Site Report: USCG Kodiak Bldg 24 Steam Plant

Site Name: USCG Kodiak Bldg 24 Steam Plant
Address: Nyman Peninsula, Kodiak, AK 99619
File Number: 2601.38.057
Hazard ID: 2088
Status: Active
Staff: Curtis Dunkin, 9072693053 curtis.dunkin@alaska.gov
Latitude: 57.731752
Longitude: -152.505914
Horizontal Datum:WGS84

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

Petroleum contaminated soils due to the release of approximately 900 gallons of JP-5.

Action Information

Action Date Action Description DEC Staff
8/30/1996 Update or Other Action Plan for bioremediating some of the contaminated soils denied until additional information is provided. Don Fritz
9/20/1996 Site Added to Database Petroleum contamination. Don Fritz
9/20/1996 Site Ranked Using the AHRM Site ranked. Don Fritz
6/22/2004 Update or Other Action File number assigned and entered into the Fileroom DB and CS DB. Alyce Hughey
12/14/2004 Update or Other Action Reviewed the reports and file. Sent an email to Tim Stott, USCG Seattle, requesting clarification, any additional data and reports and if any ADEC closures had been issued. Awaiting a response prior to making a risk management decision tha tis protective of human helath and the environment. Donald Seagren
9/15/2016 Site Visit ADEC Contaminated Sites program staff conducted site visits and inspections of the contaminated sites which are located on the USCG Base Kodiak between September 15-16, 2016. Curtis Dunkin
9/27/2018 Site Visit ADEC's project manager for the Kodiak USCG contaminated sites traveled to Kodiak, AK and participated in a day-long annual planning meeting and conducted site inspections with project delivery team representatives from the USCG and Environmental Protection Agency. Curtis Dunkin
7/10/2019 Meeting or Teleconference Held ADEC traveled to Seattle, WA and participated in two days of technical planning and project status update and prioritization meetings with representatives from the US Coast Guard, US Environmental Protection Agency, and their respective contracted technical support. Curtis Dunkin
8/22/2019 Site Visit ADEC traveled to the USCG Base Station, Kodiak and participated in two full days (August 21-22, 2019) of site inspections and technical project team meetings with representatives from the EPA, USCG, and their respective contracted technical support. Curtis Dunkin
3/10/2020 Document, Report, or Work plan Review - other ADEC reviewed the draft 2019 UST Removal Action Environmental Management Plan and submitted comments to the US Coast Guard. Curtis Dunkin
3/16/2020 Meeting or Teleconference Held ADEC reviewed RTCs on the draft 2019 UST Removal Action Environmental Management Plan and submitted RTC review determinations to the US Coast Guard. ADEC participated in a resolution and work plan finalization meeting via teleconference with representatives from the US Coast Guard and their contracted technical support and field implementation team. Curtis Dunkin
7/22/2020 Meeting or Teleconference Held ADEC participated in annual project prioritization meetings on July 21 and 22 with representatives from the US Coast Guard, the Environmental Protection Agency, and respective contracted project technical support and implementation teams. The purpose of the annual meetings are for stakeholders to provide respective site status updates, conduct technical planning and site prioritization, and scheduling for implementation of projects through the current and upcoming fiscal years. Curtis Dunkin
1/28/2022 Document, Report, or Work plan Review - other ADEC reviewed the responses to comments and the redline revised draft final 2022 Monitoring Well Decommissioning Work Plan and submitted review determinations and approvals to the USCG to finalize the document and and implement the work plan in the field. Curtis Dunkin
5/19/2022 Document, Report, or Work plan Review - other ADEC reviewed the responses to comments and the revised redline final 2022 Underground Storage Tank Removal Action Work Plan and submitted approval to the USCG to finalize the document and implement the plan in the field. Curtis Dunkin
9/13/2022 Meeting or Teleconference Held ADEC participated in two full days of annual project delivery team meetings with representatives from the USCG, EPA, and their respective contracted technical support staff. Curtis Dunkin
4/22/2024 Site Visit ADEC staff conducted 4 full days of site visits and inspections of all active contaminated sites located on USCG Base Kodiak during the week of April 22, 2024 including comprehensive site walks, land use and site condition evaluations, and in-situ inspections and observations of field work implementation; including multiple ADEC-approved site characterization and cleanup removal action efforts at multiple sites across the Base. Curtis Dunkin
6/26/2024 CERCLA PA ADEC reviewed the draft 2024 Base USCG Kodiak PFAS Preliminary Assessment (PA) Report and submitted comments to the U.S. Coast Guard. The draft PA effort evaluated both confirmed as well as potential historical AFFF use and/or release locations across the contiguous USCG Base Kodiak as well as other adjacent USCG properties. The report also ranked the inventory of sites and proposed future actions and investigation efforts. Curtis Dunkin
8/26/2024 Meeting or Teleconference Held ADEC staff participated in 3 days of annual project delivery team planning and prioritization meetings in Seattle, WA at the EPA Region 10 Headquarters with stakeholders from the U.S. Coast Guard, EPA-RCRA, and ADEC. Curtis Dunkin
5/7/2025 Site Visit ADEC staff traveled to Kodiak and conducted site visits at multiple active Base Kodiak sites to evaluate current site conditions and considerations in support of ongoing site management and oversight during the 2025-26 field season. Curtis Dunkin
9/17/2025 Meeting or Teleconference Held ADEC staff traveled to Seattle, WA to participate in two full days of annual Project Delivery Team meetings with representatives from the U.S. Coast Guard and EPA-RCRA to discuss the status and planned work updates and project prioritization and implementation schedules for the 2025-26 fiscal years. Curtis Dunkin
11/25/2025 Offsite Soil or Groundwater Disposal Approved ADEC reviewed the Contaminated Media Transport and Treatment or Disposal Form and the supporting laboratory analytical waste characterization reports for seventy 55-gallon drums of PFAS-contaminated soil and water investigative derived wastes that were generated from implementation of the 2025 USCG Kodiak Base-wide PFAS Site Inspection Work Plan at multiple locations and areas of concern within and outside of the continuous Base Kodiak. ADEC submitted approval to the U.S. Coast Guard to conduct offsite transport to and disposal of the wastes at the Clean Harbors Grassy Mountain Landfill Facility located in Aragonite, UT. Curtis Dunkin

Contaminant Information

Name Level Description Media Comments

Control Type

Type Details

Requirements

Description Details

There are no documents for this site report.