2014 |
Update or Other Action |
Received draft report titled 'Removal Action Report, Davidson's Landing.' |
Meredith Savage |
10/24/2014 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 72131 Davidsons Landing. |
Meredith Savage |
12/23/2014 |
Document, Report, or Work plan Review - other |
ADEC received a report titled Final Removal Action Report – Davidson’s Landing FUDS, Alaska, on December 11, 2014. This report addresses actions taken to remove partially buried drums from the site known as Davidson’s Landing. Five drums were removed from a small slough draining into the larger Unnamed Slough that bisects the site and additional drum parts were removed from the Unnamed Slough. Two more drums were found on land along the west bank of the Unnamed Slough. None of the drums were intact enough to hold fluids. Soil or sediment samples were collected from directly beneath each drum or drum carcass and analyzed for diesel range organics (DRO), residual range organics (RRO), polycyclic aromatic hydrocarbons (PAHs), metals, polychlorinated biphenyls (PCBs), and benzene, toluene, ethylbenzene, and xylene, (BTEX). All results were below applicable action levels. Impacts were minimal and site restoration was not required.
ADEC has reviewed this report, finds that it adequately meets the applicable requirements of 18 AAC 75.340, .355, and .360, and accepts it as final. Remedial action at this site has fulfilled the requirements laid out in the September 2013 Decision Document and the site is ready for closure.
|
Meredith Savage |
12/29/2014 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 72131 Davidsons Landing. |
Meredith Savage |
6/19/2015 |
Institutional Control Record Removed |
Institutional Controls have been removed. |
Meredith Savage |
6/19/2015 |
Cleanup Complete Determination Issued |
The Alaska Department of Environmental Conservation has completed a review of the environmental records associated with the Davidson's Landing Site. Based on the review a Cleanup Complete determination has been issued. No further remedial action is required at this site. |
Meredith Savage |