Action Date |
Action |
Description |
DEC Staff |
5/1/1993 |
Preliminary Assessment Approved |
(Old R:Base Action Code = SA1 - Phase I Site Assessment (General)). S&W site assessment report for replacement sewer line revealed soil and GW contamination in 3 of 32 borings. Free product found in one well point. Site capped, but is up-gradient from numerous LUST sites currently under investigation. |
Cindy Thomas |
5/1/1993 |
Update or Other Action |
(Old R:Base Action Code = NOR - Notice of Release Letter (LUST)). Sent NORL to FIA requesting Interim Corrective action and site assessment plan. Should measure and recover free product, retain consultant to do SA, install and sample a series of monitoring wells, all within the sampling parameters of the Airport Industrial Road users group. Should notify ADEC of intent once SA is confirmed. |
Cindy Thomas |
6/30/1993 |
Site Added to Database |
Jet Fuel contamination. File # 100.38.082. |
Cindy Thomas |
7/26/1993 |
Site Ranked Using the AHRM |
Insufficient data to score. |
Former Staff |
5/18/1994 |
Site Ranked Using the AHRM |
Ranked. |
Former Staff |
6/29/1994 |
Update or Other Action |
(Old R:Base Action Code = RPL2 - Site Information Request Letter). Sent PRP-CS Database Notification Letter to RP requesting update and more environmental information concerning contaminated site. Alan Braley returned information form for the site. |
Jeff Peterson |
1/17/1995 |
Update or Other Action |
SITE SUMMARY: FIA has failed to proceed with investigation for GW contamination. Consider enforcement action. FIA is trying to set up term contract. Free product discovered in 93 during sewer line installation. Site is upgradient from Airport Land Users Group Area and should be investigated in summer of 1995. Source of contamination unknown. |
Cindy Thomas |
7/10/2002 |
GIS Position Updated |
Changed the Latitude, Longitude, Method Accuracy, Accuracy and Unit fields. |
Heather Goldman |
8/12/2002 |
Update or Other Action |
Update: An Expidited Site Assessment was completed in 1999. Soil, soil gas, and groundwater samples were collected to delineate the separate and dissolved-phase plumes. Free product has been identified around the low point drain, Valve Pit #1 and Valve Pit #2. Dissolved plumes were also observed around a fuel tank south of the ARFF Maintenance Facility. Preliminary risk-based cleanup levels were also developed. Airport Industrial Road proposed as point of compliance. |
Janice Wiegers |
8/13/2002 |
Update or Other Action |
Product recovery report for 2001/2002 winter submitted. Approximately 7 gallons recovered from low point drain (RW-1 and RW-2) and 1.2 gallons from Valve Pits (MW-6 and MW-7). Groundwater elevations throughout the winter were higher than normal. |
Janice Wiegers |
12/4/2002 |
Update or Other Action |
ADEC approves cessation of product recovery at valve pits based on limited recovery. |
Janice Wiegers |
1/13/2003 |
Site Ranked Using the AHRM |
Preliminary ranking. |
Deborah Williams |
3/17/2003 |
Update or Other Action |
Fall 2002 groundwater monitoring report submtited. MW-34 was installed north of Airport Industrial Road to monitor for chlorinated compounds. Trichlorofluoromethane was the only compound detected. |
Janice Wiegers |
3/28/2003 |
Update or Other Action |
NFRAP request submitted - site under review. |
Janice Wiegers |
6/25/2003 |
Update or Other Action |
Product recovery report submitted. Groundwater levels decreased to within 1.5 feet of the lowest observed elevation (in 2000). Product did not accumulate in valve pits enough to warrant recovery. Only one liter of product was recoverd from the low point drain during a rebound test. |
Janice Wiegers |
7/29/2003 |
Meeting or Teleconference Held |
Met with DOT to discuss monitoring. Petroleum monitoring will be reduced to MW-25, MW-15, MW-18, MW-33, MW-28, and MW-32. MW-11, MW-12, and MW-34 will continue to be monitored for chlorinated solvents. |
Janice Wiegers |
7/27/2004 |
Meeting or Teleconference Held |
Met with DOT and Oasis to discuss NFRAP request and provide comments from the ADEC risk assessor for alternative cleanup levels proposed in the 1999 Expedited Site Assessment/Release Investigation. FIA will address comments before further consideration is given to a NFRAP. Solvent issues will be addressed in a separate site as the hydrant fuel line is not the source of this contamination. Also clarified that petroleum contamination in from the hydrant fuel line is regulated under the LUST regulations, as previously agreed on. |
Janice Wiegers |
12/21/2004 |
Update or Other Action |
Groundwater monitoring report submitted for drainage pond investigation. Tetratchloroethene, trichloroethene, cis-1,2-dichloroethene, and vinyl chloride remain above cleanup levels in MW-11. A trend analysis of the 1999 to 2004 data indicates that the solvent concentrations in MW-11 may be slightly increasing - although the plume is believed to be stable. Oasis recommends installation of an additional monitoring well and replacement of MW-11. |
Janice Wiegers |
8/17/2005 |
Update or Other Action |
Site name changed from FIA- Hydrant Fuel System to FIA - Drainage Pond. This site will be used to track solvents that were identified during investigation of the hydrant fuel releases. The petroleum issues associated with the hydrant fuel line will now be tracked in the LUST database under Event 2908. |
Janice Wiegers |
12/16/2005 |
Update or Other Action |
Groundwater monitoring and well removal report submitted. Wells MW-1, 3, 6, 7, 8, 13, 14, 16, 17, 19, 20, 24, and 26 were decommissioned. Before decommissioning, groundwater samples were analyzed for BTEX, GRO, and DRO from MW-1R, MW-19, MW-20, MW-24, and the lawn watering well. MW-1R contained DRO above cleanup levels, so it was not removed. No contaminants were found in the lawn watering well. The firefighting well at the Airport Rescue and Firefighting building was not sampled because it is not used and DOT plans to decommission it. All remaining wells were resurveyed for elevation.
