Action Date |
Action |
Description |
DEC Staff |
5/21/1991 |
Update or Other Action |
Notice of Release Letter sent. |
Former Staff |
8/9/1991 |
Update or Other Action |
Former SA1 R:Base Action. A 1,000 gallon diesel fuel tank was decommissioned in place because it extends beneath a building. Strong fuel odor and visible staining in soil. Less than one cubic yard of soil was removed. Groundwater was present at 1.8 feet below ground surface. A heavy sheen was present on the ground water. The tank was filled from 55 gallon drums. No secondary containment was used in the drum handling area, surface spills and stressed vegetation were present. No known wells on the island, surface water is used as a drinking water supply for island residents. A 500 gallon gasoline tank was removed. Three cubic yards of fuel impacted soil was placed in supersacks and taken to the USCG base on Kodiak Island. Ground water was encountered at 3.5 feet below ground surface. A light sheen was present on the ground water. Approximately 100 gallons of water suspected of being contaminated was contained and stored on site. SA report states a release investigation is necessary for the diesel impacted area but not the gasoline UST area. The release investigation should address both areas due to sheen that was present in gasoline UST excavation. |
Former Staff |
9/17/1992 |
Site Added to Database |
Petroleum contamination. |
Former Staff |
3/15/1993 |
Leaking Underground Storage Tank Corrective Action Underway |
LUST Corrective Action Underway this date. |
Former Staff |
6/16/1995 |
Site Ranked Using the AHRM |
Initial ranking. Action code added because it wasn't when the site was originally ranked. |
Kent Patrick-Riley |
12/13/1999 |
Site Number Identifier Changed |
Formerly a LUST site. Changed workplan from 00 to 01 as numerous sites are non-regulated. |
Eileen Olson |
4/10/2000 |
Site Characterization Workplan Approved |
|
Eileen Olson |
4/23/2000 |
Meeting or Teleconference Held |
Met with Brad Platt of FAA's EOSH Services Team on March 23rd to discuss scheduled demolition and decommissioning projects including FAA's Woody Island Station which have contaminated sites issues. |
Eileen Olson |
6/22/2000 |
Update or Other Action |
Department approval for FAA’s revised plan which proposes transporting diesel contaminated soil to the thermal remediation unit currently operating at the Kodiak USCG base. Work to be done under the Corps’ TERC contract, with Jacobs Engineering. Soil will be placed in "supersacks", transported by landing craft to Kodiak, and trucked to the USCG base
where the supersacks will be covered and stored until they are remediated in the
fall. FAA expected to begin transporting the soils on June 19th. |
Eileen Olson |
9/26/2001 |
Update or Other Action |
Site closure was granted for the former tank site at Building 603. The closure is recorded as a separate database entry.
Subject: Review of “Remedial Action Report, FAA Woody Island Demolition”, dated December 2000, and response to requests for site closure status (no further action) and site closure status approval for Building 603 – Engine Generator Building. |
Eileen Olson |
9/27/2001 |
Update or Other Action |
Email and telephone communications with FAA regarding the Lesnoi area. The area encompassing Buildings #400, #401, and #603 is to be transferred over to Lesnoi Native Corp. without site closure. Building #603 was given site closure status this week. Buildings #400 and #401 need sampling clarification prior to site closure. FAA will submit the clarification information sometime next year when their contractor can research the request. |
Elizabeth Stergiou |
10/15/2001 |
Update or Other Action |
Site closure was granted for tank sites at Buildings 400 and 401. The closures are recorded as separate database entries. |
Eileen Olson |
10/1/2002 |
Update or Other Action |
DEC faxed approval to United Soil Recycling (USR) to transport contaminated soils to USR's Kodiak Recycling Facility from the FAA Woody Island Station site, with note stating that approval is contingent upon soil treatment facility's permit approval by ADEC's Paul Horwath. |
Eileen Olson |
1/14/2003 |
Update or Other Action |
Rec'd fax from Brad Platt "Woody Island Contaminated Soil Information" with attached certification that United Soil Recycling, Kodiak facility, rec'd and accepted on 10/25/2002 861 tons of petroleum contaminated soil which originated from the FAA Wood Island Station; and certification that "soil has been thermally remediated to levels in accordance with 18 AAC 75.341". . |
Eileen Olson |
3/12/2003 |
Update or Other Action |
Confirmation of contaminated soil remediation was provided to the Department. The soil was generated from three sites on Woody Island totaling 7c.y. The fourth site was on Kodiak Island and was 20 c.y. The soils from Woody island were transported to Kodiak Island where they were thermally treated and disposed of properly at the USCG station. |
