Skip to content Skip to content

Site Report: ConocoPhillips West Sak River State 1

Site Name: ConocoPhillips West Sak River State 1
Address: Kuparuk Industrial Camp,, 1 Mile East, Deadhorse, AK 99734
File Number: 300.38.226
Hazard ID: 1962
Status: Cleanup Complete - Institutional Controls
Staff: IC Unit, 9074655229 dec.icunit@alaska.gov
Latitude: 70.339401
Longitude: -149.541090
Horizontal Datum:WGS84

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

One gravel pad boring DRO and RRO. Half of pad is impacted by low-level hydrocarbons. One off-pad tundra soil sample showed concentrations of DRO 2 pore water samples collected off NW corner showed elevated DRO.

Action Information

Action Date Action Description DEC Staff
5/25/2004 Meeting or Teleconference Held DEC, ConocoPhilips & Weston met to discuss pending charaterization work plan & future work planned for summer 2004. Linda Nuechterlein
8/6/2004 GIS Position Updated Topozone. NAD27. Sarah Cunningham
8/6/2004 Site Added to Database DRO and RRO. Sarah Cunningham
8/9/2004 Site Characterization Workplan Approved Final Site Charaterization Work Plan approved. Work tentatively scheduled to begin around August 19, 2004. Linda Nuechterlein
7/13/2005 Site Ranked Using the AHRM Low priority. Sarah Cunningham
3/1/2007 Update or Other Action Received WSRS 1 Site Characterization and Cleanup Plan. Samples were collected from boreholes in 2004 and indicate DRO concentrations up to 19,000 mg/kg at 2.0 ft bgs near the center of the pad. Two areas of historic hydrocarbon contamination have been identified and partially excavated prior to the 2004 investigation. The site cleanup plan specified three areas of contaminated soil for removal, A,B,and C. Contaminated soil wiil be taken to G&I. Bill O'Connell
8/21/2007 Update or Other Action Site visit was made by both CS and Reserve Pit staff during the Conoco Agency visit on Aug. 21st. Site is listed on Charter D.3(Reserve Pit) list but not on Charter D.2 list. There is gravel pad HC contamination and Conoco plans to address both pad and reserve pit issues in 2008 . Linda Nuechterlein
12/21/2007 Update or Other Action Received Plan of Operations and Permit Applications for WSRS 1, which includes an updated CAP and SAP. Approximately 6,000 cy of petroelum impacted soil will be excavated from four areas: A, B, C, and D, that were identified during site investigation activities. Soil will be field screened and segregated into clean, restricted use, and contaminated stockpiles. The stockpiles will be sampled again, clean gravel will be used as backfill, contaminated gravel will be transported to G&I and restricted use gravel will be transported to an approved stagin area for authorized re-use at a later date. Bill O'Connell
12/21/2007 Update or Other Action Received results from samples collected from thermokarst troughs along the SE corner of the pad to confirm previous sampling results that showed elevated DRO concentrations. Samples did not contain hydrocarbon concentrations indicative of contamination, so this area will not be addressed during the 2007 corrective action. Bill O'Connell
2/22/2008 Exposure Tracking Model Ranking Bill O'Connell
2/22/2008 Exposure Tracking Model Ranking Initial ranking with ETM completed. Bill O'Connell
9/10/2008 Site Visit Site visit today. Pad removed in winter 2008. Area is fairly wet, with minor sheening noted along former reserve pit, but not on gravel pad. Bill O'Connell
11/19/2008 Document, Report, or Work plan Review - other Received West Sak #1 Completion Report. This pad had apparently been impacted by a previous diesel spill that was partially cleaned up. Using data collected during the Phase II investigation, gravel was segregated into contaminated (DRO > 2,000 mg/kg), restricted use (DRO > 200 mg/kg < 2,000 mg/kg)and clean (DRO < 200 mg/kg). Contaminated gravel was transported to the G&I plant at DS 4 and restricted use and clean gravel were used to backfill the reserve pit, with restricted use gravel encapsulated by clean gravel. Additional clean gravel and a small amount of restricted use gravel was trasnported to DS 1C and used as backfill in