Action Date |
Action |
Description |
DEC Staff |
7/22/1998 |
Update or Other Action |
Letter to RP regarding solid waste and removal of hazardous substances. |
Renee Evans |
8/18/1999 |
Meeting or Teleconference Held |
Meeting with Contractor and Kris McCumby regarding what would be needed for a site assessment. |
Renee Evans |
11/24/1999 |
Site Added to Database |
Petroleum, possibly hazardous substance. |
Renee Evans |
11/30/1999 |
Site Ranked Using the AHRM |
Site ranked but needs to be reranked after site characterization completed. |
Renee Evans |
8/3/2000 |
Update or Other Action |
Site Screening - sent to Bill Janes. |
Renee Evans |
7/10/2002 |
GIS Position Updated |
Changed the Latitude, Longitude, Method Accuracy, Accuracy and Unit fields. |
Heather Goldman |
5/3/2004 |
Update or Other Action |
NTP to conduct Brownfield Assessment on property approved. Contract awarded to Weston Solutions, Inc. to conduct phase 1 and limited release investigation across the property. |
John Carnahan |
5/11/2004 |
Brownfields Award |
Site determined to meet Brownfield inclusion criteria by EPA and approved for BF Site Assessment through State Cooperative Agreement funding. FY 2004 SO CIP funds $57,264 awarded to Fairbanks North Star Borough for a phase I ESA and site characterization report for the Former Universal Recycling. Current status: Project led to the procurement of two additional EPA grants totaling $400,000. |
John Carnahan |
6/1/2004 |
Update or Other Action |
Quality Assurance Program Plan (QAPP) approved by the EPA via email to DEC. The QAPP for the Universal property was reviewed by EPA's Quality Assurance Officer, Don Methany, and no deficiencies were noted and overall approval was recommended. |
John Carnahan |
7/23/2004 |
Preliminary Assessment Approved |
Received Site Characterization Report for site. Recommendations for additional characterization. GW impacts unconfirmed. Various potential soil contaminants. |
John Carnahan |
6/29/2005 |
Update or Other Action |
Phase II Site Assessment work plan received. |
Kim DeRuyter |
8/4/2005 |
GIS Position Updated |
Double checked location due to inclusion into potential Brownfield status. Coordinates look good, updated accuracy and datum fields. |
Torsten Ernst |
11/22/2005 |
Meeting or Teleconference Held |
Meet with FNSB represenatives to discuss project workplan and status. Discuss potential cleanup grant application. |
John Carnahan |
5/26/2006 |
Update or Other Action |
Received call from Tami Sheehan with the FNSB to report that their contractor was going to be ready to move materials from the stie and work with overpacks. They are coordinating with EPA as appropriate. |
John Carnahan |
8/28/2006 |
Meeting or Teleconference Held |
Met with FNSB, consultant (Nortech) and teleconference with Susan Morales with EPA to discuss the components of EPA's ABCA requirement (Analyses of Brownfield Cleanup Alternatives). The components will generally meet the state requirements for developing a CAP for review and approval. For the most part, CS for the site will result in debris removal and disposal to the availability of funding. |
John Carnahan |
3/20/2007 |
Update or Other Action |
Received Analysis of Brownfield Cleanup Alternatives (ABCA) from FNSB consultant, dated 3/19/07 (copy to file). Received copy of Community Involvment Plan (CIP). |
John Carnahan |
6/12/2008 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed. |
John Carnahan |
7/28/2008 |
Site Characterization Workplan Approved |
Discussed workplan action items with FNSB and consultant regarding excavation and sampling associated with ash pit location, and concrete trench area. Based on sample information to date, excavation and removal of limited amount of potential contamination will be completed, with subsurface discrete sampling at limits of excavation. Sampling will be for DRO and dioxin. Upon successful closure sampling (below DEC MCLs) at these locations, the site will be in position for closure determination. |
John Carnahan |
10/25/2008 |
Update or Other Action |
DEC received the Phase II Environmental Site Assessment Site Characterization Report for the Former Universal Recycling Facility. During the assessment over 50 drums and five tons of lead-acid batteries along with other potentially hazardous wastes were identified on the site. As of the date of this report, three primary surface drum and debris removal efforts had been completed. The initial drum field characterization was completed in the fall of 2005 and the drums were removed in May 2007. Disposal of surface wastes and debris were completed in October 2007 prior to the assessment activities to allow access to the entir site. The second set of drums was characterized in November 2007 and removed in March and April 2008. After this work, the consultant recommended that no additional debris or drum removal is necessary.
A total of 63 soil borings were installed and 36 samples were collected to determine if contamination remained at the site. Some areas of concern at the site included the following: 1. Cutout area in the concrete slab in the southeastern portion of the site. This area contained levels of DRO and dioxin slightly above cleanup levels. A total of 13 cubic yards of mixed burned debris and ash were excavated from this area. After excavation and sampling, the consultant recommended additional excavation from this area.
2. The presence of surface ash that may be related to burn barrels and/or an incinerator. The larger location with surface ash was located on the east side of the site (450 square feet). Assessment was completed in this area in 2007 and 2008 that included the excavation of 35 cubic yards of surface ash mixed with coal ash. Sampling indicated additional excavation of approximately 5 cubic yards in this area.
Two groundwater sampling events have been completed at this site: one in 2004 and 2007. The data from 2004 is unusable because the data was not from the water table. In 2007, the groundwater was sampled at five locations and no contamiants of concern were observed near DEC regulatory limits. |
Deborah Williams |
12/4/2009 |
Site Visit |
Drive by site to see status of lot. |
John Carnahan |
1/14/2010 |
Update or Other Action |
DEC received the Final Cleanup Report for the Former URI Facility dated December 28, 2009. According to the report numerous waste streams and debris were removed from the property. A 10,000-gallon tank, 7 plastic totes of lead-acid batteries were disposed of properly. A total of 52 supersacks of contaminated soil and ash were disposed of by Emerald as non-hazardous wastes.
At the completion of the assessment activities, two locations had contaminant concentrations above DEC cleanup levels. Nortech excavated soil in these two areas: six supersacks of soil was excavated from the former surface ash area and one primary sample and a field duplicat were collected from the limits of the excavation. The metals and dioxin concentrations at this location were below DEC cleanup levels. Three supersacks of soil were excavated from the southern end of the concrete cutout. One sample was collected from the limits of the excavation. The dioxin concentrations were below DEC cleanup levels. No additional excavation or sampling was considered necessary or recommended to address these areas. |
Deborah Williams |
3/30/2010 |
Meeting or Teleconference Held |
Meeting with FNSB representatives and consultant on closure determination. |
John Carnahan |
3/31/2010 |
Cleanup Complete Determination Issued |
|
John Carnahan |