| Action Date |
Action |
Description |
DEC Staff |
| 10/26/1992 |
Update or Other Action |
(Old R:Base Action Code = MS - Monitoring/Sampling). WDO Hydrologist Eileen Olson traveled to the site to re-sample the retort site and to sample background soils for mercury. Results of the WDO sampling showed mercury contamination of soils to be pervasive in the immediate vicinity of the retort shack. |
Former Staff |
| 11/21/1992 |
Site Ranked Using the AHRM |
Initial site ranking. Recreation area value changed from site managers submitted form. |
Former Staff |
| 12/1/1992 |
Notice of Violation |
Notice of Violation issued this date. |
Eileen Olson |
| 12/21/1992 |
Notice of Violation |
WDO issued an NOV/RCA to BLM requesting a contamination assessment and Phase I Remedial Action Plan as one document by February 28, 1993, and specified cleanup of mercury contaminated soils should begin by July 1993 and be essentially completed by August 31, 1993. |
Former Staff |
| 1/13/1993 |
Site Added to Database |
Site added to database. |
Former Staff |
| 5/5/1993 |
Site Characterization Workplan Approved |
(Old R:Base Action Code = SA1R - Phase I SA Review (CS/LUST)). A review letter was sent approving the retort site characterization plan, which was received by WDO on April 1, 1993. For clarity, the plan submitted will be referred to as the Red Top Site Characterization Plan instead of the original title, "Red Top Retort Sampling and Analysis Plan, Near Dillingham, Alaska." Although the department's NOV of December 21, 1992, had requested a combination site assessment and remedial action plan, it was agreed that a two-phase approach was appropriate since insufficient site information is available to plan remediation. The remedial action plan for the retort site and a site characterization plan for the mine site, which is over a mile from the retort site, will be submitted later this summer after the retort site characterization is complete. Site characterization work is expected to begin in mid-June, and remedial action at the retort site is still required to take place this summer. |
Former Staff |
| 5/5/1993 |
Update or Other Action |
Conditional approval of work plan received from BLM on April 1, 1993 |
Eileen Olson |
| 6/14/1993 |
Update or Other Action |
ADEC letter requesting that BLM notify the Department of whether it intends to complete site work according to the schedule requested by the Department's Notice of Violation/Request for Corrective Action (NOV). |
Eileen Olson |
| 6/15/1994 |
Update or Other Action |
Site cleanup was done in 1994 by BLM without Department involvement under the auspices of CERCLA, as an emergency removal action. However, CERCLA stipulates that an action memorandum be prepared prior to beginning work, and that an administrative record be set up at or near the site for public review. Neither of these requirements appear to have been met. |
Eileen Olson |
| 12/1/1994 |
Update or Other Action |
(Old R:Base Action Code = FI - Field Inspection (General)). The retort site has been torn down. Highly impacted soils have been excavated to drums but left at the site. Water quality indicated that river water has mercury above MCLs but no work for background so - where is the maximum. |
Ray Dronenburg |
| 9/29/1997 |
Update or Other Action |
Site visit. Staff visited this site with BLM personnel Joe Dygas and Carl Persson, and Aleknagik City Manager Mike Shuler on Monday September 29. Mr. Shuler expressed concern that an unsightly chain-link fenced enclosure has been present next to the Wood River for three years, and that the mercury-contaminated soils stored in fish totes within the enclosure are not properly secured. BLM is working with the City of Aleknagik and ADEC to determine a course of action which may include moving the mercury-contaminated soils away from the river. |
Eileen Olson |
| 10/10/1997 |
Notice of Violation |
Notice of Violation and Request for Interim Corrective Action sent following site visit during which ADEC staff observed hazardous substances stored in flood plain. |
Eileen Olson |
| 1/14/1998 |
Update or Other Action |
The department issued a "Freedom of Information Act Request" to view BLM files. |
Eileen Olson |
| 4/24/1998 |
Meeting or Teleconference Held |
Meeting participants included CSRP staff and legal counsel; BLM staff, management, legal counsel, and a representative of BLM's consultant, Harding Lawson; and by teleconference, EPA, to discuss issues relating to past and planned cleanup activities at the site. The Department's community relations specialist, Grechen Schmidt, and CERCLA specialist Howard Orlean attended. Site cleanup was done in 1994 by BLM without Department involvement under the auspices of CERCLA, as an emergency removal action. However, CERCLA stipulates that an action memorandum be prepared prior to beginning work, and that an administrative record be set up at or near the site for public review. Neither of these requirements appear to have been met. The action memorandum must justify the emergency action based on an imminent and substantial threat to human health or the environment. During the meeting CSRP staff emphasized that an administrative record is required, and that the public notification and participation process should begin as soon as possible. The major issue is that the regulatory status of the excavated, mercury-contaminated soils at the site has not been determined; that is, whether the soils are or could be hazardous waste, or are solid waste. BLM counsel plans to write a letter to EPA requesting a determination of the legal status of the soils by early May, with a response requested as soon as possible. BLM will also send information notifying the community of work planned for the site by early May. CSRP reminded BLM that both the petroleum hydrocarbon contamination in site soils, and the improperly stockpiled petroleum contaminated soils which were excavated in 1994 still need to be characterized. |
