Action Date |
Action |
Description |
DEC Staff |
10/7/1992 |
Preliminary Assessment Approved |
Received "Preliminary Assessment, Fort Greely, Alaska, Draft" prepared by CH2M Hill to determine source areas for CERCLA. |
Former Staff |
10/29/1992 |
Site Added to Database |
Suspected contaminants include solvents, POLs, and PCBs. |
Former Staff |
5/16/1994 |
Update or Other Action |
(Old R:Base Action Code = RPL2 - Site Information Request Letter). Staff sent PRP-CS Database Notification Letter to Cristal Fosbrook requesting update/confirmation of information concerning the contaminated site. |
Jeff Peterson |
1/4/1995 |
Site Ranked Using the AHRM |
Initial ranking. |
Jeff Peterson |
10/1/2004 |
Institutional Control Record Established |
In the October 2004 Draft Decision Document Fact Sheets, administrative controls (ACs)were estblished in order to minimize risk to human health and the environment. The site is included in the post’s Geographic Information System (GIS), a tool used in the Dig Permit process for notifying contractors, workers, and base personnel of the potential for contamination to exist at this site. The Dig Permit process is used to prevent installation of water production well(s) through the contaminated area, and prevent removal of contaminated material from the site to off-base locations or to environmentally sensitive areas. If future land disturbance activities at the site encounter contamination, the contaminated material encountered will be properly remediated or disposed of in accordance with applicable regulations. The site will be included in 5-year reviews to periodically verify compliance with the ACs. |
Emily Youcha |
11/26/2004 |
Update or Other Action |
In 1997 test pits were excavated and PAH were detected, benzo(a)pyrene concentrations exceeded ADEC Method Two cleanup levels (21 mg/kg). In 2002, a surface sample collected at or very near BRAC parcel 92 contained DRO at 3,100 mg/kg and a variety of PAH compounds above ADEC Method Two cleanup levels. The site status is considered "unresolved" between ADEC and SMDC. Further investigation into the migration to ground water pathway is needed. Administrative Controls have been established for this site. |
Emily Youcha |
11/26/2004 |
Site Ranked Using the AHRM |
Site re-ranked based on known contamination at site. |
Emily Youcha |
12/20/2004 |
Update or Other Action |
ADEC reviewed a report titled "Comprehensive evaluation of groundwater monitoring program Fort Greely, Alaska". The report discussed the existing monitoring network at Fort Greely and the parameters evaluated in ground-water sampling events. ADEC recommended additional investigation into infiltration and vertical hydraulic gradients. ADEC also recommended additional monitoring wells in the Old Post area and more ground-water monitoring at certain specific sites. |
Emily Youcha |
5/25/2005 |
Meeting or Teleconference Held |
Staff conducted a site visit of Fort Greely. Summer fieldwork is underway and includes soil gas surveys, drilling and sampling several deep boreholes, and installation of at least two new monitoring wells. Staff also attended a RAB meeting where the general public received an update on site work for this and upcoming seasons. |
Emily Youcha |
6/9/2005 |
Site Ranked Using the AHRM |
Changed the Confirmed Release field from 0.5 to 1 based on the samples results indicated in the 11/26/04 Update action Comments. |
Former Staff |
9/30/2005 |
Meeting or Teleconference Held |
Staff particpiated in a Restoration Advisory Board Meeting for Fort Greely on September 28. |
Emily Youcha |
5/22/2007 |
Meeting or Teleconference Held |
Staff attended Interagency Coordination Meeting in Fairbanks. A summary of the past years and future remedial efforts was provided. |
Zachary Richter |
5/23/2007 |
Meeting or Teleconference Held |
ADEC Staff attended a RAB meeting held in Delta Junction. The past years work at Fort Greely was summerized and future work projects were presented. Work at the North and South Tank Farms was highlighted. |
Zachary Richter |
5/23/2007 |
Update or Other Action |
The Alaska Department of Environmental Conservation (ADEC) received the Groundwater Monitoring and Data Analysis Work Plan Fort Greely, Alaska on April 27, 2007. This work plan abides by the 2005 Final Work Plan with modifications to the wells and analytical parameters to be monitored particularly the addition of polycyclic aromatic hydrocarbon analysis at monitoring wells MW-12, MW-13, and MW-14. Additionally, the pump type used in sampling the monitoring wells will be changed by replacing the Grundfos Ready Flow pump with a QED Sample Pro 1.75 inch bladder pump and QED MP10 controller, or equivalent. All other sampling methodology will remain the same as the 2005 Final Plan. The final modification to the 2007 Work Plan is the addition of Volatile Organic Analysis/1,2-dibromoethane monitoring at drinking water wells ECP2 and ISFAC at the missile field. An updated list of wells to be monitored, and the parameter for analysis from each well, for upcoming sampling events has been provided to replace Table 5 of the 2005 Final Work Plan. ADEC has completed its review of this document and has found that the Groundwater Monitoring and Data Analysis Work Plan Fort Greely, Alaska for 2007 adequately meets the requirements set forth in 18AAC75.355, and with the addition of the previously agreed upon amendment, this work plan is approved.
