Action Date |
Action |
Description |
DEC Staff |
12/1/1993 |
Update or Other Action |
Environmental Compliance Investigation Report. Prepared by Ecology and Environment, Inc. Dated December 1993. 205 pages. (CS Database Updated 3/6/2018) |
Jamie McKellar |
12/1/1999 |
Update or Other Action |
Tank and Pipeline Decomissioning Assessments, Puntilla Lake FAA Station. 163 pages. (CS Database Updated 3/6/2018) |
Jamie McKellar |
1/1/2001 |
Update or Other Action |
Pre-field Planning Document, Release Investigation Plan, Fuel Storage Tank Management Program. Prepared by CH2-OH. Dated January 2001. (CS Database Updated 3/6/2018) |
Jamie McKellar |
6/6/2002 |
Site Added to Database |
DRO. |
Elizabeth Stergiou |
6/11/2002 |
Update or Other Action |
Project management transfered from Eileen Olson to Elizabeth Stergiou. |
Elizabeth Stergiou |
5/21/2004 |
Site Number Identifier Changed |
Corrected Region from 31 to 22. |
Former Staff |
8/22/2005 |
Update or Other Action |
Site File Reviewed: 3 Tanks (20-A-1, 20-A-2, and 20-A-3) and the fuel delivery pipeline were removed in 1999. Elevated levels of DRO are present at each tank area and along most of the pipeline. Additional characterization and petroleum contaminated soil removal is needed. Email sent to FAA. |
Anne Marie Palmieri |
11/22/2005 |
Site Characterization Workplan Approved |
Site characterization workplan approved this date; will be implemented in FY06. |
Anne Marie Palmieri |
8/1/2006 |
Update or Other Action |
Puntilla Lake Release Investigation Work Plan, Revision 1. Prepared by Bristol Construction Services. Dated August 2006. 70 pages. (CS Database Updated 3/6/2018) |
Jamie McKellar |
8/1/2006 |
Update or Other Action |
Site characterization fieldwork is set to begin this month. |
Anne Marie Palmieri |
2/1/2007 |
Update or Other Action |
Puntilla Lake Phase I Release Investigation Report Draft. Prepared by Bristol Construction Services, LLC. Dated February 2007. 196 pages. (CS Database Updated 3/6/2018) |
Jamie McKellar |
4/13/2007 |
Exposure Tracking Model Ranking |
ETM ranking |
Anne Marie Palmieri |
5/1/2010 |
Update or Other Action |
Puntilla Lake Phase 2 Release Investigation. Prepared by Bristol Construction Services, LLC. Dated May 2010. 251 pages. |
Jamie McKellar |
6/22/2010 |
Site Characterization Workplan Approved |
Approved Phase 2 Release Investigation Work Plan to delineate the horizontal and vertical extent of petroleum contamitaion using Ultraviolet Optical Screening Tool (UVOST) with Laser-Induced Fluorescense (LIF) to provide real time field screening data, collecting soil samples for laboratory analysis, and installaing and sampling 5 monitoring wells to determine the presence of petroleum in the groundwater. |
Melody Debenham |
5/14/2012 |
Document, Report, or Work plan Review - other |
Approved the Sampling and Analysis Plan describing the removal of lead-acid batteries near the Non Directional Beacon (NDB) area. An area approximately 20’ by 10’ contains broken lead-acid batteries, which will be removed and transported off site for disposal along with lead contaminated soil. Surface soil metals concentrations will be measured in the field using an x-ray fluorescence detector and confirmation samples will be collected for laboratory analysis. |
Melody Debenham |
4/16/2013 |
Document, Report, or Work plan Review - other |
Received the final report documenting removal of lead-acid batteries and associated lead impacted soil at the Non Directional Beacon area. Broken lead-acid batteries and associated soil were removed from a 16’ by 17’ area and transported offsite for disposal. Field screening was performed using an x-ray fluorescence detector, and confirmation samples were collected for laboratory analysis. Confirmation sample results show lead contaminated soil remains onsite. The FAA will return to the site to perform additional removal actions. |
Melody Debenham |
7/7/2014 |
Document, Report, or Work plan Review - other |
Approved final work plan for soil removal at lead battery area of concern and groundwater sampling at petroleum contamination area of concern. Field screening for lead will be performed with an x-ray fluorescence detector and confirmation samples will be collected and analyzed for lead once removal actions are complete. Groundwater at the petroleum contamination area of concern will be sampled for gasoline, diesel, and residual range organics and benzene, toluene, ethylbenzene, and xylenes. |
Melody Debenham |
11/4/2014 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed for source area id: 79441 name: Battery Disposal Area near NDB |
Melody Debenham |
11/10/2014 |
Document, Report, or Work plan Review - other |
Approved final 2014 Groundwater Monitoring and Soil Remediation Report. Groundwater sampling results shows DRO, GRO, and benzene remain above cleanup levels. Approximately 1.5 cubic feet of lead contaminated soil was removed from the battery disposal area and transported offsite for disposal. Confirmation sampling shows remaining concentrations of lead are below the cleanup level. |
Melody Debenham |
6/10/2021 |
Document, Report, or Work plan Review - other |
Draft WP for 5 sites received. Comments sent 06/16/2021.Acceptance of RTC sent 06/25/2021. Approval letter for final WP sent 07/06/2021. |
Shonda Oderkirk |
12/6/2021 |
Document, Report, or Work plan Review - other |
Draft Groundwater Monitoring for FAA Stations Bettles, Puntilla, Chena NDB. Report was supposed to include Yakataga and St. Mary's, but they weren't able to get out there due to COVID restrictions. 1/5/2022 Comments sent. DEC RTC sent 2/8/2022. 03/01/2022: received Final report copy. Approval letter sent 03/07/2022. |
Shonda Oderkirk |
12/6/2021 |
Document, Report, or Work plan Review - other |
Draft Groundwater Monitoring for FAA Stations Bettles, Puntilla, Chena NDB. Report was supposed to include Yakataga and St. Mary's, but they weren't able to get out there due to COVID restrictions. 1/5/2022 Comments sent. DEC RTC sent 2/8/2022. 03/01/2022: received Final report copy. Approval letter sent 03/07/2022. |
Shonda Oderkirk |