Bob Glascott |
8/26/2005 |
Update or Other Action |
Staff reviewed site file and reports and sent a letter addressing all potential areas of concern and previous closure requests. Those decisions are detailed in the entries below on this same date. |
Anne Marie Palmieri |
8/26/2005 |
Update or Other Action |
Underground Storage Tank (UST) 31-C-1 (Active RCAG) – This 500-gallon UST was in service from 1961 until removal in 1991. Soil samples were collected and method two cleanup levels were met. No soil was removed. The department requires no further investigation at this area and considers it closed. |
Anne Marie Palmieri |
8/26/2005 |
Update or Other Action |
Non-Directional Beacon – FAA has requested site closure at this area. The Environmental Compliance Investigation Report (ECIR) dated 1992 reported the presence of a transformer which had been shot with a bullet at Building 402, however no stained soil was found. This area has been regraded and the transformers removed. No further investigation is required at the Non-Directional Beacon area. |
Anne Marie Palmieri |
8/26/2005 |
Update or Other Action |
AST 31-D-1 (Building 404, Inactive RCAG) – FAA has requested site closure at the location of the former AST 31-D-1. This 1000-gallon tank was removed in 1990. Three (3) cy of soil were removed and later treated on Kodiak. Confirmation samples from the excavation showed the presence of elevated concentrations of diesel-range organics up to 14,772 mg/kg. Closure cannot be granted as petroleum contaminated soil remains. Furthermore, the dead vegetation and stained soil south of Building 404, shown on Figure 3-6 of the Environmental Compliance Investigation Report (ECIR) dated 1992, and the petroleum contaminated soil at the concrete piers, documented in Section 5.5 of the Remedial Action Report dated December 2000, should be addressed. Additional site characterization and/or cleanup are requested for these areas. |
Anne Marie Palmieri |
8/26/2005 |
Update or Other Action |
Building 201 (Inactive RCAG) – FAA has requested site closure specifically for the polychlorinated biphenyls (PCBs) contamination at Building 201. As part of the Expanded Site Investigation dated 1996, soil contaminated with petroleum hydrocarbons and PCBs was excavated. PCBs confirmation samples showed one result of less that 5 milligrams per kilogram (mg/kg) PCBs and five results of non-detect. One petroleum hydrocarbon sample result showed an elevated concentration of 13,500 mg/kg for diesel-range organics. Closure is evaluated for an area of concern and cannot be split by the various contaminants of concern. As there is residual petroleum hydrocarbon contamination at Building 201, DEC is unable to grant closure. Also, the current default soil cleanup level for PCBs is 1 mg/kg. Further discussion on PCBs in soil at this site is needed before additional work is performed in the field. |
Anne Marie Palmieri |
8/26/2005 |
Update or Other Action |
AST 31-B-4 (Tank Farm) – This 20,000-gallon diesel tank was one of five AST(s) in the tank farm. As reported in the Technical Memorandum dated December 1997, field screening showed contamination present around the dispenser and tanks 31-B-1, 31-B-2, and 31-B-3. No contamination was found to be present at tank 31-B-4 and no soil was removed. Therefore, the department requires no further investigation at this tank. |
Anne Marie Palmieri |
8/26/2005 |
Update or Other Action |
AST 31-B-5 (Tank Farm) – This 500-gallon gasoline tank was located adjacent to AST 31-B-4 in the tank farm. Field screening showed that no contamination was present around this tank. No soil was removed. The department requires no further investigation at this tank. |
Anne Marie Palmieri |
8/26/2005 |
Update or Other Action |
AST 31-B-1, B-2 and B-3 (Tank Farm) – Based on information available during this file review, additional site characterization and/or cleanup are necessary at these former tank sites. |
Anne Marie Palmieri |
8/26/2005 |
Update or Other Action |
Pipeline (Tank Farm) – A total of approximately 700 linear feet of 2-inch pipe and 600 linear feet of 4-inch pipe were removed in 1997 and 2000. Field screening along the joints and junctions of the pipeline showed that no contamination was present. These activities are documented in the Technical Memorandum dated 1997 and the Remedial Action Report dated December 2000. The department requires no further investigation along these former pipelines. |
Anne Marie Palmieri |
8/26/2005 |
Update or Other Action |
AST 31-E-10 (Building 600) – This 3000-gallon AST was decommissioned in 2000. No evidence of contamination was noted during the field screening while decommissioning the tank. Thus, the decision was made in the field not to collect any soil samples. No soil was removed. A description of this tank is located in the Remedial Action Report dated December 2000. The department does not consider this former tank site to be a contaminated site and is not requesting any further characterization associated with the tank. |