|
Zachary Richter |
7/2/2007 |
Update or Other Action |
The Alaska Department of Environmental Conservation (ADEC) has completed its assessment of the environmental laboratory data and quality assurance requirements as set forth in ADEC Technical Memorandum 06-002 for the Groundwater Monitoring 2006 Analytical Data Report Fort Greely, Alaska, February 2007. The report adequately addresses the requirements set forth by ADEC for both laboratory data packages and Quality Assurance (QA) Summaries, therefore the report is approved. |
Zachary Richter |
3/27/2008 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed. |
Deborah Williams |
11/5/2008 |
Meeting or Teleconference Held |
ADEC staff participated in the Restoration Advisory Board meeting for Fort Greely in Delta Junction. During the meeting, Glen Shonkwiler with the United States Army Space and Missile Defense Command presented the fieldwork that was completed during the 2008 field season at Fort Greely. The 2008 fieldwork included remediating the soil in the biocell at the South Tank Farm (STF); conducting further delineation of the subsurface soils at the STF; installing four groundwater monitoring wells in the Old Post area and downgradient of the STF; completing the investigation at the MOGAS fuel line in the Old Post area; conducting additional survey of the Jarvis Creek Munitions Burial site; and conducting additional investigation of the Building 675 vault. He also presented the work that was planned to be completed during 2009. |
Deborah Williams |
10/21/2009 |
Document, Report, or Work plan Review - other |
ADEC staff reviewed the document titled Draft 2008 Groundwater Monitoring and Data Analysis Report, Fort Greely, Alaska, dated March 2009. The Fort Greely groundwater monitoring program consists of monitoring wells that were installed during investigation activities on FGA from 1997 to the present. DEC approved a comprehensive groundwater monitoring approach in the 2005 Work Plan. Yearly modifications to the 2005 workplan are incorporated as needed to address environmental program objectives. Monitoring well locations and sampling frequency have been chosen to provide site specific monitoring where necessary, and comprehensive coverage for the old post and main cantonment areas of Fort Greely. Currently, a total of 30 wells are included in the groundwater monitoring program: 11 of these are sampled during the spring and fall on even numbered years, two drinking water wells are sampled quarterly, and 17 monitoring wells are sampled semi–annually. This report summarizes the 2008 groundwater monitoring efforts. A letter detailing staff comments has been provided to the Army. |
Tana Robert |
11/13/2009 |
Document, Report, or Work plan Review - other |
Staff reviewed and provided comments on the document titled DRAFT 2008 COMPLIANCE CLEANUP SITES ANNUAL REPORT: MOGAS/DFA Fuel Line at Old Post (BRAC Sites 134, 96, 97, 98, 99, and 100); Building 163 and Former UST Tank Farm (BRAC Site 94); Building 100 Drum Storage (BRAC Site 92); Evergreen Road POL Yard (BRAC Site 102); Dry Wells Located at Buildings 628, 612, and 675 (BRAC Sites 57, 135, and 54); Preconstruction Environmental Survey for Proposed CAC Site FORT GREELY, ALASKA (April 2008) prepared for the US Army Space and Missile Defense Command by ASTS Incorporated. |
Tana Robert |
7/23/2010 |
Site Characterization Workplan Approved |
Approved 2010 IRP Work Plan. Diesel impacted soil will be removed at this site. |
Melody Debenham |
3/20/2013 |
Document, Report, or Work plan Review - other |
Approved the final soil stockpile characterization report documenting sampling of petroleum impacted soils contained in long-term stockpiles and supersacks staged near the landfarm area. The stockpiled soil was generated during remedial actions conducted from 2010 to 2012 at multiple sites at Fort Greely, including BRAC 92. Based on the information presented in the report, and in consultation with the solid waste program, the stockpiled soil is suitable for use as daily cover at the Fort Greely landfill. |
Melody Debenham |
9/4/2013 |
Document, Report, or Work plan Review - other |
Approved the final groundwater sampling work plan for Ft. Greely. As part of the multi-year, post-wide groundwater monitoring program, groundwater samples will be collected from 35 wells. |
Melody Debenham |
4/29/2015 |
Meeting or Teleconference Held |
Attended Restoration Advisory Board Meeting. Proposed work in 2015 includes post-wide groundwater monitoring, decommissioning unused monitoring wells, developing a Land Use Control and Long Term Maintenance Plan, and completing propose plans/no further action documents for 51 sites. |
Melody Debenham |
8/28/2015 |
Document, Report, or Work plan Review - other |