|
Janice Wiegers |
12/19/2005 |
Update or Other Action |
Further VOC Characterization at Former Drainage Pond, report received. Tetratchloroethene, trichloroethene, cis-1,2-dichloroethene, and vinyl chloride remain above cleanup levels in MW-11R, which replaced MW-11 due to poor recharge. This well was sampled at the 15, 25, and 34.5 feet. The highest concentrations of tetratchloroethene, cis-1,2-dichloroethene, and vinyl chloride were reported at the 34.5 foot depth. The report recommends reinstall of MW-29 which is no longer usable, new MW's further downgradient of MW-34 and 35, evaluation of natural attenuation of chlorinated solvents, and use of passive diffusion membrane sampling in MW-11R. |
Kim DeRuyter |
10/20/2006 |
Site Characterization Workplan Approved |
Site Characterization Work Plan submitted by FIA, prepared by Oasis. 54 soil gas modules will be placed in a grid pattern covering the site, and the area north of Airport Industrial Road. PCE and TCE were observed to increase in concentration at a depth of 35 feet in MW-11R during a 2005 sampling event. Passive diffusion bag samplers will be used in MW-11R to determine if the 2005 data is real or an artifact of the low flow sampling method employed at that time. Groundwater samples will be collected from the existing wells, two new wells downgradient of MW11-R, and replacement wells for MW-29 and MW-30. |
Kim DeRuyter |
10/20/2006 |
Site Number Identifier Changed |
Contamination was first discovered at this site in 1993 during construction of a new storm sewer. Further site characterization efforts lead to the discovery of free product associated with the Hydrant Fuel Line. This contamination was tracked in the LUST database under event ID 3016. The Hydrant Fuel Line site achieved a ‘no further remediation planed status’ in February 2006. To differentiate the solvent contamination at the Former Drainage Pond from the Hydrant Fuel line the file number has been changed to 100.38.188. Refer to file # 100.38.128 and LUST event ID 3016 for historic site information. |
Kim DeRuyter |
12/28/2006 |
Update or Other Action |
OIT Certificate of RCRA Exemption forms received from OASIS. Purge water contained 8.66 ug/L benzene, and low levels of other solvents. |
Kim DeRuyter |
10/10/2007 |
Site Characterization Report Approved |
Approved work plan for source characterization near monitoring well MW-11R and annual monitoring at six monitoring wells. Goal is to delineate the extent of PCE contaminated soil. Natural attenuation monitoring will also be included in report. |
Neal Everson |
11/27/2007 |
Update or Other Action |
Reviewed report of Further VOC Characterization dated 26 Mar 2007. The soil gas survey and gw monitoring results helped delineate the area of chlorinated compound contamination which appears to be relatively small and mostly confined to area around MW-11R. Results of work from fall 2007 work plan will arrive shortly. |
Neal Everson |
12/28/2007 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed. |
Neal Everson |
6/18/2009 |
Site Characterization Report Approved |
DEC reviewed the 2008 Groundwater Monitoring Report and Feasibility study by Oasis Env. 3 MWs were sampled, including nested well MW-11R with Passive Diffusion Bags. MW-11R remains the only well with concentrations of VOCs exceeding cleanup levels. MW-11R contained PCE, TCE, cis-1,2-DCE and vinyl chloride above cleanup levels. Oasis recommends additional characterization of source area by 1. installing dataloggers, 2. determine vertical distribution of soil contamination, 3. install new groundwater monitoring wells to better delineate gw plume, 4. collect discrete gw samples from depth to verify MW-11R sampling results. Feasibility study evaluates remediation alternatives. Recommended approach is substrate addition (HRC) to stimulate reductive dechlorination by MNA after further site characterization. |
Neal Everson |
9/14/2009 |
Update or Other Action |
Project manager changed to Ann Farris. |
Janice Wiegers |
10/30/2009 |
Meeting or Teleconference Held |
Met with env. mgr for airport as part of review of whole airport. Drainage pond is one of the priorities for FY10 for both DOT and DEC. She will have new term contractors by January to followup on the feasibility study completed this year and work on a rod. |
Ann Farris |
6/20/2011 |
Document, Report, or Work plan Review - other |
DEC received the Additional Characterization and Groundwater Monitoring Report from Oasis. Additional delineation of chlorinated solvents was completed. Solvents appear to be confined to the property. |
Tamara Cardona-Marek |
1/30/2012 |
Document, Report, or Work plan Review - other |
DEC received the Groundwater Elevations from Fall 2010 to Fall 2011 report from Oasis. Report suggests that groundwater changes direction (as much as 180 degrees) during part of the year. |
Tamara Cardona-Marek |
2/1/2012 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 72901 Former Drainage Pond. |
Tamara Cardona-Marek |