Anne Marie Palmieri |
8/26/2005 |
Update or Other Action |
AST 31-E-6 (Building 103) – During the 2004 decommissioning activities, an investigation was conducted around the tank cradle where the former heating oil AST sat. The AST was removed at an unspecified point in the past. Soil samples were collected and met the default method two cleanup levels. No soil was removed. Discussion concerning this tank is located in the Remedial Action Report dated December 2004. The department requires no further investigation at this area. |
Anne Marie Palmieri |
8/26/2005 |
Update or Other Action |
AST 31-E-5 (Building 104) – During the 2004 decommissioning activities, an investigation was made around the tank cradle where the former heating oil AST sat. The AST was removed at an unspecified point in the past. Soil samples were collected and met the default method two cleanup levels. No soil was removed. Discussion concerning this tank is located in the Remedial Action Report dated December 2004. The department requires no further investigation at this area. |
Anne Marie Palmieri |
8/26/2005 |
Update or Other Action |
AST 31-E-4 (Building 105) – During the 2004 decommissioning activities, an investigation was made around the tank cradle where the former heating oil AST sat. The AST was removed at an unspecified point in the past. Soil samples were collected and met the default method two cleanup levels. No soil was removed. Discussion concerning this tank is located in the Remedial Action Report dated December 2004. The department requires no further investigation at this area. |
Anne Marie Palmieri |
8/26/2005 |
Update or Other Action |
UST 31-E-3 (Building 107) – Two (2) 560-gallon USTs were removed during the 2004 decommissioning activities. Three (3) cy of petroleum-contaminated soil were excavated and sent to Alaska Soil Recycling. Soil confirmation samples were collected and the default method two cleanup levels were met. Discussion concerning this tank is located in the Remedial Action Report dated December 2004. The department requires no further action at this site. Site closure is approved. |
Anne Marie Palmieri |
8/26/2005 |
Update or Other Action |
UST 31-E-2 (School) – A 650-gallon UST was removed during the 2004 decommissioning activities. Five (5) cy of petroleum-contaminated soil were excavated and sent to Alaska Soil Recycling. Soil confirmation samples were collected and the default method two cleanup levels were met. Discussion concerning this tank is located in the Remedial Action Report dated December 2004. The department requires no further action at this site. Site closure is approved. |
Anne Marie Palmieri |
6/8/2007 |
Exposure Tracking Model Ranking |
ETM ranking |
Anne Marie Palmieri |
8/24/2007 |
Site Characterization Report Approved |
ROST report dated 2/07 approved this date. |
Anne Marie Palmieri |
2/10/2009 |
Document, Report, or Work plan Review - other |
Based upon the information provided in the 1997 ROST Site Investigation, DEC has closed multiple areas of concern; details on specific areas will follow in separate comment fields. Remaining areas where additional investigation or cleanup is needed include: Building 605 (repair shop), inactive RCAG, Building 405 (vortac), Building 404, Tank Farm, and Building 300. For those areas where contamination above the department’s most stringent cleanup levels is being left in place; i.e. DRO greater than 230 mg/kg, the presence of this contaminated soil should be tracked. If in the future this contaminated soil is excavated by FAA, the landowner, or another party, the department should be notified as the soil will need to be managed in accordance with department regulations current at that time. |
Anne Marie Palmieri |
2/10/2009 |
Update or Other Action |
Building 605: Repair Shop – During the ROST investigation, 25 probes were advanced and 12 samples were collected. Diesel range organics (DRO) was found at concentrations up to 5910 milligrams per kilogram (mg/kg) with the main part of the plume on the northern side of the former building location. The ROST investigation found the fuel present at relatively shallow depths, however in the footprint of the former building there was fuel indicated at 21 feet below ground surface (bgs). Samples were also analyzed for polychlorinated biphenyls (PCBs) with the highest concentration detected of 0.08 mg/kg, well below the department’s cleanup level of 1 mg/kg. No additional investigation of PCBs is required. Given the concentrations of and extent of petroleum contamination found, this area needs to be addressed further. |
Anne Marie Palmieri |
2/10/2009 |