Approved the Final 2014 Groundwater Monitoring and Data Analysis Report documenting the 2014 post-wide groundwater monitoring activities at Fort Greely. Analytical results from four monitoring wells at the BRAC 94 site were above cleanup levels for diesel range organics, gasoline range organics, and/or benzene. Results from one monitoring well at the South Tank Farm site were above the cleanup level for ethylene dibromide. All other results were either non-detect or below the cleanup level, including all supply well results. |
Melody Debenham |
8/28/2015 |
Document, Report, or Work plan Review - other |
Approved the Final 2015 Groundwater Monitoring and Data Analysis Work Plan Addendum for long-term post-wide groundwater monitoring at Fort Greely. Groundwater samples will be collected from 25 monitoring wells and 5 supply wells. |
Melody Debenham |
9/20/2016 |
Document, Report, or Work plan Review - other |
Approved final 2015 groundwater monitoring report. |
Melody Debenham |
12/7/2018 |
Document, Report, or Work plan Review - other |
DEC approved the Final 2016 Groundwater Monitoring and Data Analysis Report, Fort Greely, Alaska (November 2017). The report provides a summary of the 2016 field activities, site background, analytical results and recommendations for future sampling events at Fort Greely, Alaska (FGA). During the 2016 sampling event, 39 wells were sampled at nine site locations. Of those 39 wells sampled, seven wells contained one or more exceedances of the project action limits for diesel range organics (DRO), ethylene dibromide (EDB), benzene and 1,2,4-trimethylbenzene. The FGA monitoring wells will continue to be sampled. |
Erica Blake |
10/30/2019 |
Document, Report, or Work plan Review - other |
DEC approved the Groundwater Sampling and Environmental Support Services Fort Greely, Alaska Final Work Plan (dated October 30, 2019). The purpose of this groundwater monitoring work plan is to guide groundwater sampling activities at selected locations with known or suspected contaminant releases present on Fort Greely, Alaska (FGA). Areas on FGA to be investigated under this work plan are; Robin Road Fuel Spill [Base Realignment and Closure (BRAC) Site 30], Evergreen Road Pipeline Fuel Spill Area (BRAC Site 73), Former Landfills 4 and 5 (BRAC Site 88), BRAC Site 94, BRAC Sites 85N/85S and 133, Tar and Asphalt Disposal Area (TAADA), BRAC Site 92 and 134, Petroleum, oil and lubricant (POL) facility, and South Tank Farm. In addition to collecting groundwater samples and water level measurements, this work plan discusses installation activities for five monitoring wells. The location of these five wells will be provided to DEC in a work plan addendum prior to the spring/summer 2020 work. This work plan describes activities to be conducted fall 2019, and spring/summer 2020. |
Erica Blake |
12/16/2020 |
Meeting or Teleconference Held |
DEC had a teleconference with the Fort Greely Directorate of Public Works (DPW) environmental staff, the U.S. Corp of Engineers, and contractors assisting with the restoration projects to discuss the status of various site cleanup work (specifically discussing sites associated with the Fort Greely Groundwater Monitoring Program). |
Erica Blake |
4/28/2021 |
Meeting or Teleconference Held |
DEC staff attended the 2021 Fort Greely Restoration Advisory Board (RAB) meeting in Delta Junction, Alaska at the Delta Junction City Hall. Updates on fieldwork conducted during 2019 and 2020 were presented to community members, RAB members and Fort Greely staff in attendance. |
Erica Blake |
6/8/2021 |
Document, Report, or Work plan Review - other |
ADEC provided review comments for the "Groundwater Sampling and Environmental Support Services, Fort Greely, Alaska, Draft Groundwater Monitoring Report 2020, Fort Greely, Alaska" (dated April 19, 2021) to the U.S. Army. The document discusses results from the 2020 groundwater sampling and includes updated UFP-QAPP pages for the upcoming 2021 field season. |
Erica Blake |
7/19/2021 |
Document, Report, or Work plan Review - other |
ADEC provided responses to comments for the Groundwater Sampling and Environmental Support Services, Fort Greely, Alaska, Draft Groundwater Monitoring Report 2020, Fort Greely, Alaska (dated April 19, 2021) to the U.S. Army. Sites discussed in the document for a recommended No Further Action, ADEC will review site information for closure separately. A redline version of the document was requested for conducting a comment backcheck. |
Erica Blake |
7/30/2021 |
Document, Report, or Work plan Review - other |
ADEC provided approval for the "Groundwater Sampling and Environmental Support Services, Fort Greely, Alaska, Final Groundwater Monitoring Report 2020, Fort Greely, Alaska" (dated July 29, 2021) to the U.S. Army. The document includes results from groundwater monitoring activities conducted in 2020, and includes work plan pages describing proposed sampling activities for the upcoming 2021 field season. |
Erica Blake |
7/27/2022 |
Document, Report, or Work plan Review - other |