10/14/2013 |
Update or Other Action |
Site symbol visually adjusted using ArcGIS and documents from the file. 10/14/13; MLB. 64.813852, -147.873181. |
Michelle Barnes |
11/6/2013 |
Document, Report, or Work plan Review - other |
DEC reviewed and commented on the 2013 Drainage Pond work plan for groundwater monitoring. |
Robert Burgess |
11/8/2013 |
Site Characterization Workplan Approved |
DEC approved the Drainage Pond Work Plan following comment resolution. |
Robert Burgess |
5/13/2015 |
Document, Report, or Work plan Review - other |
DEC received and reviewed the 2013 FIA Drainage Pond Site Groundwater Monitoring Report-Final. The report describes the groundwater sampling activities that took place in 2013, including well inspection. Currently contaminants exist in well MW-11R but were not detected in other wells in 2013. However, some wells were frozen or damaged and could not be sampled. Some wells at the site have been damaged or destroyed; existing wells will be repaired and additional sampling will take place in 2015. |
Robert Burgess |
4/11/2016 |
Update or Other Action |
A letter was sent to the Airport Environmental Manager referencing several sites at the Fairbanks Airport. The letter included a statement urging the airport to continue work at the drainage pond site, which did not take place in 2015 due to funding problems. |
Robert Burgess |
5/26/2016 |
Meeting or Teleconference Held |
DEC met with the airport environmental manager to discuss several sites at the Fairbanks airport. The environmental manager indicated that monitoring will continue this field season. |
Robert Burgess |
5/8/2017 |
Document, Report, or Work plan Review - other |
DEC reviewed and approved the 2017 Groundwater Monitoring Work Plan which describes the sampling of several groundwater monitoring wells at the site. |
Robert Burgess |
1/23/2018 |
Meeting or Teleconference Held |
Met with FAI environmental manager to discuss several sites. For the drainage pond, the discussion included whether additional delineation and remediation is needed. Currently, the airport budget being used for PFAS plume investigation is a potential barrier to additional work at the site, however FAI stated that the drainage pond site is a priority. |
Robert Burgess |
1/23/2018 |
Document, Report, or Work plan Review - other |
DEC received the 2017 Groundwater Monitoring Report describing sampling and well surveys conducted during 2017 field season. Some of the monitoring wells were destroyed or missing. Existing wells were repaired as necessary and surveyed for groundwater flow. Samples were taken from 6 wells that were in good condition. Chlorinated compounds were detected above cleanup levels and consultants reported a small but persistent source remains in the subsurface. |
Robert Burgess |
3/12/2019 |
Meeting or Teleconference Held |
DEC staff and the DOT/FIA Environmental Manager to discuss airport priorities regarding contaminated sites located at the airport. For the drainage pond, additional site characterization was discussed and the need for additional work. The Environmental Manager indicated they have retained environmental consultants and would prepare a work plan. |
Megan Roberts |
3/28/2019 |
Workplan Requested |
DEC provided comments to the 2017 Groundwater Monitoring Report and requested additional soil and groundwater characterization. Work plan was requested. |
Megan Roberts |
5/15/2019 |
Update or Other Action |
DEC received response to comments indicating the airport has contracted new environmental consultants and will address the site characterization requirements in a future work plan. |
Megan Roberts |
11/29/2019 |
Site Characterization Workplan Approved |
DEC approved the 2019 Drainage Pond Groundwater Monitoring Work Plan after comment resolution. |
Rebekah Reams |
2/18/2020 |
Meeting or Teleconference Held |
DEC met with FIA Environmental Manager and Jacobs personnel to discuss additional characterization of contamination in soil and groundwater at the site. |
Rebekah Reams |
5/1/2020 |
Meeting or Teleconference Held |
DEC staff met with the FIA Environmental Manager to provide site summaries of contaminated sites located on airport property, to discuss closure with institutional controls on airport property, and plan for future work on airport lead sites. |
Rebekah Reams |
6/18/2020 |
Document, Report, or Work plan Review - other |
Revised 2019 Groundwater Monitoring Report Submitted. This report documents groundwater monitoring conducted at 6 monitoring wells (MW-11R, MW-34, MW-38S [shallow], MW-
38D [deep], MW-39, and MW-40) in December 2019. Highest concentration of contaminants were present in MW-11R. Analytical results indicated four of the six wells (MW-11R, MW-38S,MW-39, MW-40) had analytes above DEC cleanup levels. All analytes were below cleanup levels or not detected in two of the monitoring wells (MW-34, MW-38D). Depth to water 7.04-9.2 feet below ground surface. Groundwater flow direction to the west.