Update or Other Action |
Aboveground Storage Tank (AST) 31-D-1 (Building 404, Inactive RCAG) – This 1000-gallon tank was removed in 1990. Three (3) cy of soil was removed. Confirmation samples from the excavation showed the presence of elevated concentrations of diesel-range organics up to 14,772 mg/kg. Closure was not granted in the department’s August 25, 2005 letter as petroleum contaminated soil was suspected to remain. During the ROST investigation, 10 probes were advanced. No fuel was indicated in any of the probes and the analytical results from the one sample collected were non-detect for all petroleum constituents. Therefore, the department determines that no additional characterization and/or cleanup is needed at this tank. Cleanup is complete. |
Anne Marie Palmieri |
2/10/2009 |
Update or Other Action |
Inactive RCAG – In the department’s August 25, 2005 letter, it requested that the petroleum contaminated soil at the concrete piers, documented in Section 5.5 of the Remedial Action Report dated December 2000, be addressed. During the ROST investigation, 22 probes were advanced and levels of DRO up to 1500 mg/kg were found to be present, however based upon the florescence readings higher levels are suspected to be present. Contamination was found to be present from the ground surface to depths of 5 feet bgs in an area approximately 100 feet by 100 feet. Given the concentrations of and extent of petroleum contamination found, this area needs to be addressed further. |
Anne Marie Palmieri |
2/10/2009 |
Update or Other Action |
Building 201 (Inactive RCAG) – As part of the Expanded Site Investigation dated 1996, soil contaminated with petroleum hydrocarbons and PCBs was excavated. PCBs confirmation samples showed one result of less than 5 mg/kg PCBs and five results of non-detect. One petroleum hydrocarbon sample result showed an elevated DRO concentration of 13,500 mg/kg. During the ROST investigation, 12 probes were advanced. Ten samples were collected with levels of DRO up to 1400 mg/kg found to be present and PCB sample results of non-detect. Based upon a review of the florescence readings fairly low-levels of DRO contamination were found to be present from the ground surface to depths of 5 feet bgs in an area approximately 60 feet by 60 feet. Given the concentrations of and extent of petroleum contamination found, this area does not need to be addressed further. Cleanup is complete. |
Anne Marie Palmieri |
2/10/2009 |
Update or Other Action |
Former Disposal Area (Dump) – A former disposal area (dump) was located near the Communication Transmitter where debris was scattered on the ground across an approximately 3 acre area. The debris was collected and buried. During the ROST investigation, 3 probes were advanced in this area. No fuel was indicated in any of the probes and no analytical samples were collected. The department determines that no additional activities are needed at this area. |
Anne Marie Palmieri |
2/10/2009 |
Update or Other Action |
ASTs 31-B-1, 31-B-2, 31-B-3 (Building 605 Tank Farm) – Five large bulk fuel ASTs were present in this tank farm and have now been removed. As reported in the Technical Memorandum dated December 1997, field screening showed contamination present around the dispenser and tanks 31-B-1, 31-B-2, and 31-B-3. No contamination was found to be present at tanks 31-B-4 and 31-B-5; thus, the department required no further investigation at those tanks, as documented in it August 25, 2005 letter. Contamination was suspected to be present in the areas of ASTs 31-B-1, 31-B-2, 31-B-3 and the dispenser. As the tanks have been removed, specific tank locations are difficult to accurately identify and all three tanks will be treated as one area of concern. Twenty-five probes were advanced during the ROST investigation and one sample was collected. Analytical results showed DRO concentrations of 4480 mg/kg present, however based upon the florescence readings, higher levels are likely. Contamination is present in two separate areas, with the larger being approximately 150 feet by 120 feet and the smaller being 100 feet by 50 feet. Given the concentrations of and extent of petroleum contamination found, this area needs to be addressed further. |
Anne Marie Palmieri |
2/10/2009 |
Update or Other Action |
Building 600 – During the 2004 decommissioning activities and documented in the Remedial Action Report dated December 2004, samples were collected at the septic outfall and analytical results showed elevated levels of DRO and PCBs. During the ROST investigation, five probes were advanced and five samples collected at the outfall. No fuel was indicated in any of the probes and all sample results were non-detect for all petroleum constituents and PCBs. Therefore, the department determines that no additional characterization and/or cleanup is needed at this tank. Cleanup is complete.