the south reserve pit. During removal of the gravel pad, it was discovered that DRO contamination had infiltrated into the underlying tundra to such a depth that removal would have compromised the thermal stability of the area, so excavation was stopped in these areas in consultation with ADEC. Composite confirmation samples collected following removal of the pad contained DRO above the ADEC cleanup level. Several samples contained DRO between 200 mg/kg and 1,000 mg/kg, with three samples containing DRO at 2,620 mg/kg, 3,910 mg/kg, and 37,700 mg/kg. The highest DRo concentration was found in a sample collected adjacent the former wellhead after excavation into the native tundra was halted. Select samples were also analyzed for BTEX and PAHs; none were detected above ADEC cleanup levels. Any area where DRO concentrations exceeded 200 mg/kg was covered with extra overburden to minimize the exposure risk and encourage freeze back of the impacted areas. Bill O'Connell
1/13/2009 Cleanup Complete Determination Issued The Alaska Department of Environmental Conservation, Contaminated Sites Program (ADEC) has completed a review of the environmental records associated with ConocoPhillips West Sak River State 1 located in the Kuparuk Oilfield on the North Slope of Alaska. Based on the information provided to date, it has been determined that the contaminant concentrations remaining on site do not pose an unacceptable risk to human health or the environment and no further remedial action will be required as long as the site is in compliance with established institutional controls. Bill O'Connell
1/13/2009 Institutional Control Record Established Institutional Controls established and entered into the database. Bill O'Connell
12/3/2009 Document, Report, or Work plan Review - other Reviewed rehab progress report for WSRS 1. The site is stable and ready for revegetation. Bill O'Connell
1/13/2012 Update or Other Action Land use update in accordance with 2008 Cleanup Complete with Institutional Controls- Land use has not changed since issuance of closure letter Bill O'Connell
6/12/2012 Institutional Control Compliance Review An IC review was conducted on this site and the staff assigned was changed from Bill O'Connell to IC Unit. Evonne Reese
3/8/2013 Institutional Control Update Reviewed 2012 West Sak River State 1 rehabilitation progress report. Ponded surface water covered a significant portion of the pad during the 2012 inspection. Sheen was not noted, but the report recommended specifically checking for sheen during the next assessment. The report indicates successful rehabilitation is anticipated within an acceptable timeframe. Bill O'Connell
12/4/2014 Update or Other Action Staff name changed from IC Unit to McLoone. Evonne Reese
9/28/2016 Update or Other Action At this time, the project manager chooses to retain management of this site which has institutional controls. IC Unit
2/3/2021 Institutional Control Compliance Review IC compliance review started. A combined letter for all ConocoPhillips sites with ICs will be issued in early 2021 and land use will be verified. Evonne Reese
3/18/2024 Institutional Control Update DNR-SAIL added as affiliate (Office of Primary Responsibility). For DNR LAS information: ADL# 420769 Jennifer McGrath
4/4/2024 Document, Report, or Work plan Review - other Received the Progress Report for Rehabilitation of West Sak River State 1 Exploratory Wells Site. Additional vegetative cover is needed for the Capped Flare Pit and Former Gravel Pad and further monitoring or vegetative efforts may be done. Lisa Krebs-Barsis

Contaminant Information

Name Level Description Media Comments
DRO > Human Health/Ingestion/Inhalation Soil

Control Type

Type Details
Signed CS Determination

Requirements

Description Details
Advance approval required to transport soil or groundwater off-site.

No associated sites were found.

Missing Location Data

Because the GIS location data for this site has not been entered, we cannot direct you to its position on the map. Click "Continue" to proceed to the Contaminated Sites Web Map or "Close" to return to the site report.
Continue     Close