|
Rebekah Reams |
7/24/2020 |
Update or Other Action |
Deferment of site characterization activities has been approved through February 2021 due to the far-reaching effects of COVID-19 and available resources being devoted to address higher priority sites. Biennially groundwater monitoring is scheduled to continue and the Fairbanks International Airport has established plans to update the DEC on site developments in February 2021. |
Rebekah Reams |
9/4/2020 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 72901 Former Drainage Pond. |
Rebekah Reams |
2/9/2021 |
Meeting or Teleconference Held |
DEC met with FAI Environmental Manager to discuss deferred site characterization work and path forward. |
Rebekah Reams |
10/6/2021 |
Document, Report, or Work plan Review - other |
DEC approved the 2021 Drainage Pond Groundwater Monitoring Work Plan following comment resolution. This work plan proposes to sample groundwater at monitoring wells MW-11R, MW-34, MW-38S, MW-38D, MW-39, and MW-40 for chlorinated solvents and PFAS and monitoring wells MW-30, MW-11R, and MW-34 for monitored natural attenuation parameters. |
Rebekah Reams |
3/11/2022 |
Offsite Soil or Groundwater Disposal Approved |
DEC approved transport of 30 gallons of investigation derived waste generated in October 2021. |
Rebekah Reams |
8/4/2022 |
Document, Report, or Work plan Review - other |
DEC reviewed the 2021 Drainage Pond Groundwater Monitoring Report which documents groundwater sampling conducted in October 2021 at MW-11R, MW-34, MW-38S, MW-38D, MW-39, and MW-40. DEC provided correspondence in response to this report which highlights the need for additional soil and groundwater characterization at this site. |
Rebekah Reams |
8/4/2023 |
Document, Report, or Work plan Review - other |
ADEC approved the 2023 Drainage Pond Groundwater Monitoring Work Plan which outlines plans to complete groundwater sampling at MW-11R, MW-34, MW-38S, MW-38D, MW-39, and MW-40 in August 2023. |
Rebekah Reams |
2/6/2024 |
Offsite Soil or Groundwater Disposal Approved |
DEC approved offsite transport and disposal of approximately 10 gallons of water investigation derived waste generated during the 2023 groundwater monitoring event. |
Rebekah Reams |
2/15/2024 |
Long Term Monitoring Workplan or Report Review |
DEC reviewed the revised 2023 Drainage Pond Groundwater Monitoring Report which documents groundwater sampling conducted in August 2023 at monitoring wells MW-11R, MW-34, MW-38S [shallow], MW-38D [deep], MW-39, and MW-40. Samples were analyzed for benzene, tetrachloroethylene (PCE), trichloroethylene (TCE), cis-1,2-dichloroethylene (DCE), trans-DCE, vinyl chloride and natural attenuation parameters. The highest contaminant concentrations were observed at MW-11R, MW-40, and MW-38S. Depth to groundwater was 4.09 to 6.00 feet below ground surface and groundwater flow direction was to the southeast. Additional site characterization will be completed during the next biennial groundwater monitoring event, including installing temporary well points and advancing soil borings to define the extent of contamination, determine if contamination is confined to the lot boundary, and evaluate if there is a potential source present in the subsurface (buried asphalt was identified in the vicinity of MW-38 during the 2010 site characterization event). |
Rebekah Reams |