ADEC provided review comments for the Groundwater Sampling and Environmental Support Services Fort Greely, Alaska, Draft Groundwater Monitoring Report 2021, Fort Greely, Alaska (dated June 6, 2022). The document described results from land use control (LUC) inspections, well decommissioning, repair and redevelopment and groundwater sampling activities conducted during the 2021 field season. The document also included updated work plan addendum pages for upcoming 2022 fieldwork. |
Erica Blake |
9/9/2022 |
Document, Report, or Work plan Review - other |
ADEC provided responses to comments for the Groundwater Sampling and Environmental Support Services Fort Greely, Alaska, Draft Groundwater Monitoring Report 2021, Fort Greely, Alaska (dated June 6, 2022) to the U.S. Army. The document described results from land use control (LUC) inspections, well decommissioning, repair and redevelopment and groundwater sampling activities conducted during the 2021 field season. The document also included updated work plan addendum pages for upcoming 2022 fieldwork. Responses to the review comments were received September 7, 2022. All responses were accepted except for one comment regarding decommissioning a monitoring well at the Tar and Asphalt Disposal Area. A draft-final redline version of the final document was requested for review and comment backcheck prior to ADEC providing any approvals on a final version of the document. |
Erica Blake |
9/20/2022 |
Document, Report, or Work plan Review - other |
ADEC provided approval for the "Groundwater Sampling and Environmental Support Services Fort Greely, Alaska, Final Groundwater Monitoring Report 2021, Fort Greely, Alaska" (dated September 16, 2022) to the U.S. Army. Appended to the document were updated work plan pages for the upcoming 2022 field season, and the 2021 land use controls report. ADEC will work with the Army to obtain copies of background studies referenced in the 2021 Groundwater Sampling Report and verify the site boundaries for Landfill #7. With this document approval, the 2022 field work is expected to start September 26, 2022. |
Erica Blake |
2/23/2023 |
Document, Report, or Work plan Review - other |
DEC provided comments for the Environmental Summary Report: FGLY-015 Bldg Drum Storage Area (92), Draft (dated November 8, 2022) to the U.S. Army. The document summarizes site cleanup history for the Building 100 Drum Storage Area (FGLY-015). The U.S. Army is recommending the site be closed with institutional controls (ICs). DEC disagrees the site is ready closure based on the site information showing undelineated soil exceedances to the northeast and southwest, and only one groundwater well (MW-25) present at the site. A comment letter was sent requesting the U.S. Army address the data gaps before the site can be closed. |
Erica Blake |
9/15/2023 |
Long Term Monitoring Workplan or Report Review |
DEC provided review comments for the "Groundwater Sampling and Environmental Support Services Fort Greely Alaska, Draft Groundwater Monitoring Report 2022 Fort Greely, Alaska Dated June 2023" to the U.S. Army. The document describes analytical findings and groundwater monitoring activities conducted in 2022 at Fort Greely, Alaska on multiple sites. Results from land use control/institutional control inspections at several sites are also included in the report. |
Erica Blake |
1/17/2024 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 72685 Former Haz Waste storage area. |
Tim Sharp |
5/31/2024 |
Document, Report, or Work plan Review - other |
DEC reviewed Draft 2023 Long-Term Monitoring (LTM) Report Fort Greely, Alaska April 2024 and provided comments to the U.S. Army. This report details environmental activities performed at multiple sites located at Fort Greely, Alaska (FGA) during September 2023. LTM activities were carried out to comply with the Selected Remedies for the subject sites developed in the 2005 Environmental Sites Decision Document (DD), Fort Greely, Alaska and/or the 2009 Record of Decision (ROD), Nine Installation Restoration Program Sites Fort Greely, Alaska. The objective of the LTM activities was to perform annual groundwater sampling from select monitoring wells managed under the FGA LTM.
|
Carly Jensen |
6/26/2024 |
Long Term Monitoring Workplan or Report Review |
DEC reviewed Final 2023 Long-Term Monitoring (LTM) Report Fort Greely, Alaska June 2024 and provided comments to the U.S. Army. This report details environmental activities performed at multiple sites located at Fort Greely, Alaska (FGA) during September 2023. LTM activities were carried out to comply with the Selected Remedies for the subject sites developed in the 2005 Environmental Sites Decision Document (DD), Fort Greely, Alaska and/or the 2009 Record of Decision (ROD), Nine Installation Restoration Program Sites Fort Greely, Alaska. The objective of the LTM activities was to perform annual groundwater sampling from select monitoring wells managed under the FGA LTM.
Final report and work plan addendum was reviewed and accepted on June 26, 2024. |
Carly Jensen |