|
Anne Marie Palmieri |
2/10/2009 |
Update or Other Action |
UST at Building 100 – During the 2004 decommissioning activities and documented in the Remedial Action Report dated December 2004, a 500-gallon UST was removed. Soil samples were collected and elevated concentrations of DRO up to 2180 mg/kg were detected and ½ cubic yard (cy) of soil was removed. During the ROST investigation, 6 probes were advanced. Fuel contamination was indicated to a deepest point of 10 feet bgs at the former tank location and is projected to extend laterally in an area of 30 feet by 30 feet. One sample was collected and analytical results showed DRO of 795 mg/kg; based upon the florescence readings the remaining contamination is suspected to be at lower levels within a fairly limited and discontinuous contaminant plume. Given the concentrations of and extent of petroleum contamination found, this area does not need to be addressed further. Cleanup is complete. |
Anne Marie Palmieri |
2/10/2009 |
Update or Other Action |
AST at Building 101 – During the 2004 decommissioning activities and documented in the Remedial Action Report dated December 2004, a 500-gallon AST was removed. Soil samples were collected and elevated concentrations of DRO up to 566 mg/kg were detected and no soil was removed. During the ROST investigation, 13 probes were advanced. Fuel contamination was indicated to a deepest point of 13 feet bgs at the former tank location and is projected to extend laterally in an area of 60 feet by 60 feet. One sample and a duplicate were collected and analytical results showed DRO of 547 and 359 mg/kg; based upon the florescence readings the remaining contamination is suspected to be at lower levels within a fairly limited and discontinuous contaminant plume. Given the concentrations of and extent of petroleum contamination found, this area does not need to be addressed further. Cleanup is complete. |
Anne Marie Palmieri |
2/10/2009 |
Update or Other Action |
AST at Building 102 – During the 2004 decommissioning activities and documented in the Remedial Action Report dated December 2004, a 500-gallon AST was removed. Soil samples were collected and elevated concentrations of DRO up to 1430 mg/kg were detected and no soil was removed. During the ROST investigation, 3 probes were advanced and no fuel was found to be present. No analytical samples were collected. Given the lack of confirmation of the presence of contamination, this area does not need to be addressed further. Cleanup is complete. |
Anne Marie Palmieri |
2/10/2009 |
Update or Other Action |
UST at Building 106 – During the 2004 decommissioning activities and documented in the Remedial Action Report dated December 2004, a 500-gallon UST was removed. Soil samples were collected and elevated concentrations of DRO up to 353 mg/kg were detected and 1 cy of soil was removed. During the ROST investigation, 6 probes were advanced and no fuel was found to be present with the exception of low-level florescence below the former tank location. One analytical sample was collected and results for DRO and RRO were non-detect. Given the lack of confirmation of the presence of contamination, this area does not need to be addressed further. Cleanup is complete. |
Anne Marie Palmieri |
2/10/2009 |
Update or Other Action |
Building 200 – During the 2004 decommissioning activities and documented in the Remedial Action Report dated December 2004, an investigation was made around the tank cradle where the former heating oil AST sat. The AST was removed at an unspecified point in the past. Soil samples were collected and elevated concentrations of DRO up to 6320 mg/kg were detected and no soil was removed. During the ROST investigation, 10 probes were advanced. Fuel contamination was indicated to a deepest point of 10 feet bgs at the former tank location and is projected to extend laterally in an area of 40 feet by 60 feet. One sample was collected and analytical results showed DRO of 790 mg/kg; based upon the florescence readings the remaining contamination is suspected to be at lower levels within a fairly limited and discontinuous contaminant plume. Given the concentrations of and extent of petroleum contamination found, this area does not need to be addressed further. Cleanup is complete. |
Anne Marie Palmieri |
2/10/2009 |
Update or Other Action |