Eileen Olson |
| 5/14/1998 |
Meeting or Teleconference Held |
Letter reiterating meeting of April 24, 1998. During the meeting it was established that BLM had not determined the regulatory status of the excavated, mercury-contaminated soils at the site; including whether the soils are or could be hazardous waste, are solid waste, or are regulated by the Department as non-hazardous contaminated media. |
Eileen Olson |
| 5/15/1998 |
Update or Other Action |
ADEC letter to EPA requesting a determination of the regulatory status of soils excavated at the Red Top mercury retort site. |
Eileen Olson |
| 6/3/1998 |
Meeting or Teleconference Held |
ADEC letter issued: Summary of meeting held June 2, 1998. |
Eileen Olson |
| 6/9/1998 |
Meeting or Teleconference Held |
Public meeting held in Aleknagik, hosted by BLM; ADEC staff attended. Also visited site. |
Eileen Olson |
| 6/11/1998 |
Meeting or Teleconference Held |
ADEC letter to BLM: Summary of June 10, 1998 meeting, and Department reporting requirements. |
Eileen Olson |
| 6/26/1998 |
Update or Other Action |
Rec'd Pollution Report (POLREP) #9 from BLM as part of "Red Top Retort Site Flood Response" reporting. Water dropping. |
Eileen Olson |
| 9/11/1998 |
Update or Other Action |
Review letter out for "Revised Work Plan, Additional Site Characterization, Corrective Action and Disposal of Waste Materials, Red Top Retort Site" dated September 9, 1998 and "Disposition of Review Comments"-undated, both prepared by HLA/Wilder JV. |
Eileen Olson |
| 6/3/1999 |
Update or Other Action |
ADEC letter requesting additional site characterization and review of "Remedial Action Report, Red Top Retort Site" dated December 31, 1998. |
Eileen Olson |
| 9/15/1999 |
Update or Other Action |
ADEC approval of "Work Plan and Sampling and Analysis Plan, 1999 Site Characterization" dated August 30, 1999. |
Eileen Olson |
| 9/29/1999 |
Update or Other Action |
AGO received letter proposing settlement, along with the monetary amount to be paid by BLM. |
Eileen Olson |
| 11/10/1999 |
Update or Other Action |
AGO received letter from BLM counsel regarding settlement and concerns about reimbursing ADEC for legal fees (BLM did not "consider all of the claimed legal expenses reasonable"). |
Eileen Olson |
| 2/15/2000 |
Site Characterization Report Approved |
Staff reviewed the"1999 site Characterization Report" for the site, dated December 21, 1999. The report included a recommendation that the Bureau of Land Management (BLM) seek site closure with ADEC-directed institutional controls on the property title. CSRP noted that characterization sampling appears to be adequate and excavation of additional soil at the site may not be necessary, depending on input from the public and future landowners, and upon the Department’s review of additional information requested in the letter. |
Eileen Olson |
| 5/10/2000 |
Update or Other Action |
Issued review letter for Limited Waste Removal Action Report dated November 19, 1999. |
Eileen Olson |
| 8/28/2000 |
Update or Other Action |
AGO received letter from BLM's legal counsel regarding settlement of bills owed by BLM. |
Eileen Olson |
| 12/12/2000 |
Update or Other Action |
AGO received letter from BLM's legal counsel regarding settlement of BLM's bills. |
Eileen Olson |
| 2/28/2002 |
Update or Other Action |
Settlement offer letter prepared and sent with input from AGO. |
Eileen Olson |
| 9/21/2005 |
Update or Other Action |
Letter sent to BLM this date detailing site history and setting forth a list of requirements which need to be completed prior to closure. |
Anne Marie Palmieri |
| 9/26/2005 |
Meeting or Teleconference Held |
DEC staff (Palmieri and Halverson) met with BLM (Larry Beck) to discuss letter and future work at the site. |
Anne Marie Palmieri |
| 8/7/2007 |
Site Characterization Workplan Approved |
Workplan approved this date for fieldwork scheduled to occur later this month (Aug 2007). Three well points will be installed downgradient of the former retort building excavation in order to determine if groundwater is contaminated. The presence or absence of tailings and/or waste rock will be documented. |
Anne Marie Palmieri |
| 9/8/2008 |
Site Characterization Report Approved |
Site characterization report approved this date. 3 groundwater well points were installed downgradient of remaining contamination and the Wood River; all sample results were non-detect. A visual survey was conducted and 18 test pits advanced to determine if waste rock and/or tailings piles are present; none were found. Aerial photointerpretation was conducted to determine if the site is eroding into the Wood River over time; erosion is not occurring at a noticeable rate. |
Anne Marie Palmieri |
| 8/10/2011 |
Cleanup Plan Approved |
Cleanup plan (dated 8/9/11) approved this date. North Wind will excavate approx 40cy of mercury contaminated soil and dispose of it off-site. The intent is that all remaining contamination will be removed. Work should occur in the next few weeks. |
Anne Marie Palmieri |
| 3/13/2012 |
Cleanup Complete Determination Issued |
Cleanup complete letter sent to BLM this date. 39 cubic yards of contaminated soil was excavated and sent to Waste Management's landfill in Oregon. Confirmation sample results were all below 1.4 mg/kg. Unrestricted use of the property is appropriate. |
Anne Marie Palmieri |