Building 300 – During the 2004 decommissioning activities and documented in the Remedial Action Report dated December 2004, a 500-gallon AST was removed. Soil samples were collected and elevated concentrations of DRO up to 35,600 mg/kg were detected and no soil was removed. During the ROST investigation, 3 probes were advanced. Fuel contamination was indicated to a deepest point of 4 feet bgs at the former tank location and is projected to extend laterally in an area of 60 feet by 120 feet. One sample was collected and analytical results showed DRO of 24700 mg/kg; this sample location was directly below the former tank. Although the extent of contamination is fairly limited, the concentrations exceed the department’s maximum allowable concentrations. Additional characterization and/or cleanup is needed at this former tank location. |
Anne Marie Palmieri |
2/10/2009 |
Update or Other Action |
UST at Building 301- During the 2004 decommissioning activities and documented in the Remedial Action Report dated December 2004, a 500-gallon UST was removed. Soil samples were collected and elevated concentrations of DRO up to 2180 mg/kg were detected and 11 cy of soil was removed. During the ROST investigation, 16 probes were advanced. Fuel contamination was indicated to a deepest point of 11 feet bgs and is projected to extend laterally in an area of 60 feet by 80 feet. One sample was collected at the area of highest florescence and analytical results showed DRO of 129 mg/kg; based upon the florescence readings the remaining contamination is suspected to be at lower levels within a fairly limited and discontinuous contaminant plume. Given the concentrations of and extent of petroleum contamination found, this area does not need to be addressed further. Cleanup is complete. |
Anne Marie Palmieri |
12/9/2011 |
Document, Report, or Work plan Review - other |
ADEC reviewed the draft Work Plan Remedial Investigation of Contaminated Groundwater and Soil and sent comments. The investigation includes installation of several wells at 4 different areas at the site as well as collecting soil samples to delineate the extent of contamination. Comments had to do with sampling locations and frequency, the hydrocarbon risk calculator, and contact with landowners. |
Meghan Dooley |
8/16/2012 |
Site Visit |
ADEC conducted a site visit to the Woody Island FAA facility on August 16. The FAA is investigating petroleum contamination in the soil and groundwater at four locations throughout the facility. Soil borings will be advanced at all locations and monitoring wells installed in order to delineate soil and groundwater contamination. |
Meghan Dooley |
1/13/2014 |
Document, Report, or Work plan Review - other |
Draft Remedial Investigation Report, Four Sites FAA Woody Island Station, Alaska, January 2014 received by ADEC. This report covers the following sites: Shop Building 605, Tank Farm, CT Site, and Building 300. |
Debra Caillouet |
11/13/2014 |
Document, Report, or Work plan Review - other |
ADEC provided comments on the "Draft remedial Investigation Report, Four Sites FAA Woody Island Station, Alaska" January 2014 report. |
Kara Kusche |
12/29/2014 |
Document, Report, or Work plan Review - other |
"Final Remedial Investigation Report Four Sites FAA Woody Island Station, Alaska" report received by ADEC. |
Kara Kusche |
4/28/2016 |
Site Characterization Report Approved |
ADEC sent approval letter for the 2014 Final Remedial Investigation Report, Four Sites, FAA Woody Island Station. |
Kara Kusche |
11/2/2016 |
Document, Report, or Work plan Review - other |
ADEC reviews and approves the "draft Work Plan,Investigation of Contaminated Groundwater, FAA Woody Island Station, Alaska" dated October 2016. This work plan will fill groundwater data gaps at Shop Building 605 and the Tank Farm. |
Kara Kusche |
5/24/2018 |
Document, Report, or Work plan Review - other |
ADEC provides comment on the "Cleanup and Direction Finder Demolition" work plan dated April 2018. This work plan proposes debris and soil removal at the CT Dump site, soil sampling at the VOR north drum area, and demolition of the DF Tower. |
Kara Kusche |
7/2/2018 |
Site Characterization Workplan Approved |
ADEC approves the "Cleanup and Direction Finder Demolition" work plan dated June 2018. |
Kara Kusche |
8/1/2018 |
Site Visit |
ADEC conducts regulatory oversight site visit. Field activities observed were in compliance with the approved work plan. |
Kara Kusche |
8/9/2018 |
Document, Report, or Work plan Review - other |
ADEC provides comment on the "Cleanup and Directional Finder Demolition Work Plan Addendum." This addendum is in response to finding lead throughout the dump, and discusses excavation, soil removal procedures, waste stream tracking, waste characterization sampling, confirmation sampling, and disposal additions or modification to the original work plan. |
Kara Kusche |
8/16/2018 |
Site Characterization Workplan Approved |
ADEC reviews the updated document titled "Cleanup and Direction Finder Demolition, Woody Island, Alaska, Work Plan Addendum, CT Dump Removal" and dated August 14, 2018. ADEC approves the work plan addendum. |
Kara Kusche |
10/15/2018 |
Offsite Soil or Groundwater Disposal Approved |
ADEC approves 1000 cubic yards of soil containing PCBs, lead, asbestos, and POL to be transported and disposed of at waste facilities in Washington and Oregon. |
Kara Kusche |
3/20/2019 |
Document, Report, or Work plan Review - other |
ADEC reviews and provides comment on the Draft Report for "Woody Island Demolition and Environmental Remediation: dated February 2019. The Direction Finder has been demolished, removed, and lead is all below clean up levels. The former north drum area at the VOR was sampled, and samples show that contamination is below cleanup levels. Debris and soil was removed from the CT Dump, areas of lead and PCB contamination remain, 1,100 cubic yards of material was removed offsite in 2018, and containerized non-hazardous waste remains to be disposed of in 2019. |
Kara Kusche |
4/18/2019 |
Site Characterization Workplan Approved |
ADEC reviews and approves the work plan addendum titled "Work Plan Addendum 2, Federal Aviation Administration, Cleanup and Direction Finder Demolition, Woody Island, Alaska" dated April 2019. The work plan addendum is a continuation of 2018 field work and aims to remove all contamination at the dump to below clean up levels. |
Kara Kusche |
5/22/2019 |
Site Characterization Report Approved |
ADEC approves the report titled "Final Report, Federal Aviation Administration, Woody Island Demolition and Environmental Remediation, Woody Island, Alaska" dated May 2019. |
Kara Kusche |
5/22/2019 |
Offsite Soil or Groundwater Disposal Approved |
608 cubic yards of PCB/lead/POL contaminated soils originating from the Dump area are approved for transport and disposal out of state. |
Kara Kusche |
4/29/2020 |
Document, Report, or Work plan Review - other |
ADEC provides comments on the report titled "Demolition and Environmental Remediation Final Report, Draft 2019 Addendum" dated December 2019. The report documents additional excavation of 12 remaining lead an PCB locations. Following field work, 11 of 12 locations meet cleanup levels, and 1 location still exceeds cleanup levels for PCBs and DRO. |
Kara Kusche |
8/4/2020 |
Update or Other Action |
ADEC provides comment on the document package and associated calculations titled "Draft Report Addendum to the Final Remedial Investigation Report, Four Sites, FAA Woody Island Station, Alaska" dated December 24, 2019. This submittal provides HRC calculations for 4 areas: building 605, tank farm, CT site, and building 300. |
Kara Kusche |
9/15/2020 |
Document, Report, or Work plan Review - other |
ADEC reviews FAA's responses to ADEC's comments on the HRC calculation. ADEC and FAA are in agreement with all comments resolved. FAA will update and resubmit document for approval. |
Kara Kusche |
9/15/2020 |
Site Characterization Report Approved |
ADEC approves the report titled "Demolition and Environmental Remediation Final Report, Final 2019 Addendum" dated May 2020. ADEC concurs with the recommendations for next steps presented in the report: further excavation at location PCB08 (contamination remains at three of four
sidewalls ranging from 1.05 to 1,270 mg/kg total PCBs and DRO from 416 to 548 mg/kg). |
Kara Kusche |
1/15/2021 |
Site Characterization Report Approved |
ADEC approves the "Final Report Addendum to the Final Remedial Investigation Report, Four Sites, FAA Woody Island Station, Alaska" dated September 18, 2020 and agrees with the conclusions and recommendations presented. This addendum updates HRC calculations to the 2014 report which covers Shop Building 605, Tank Farm, CT site, and Building 300 areas of concern.
|
Kara Kusche |
3/24/2021 |
Document, Report, or Work plan Review - other |
ADEC reviews the "Draft Report Addendum 2, Federal Aviation Administration Woody Island Demolition and Environmental Remediation, Woody Island, Alaska" report dated November 2020. ADEC does not have any requests for revisions, and will wait for the final draft before approving. This report documents 2020 work at the Dump location PCB08. DRO has been removed and now meets cleanup levels. PCBs exceed cleanup levels with a max value of 58 mg/kg. ADEC agrees with report recommendations to finish excavating remaining PCB contamination and dispose of contaminated soils. |
Kara Kusche |
4/23/2021 |
Site Characterization Report Approved |
ADEC approves the document titled
"Final Report Addendum 2, Federal Aviation Administration, Woody Island Demolition and Environmental Remediation, Woody Island, Alaska" dated March, 2021. ADEC agrees with report conclusions and recommendations. |
Kara Kusche |
5/27/2021 |
Site Characterization Workplan Approved |
ADEC approves the "Draft Work Plan, Federal Aviation Administration, Woody Island Contaminated Soil Removal 2021, CT and Building 300 Sites, Woody Island, Alaska" dated April 2021. This work plan is to remove and dispose of petroleum contaminated soils, pilings, and debris, and and collect confirmation samples at excavation walls at the CT site and Building 300 site. 450 yards of soil are expected to be removed from the CT site, and about 30 yards from the Building 300 site. |
Kara Kusche |
1/31/2022 |
Document, Report, or Work plan Review - other |
CT Site and Building 300 site: ADEC provides comments on the report titled "DRAFT Report
Federal Aviation Administration Woody Island Contaminated Soil Removal 2021 CT and Building 300 Sites Woody Island, Alaska" dated December 2021. The report documents additional excavation of petroleum contaminated soil at two locations. Following field work, contamination above cleanup levels remains. |
Sarah Mutter |
2/3/2022 |
Document, Report, or Work plan Review - other |
CT Dump Site: ADEC provides comments on the report titled "DRAFT Report Addendum 3
Federal Aviation Administration Woody Island Demolition and Environmental Remediation CT Dump Site
Woody Island, Alaska" dated January 2022. The report documents additional excavation of hot spot PCB08. Following field work, no contamination exceeding cleanup levels at hotspot PCB08 remains. |
Sarah Mutter |
5/4/2022 |
Document, Report, or Work plan Review - other |
ADEC approves the document titled "FINAL Report Addendum 3 Federal Aviation Administration Woody Island Demolition and Environmental Remediation CT Dump Site, Woody Island, Alaska" dated April, 2022. ADEC approves this report addendum. |
Sarah Mutter |
5/5/2022 |
Document, Report, or Work plan Review - other |
ADEC approves the document titled "Final Report Federal Aviation Administration Woody Island Contaminated Soil Removal 2021 CT and Building 300 Sites Woody Island, Alaska" dated March, 2022. ADEC approves the report and concurs with the recommendations for next steps presented in the report. |
Sarah Mutter |
2/3/2023 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed for source area id: 81274 name: Woody Island Dump |
Arika Garcia |
3/6/2023 |
Update or Other Action |
ADEC issued a cleanup complete determination for the Woody Island Dump site, an area of concern within the FAA Woody Island site. |
Arika Garcia |
4/29/2024 |
Meeting or Teleconference Held |
FAA and DEC held a meeting to discuss next steps for the FAA Woody Island sites. Buildings 202 and 604 were demolished and addressed in some historical documents. There is no evidence of a release of contamination at either site, therefore, DEC and FAA agreed that the locations of these former buildings do not require additional investigation. |
Sophia Bracio |
6/21/2024 |
Site Characterization Workplan Approved |
WORK PLAN APPROVAL: Final Work Plan Woody Island and Kodiak Tower 2024 Remedial Investigation and Remedial Action, Kodiak, Alaska (Ahtna, June 2024). This work plan details proposed work at the following 5 areas of concern: Kodiak Tower (Haz ID 1318), Building 300 (Haz ID 27464), Building 605 (Haz ID 27537), CT Site (Haz ID 27467), and Tank Farm (Haz ID 27538). |
Sophia Bracio |
7/2/2024 |
Site Visit |
DEC conducted a site visit on Woody Island to observe soil and groundwater sampling and excavation activities being performed at the Bldg. 300, Bldg. 605 Shop, Tank Farm, and CT site. Work was performed in accordance with the approved work plan and DEC and FAA plan to discuss a path forward for the Bldg. 300 AOC. |
Sophia Bracio |