Action Date |
Action |
Description |
DEC Staff |
5/17/1991 |
Site Visit |
FI; Timmons conducted a field inspection at the request of State DOT and found that product from the tank had been released from a deteriorated rubber fitting. Contamination appeared to be confined to a 6' wide x 12' long x 3' deep area. There was also evidence below the 3 foot level of a plume extending downward to the base of the excavation at the 12 foot level. In order to fully assess the amount of contaminated soil the removal of the building will be necessary. Timmons recommended that the soil be stockpile and bermed and that 2 composite samples be taken from the excavation area to ensure the area is below the limit of 200 ppm TPH and 1 sample from the stockpiled soils. Timmons also noted leaking barrels of RC-600 and advised that the area be bermed. |
Former Staff |
5/21/1991 |
Site Added to Database |
|
Former Staff |
5/21/1991 |
Leaking Underground Storage Tank Release Confirmed - Petroleum |
LUST Site created in CSP for source area ID 75829 ADD; LUST site. |
Former Staff |
8/9/1991 |
Update or Other Action |
RAPR; Timmons requested that a site assessment and corrective action be performed at the site. |
Former Staff |
2/23/1993 |
Update or Other Action |
RPL2; Peterson sent PRP-CS Database Notification Letter to RP requesting update and more environmental information concerning contaminated site. DOT/Clarke Milne will respond in month or two, but as of this complete date have rec'd no response! |
Former Staff |
9/15/1993 |
Leaking Underground Storage Tank Corrective Action Underway |
LCAR; KALU - REVIEWED CORRECTIVE ACTION PLAN FOR ABOVE SITE. PLAN SEEMS ADEQUATE. WILL FOLLOW UP WITH CONSULTANT LATER IN THE YEAR. |
Former Staff |
6/6/1994 |
Update or Other Action |
CORR; Wingerter sent letter informing RP of their financial liability under new ADEC cost recovery policy. State is authorized, under Section 9003(h) of the Resource Conservation and Recovery Act to take action on this LUST facility. |
Former Staff |
5/16/1996 |
Leaking Underground Storage Tank Cleanup Initiated - Petroleum |
LCAU; Removed a 500-gallon AST and leaking underground piping system. Stock piles 135 cubic yards of diesel contaminated soil (4220 ppm). Site Assessment cmpleted by Nortech (452-5688). Cross reference file 120.38.003. |
Former Staff |
3/22/1999 |
Underground Storage Tank Site Characterization or Assessment |
SA for the removal of 3 USTs (Nos. 3,4, and possibly 2). Contaminatino identified and some soil removed and stockpiled. |
Former Staff |
1/28/2004 |
Update or Other Action |
Transferred DEC staff lead from John Carnahan |
Cynthia Pring-Ham |
1/20/2005 |
Update or Other Action |
Update GIS using site maps from Shannon Wilson Feb. 2003 report and Topozone Pro. |
Kim DeRuyter |
1/20/2005 |
Document, Report, or Work plan Review - other |
Shannon & Wilson Feb. 2002 report outlines results of soil, drinking water, and stockpile sampling at the site. The drinking water samples did not contained GRO, DRO, or BTEX above their PQLs. Soil borings were field screened to 25 feet, showing a decreasing trend in contamination with depth (2000 ppm at 15’ to 700 ppm at 25’); no analytical samples were submitted from the borings; because course gravel caused difficult drilling and insufficient sample was recovered. Soil samples were collected from the base of four test pits, and analyzed for GRO (up to 617 mg/kg), DRO (up to 249 mg/kg), and BTEX analytes, benzene (up to 0.179 mg/kg), toluene (up to 2.22 mg/kg), ethylbenzene (up to 6.15 mg/kg), and total xylenes (up to 112.3 mg/kg). Samples from the 1998 stockpile did not contain GRO, DRO, or BTEX in concentrations exceeding the ADEC migration to groundwater soil cleanup levels. The report recommends land spreading of the stockpiled soil in a non-environmentally sensitive area and requests a No Further Remedial Action Planned status for the USTs since the contamination has been removed to the extent practicable and groundwater does not appear to have been affected. Total Xylenes are above the Method 2 soil cleanup levels for inhalation, but this pathway is unlikely to be complete. |
Kim DeRuyter |
3/29/2005 |
Institutional Control Record Established |
ADEC approval will be obtained prior to removal and/or disposal of soil or groundwater from this site to an off-site location. If excavation is planned for the area of Tank #4, a plan to address the xylenes contamination should be developed. The on-site drinking water well will be sampled in the summer of 2005, and 2006; using Environmental Protection Agency (EPA) Method 524. |
Kim DeRuyter |
3/29/2005 |
Conditional Closure Approved |
Soil contamination remains underneath the shop building, and utilidor, GRO 617 mg/kg, DRO 249 mg/kg, and total xylenes 112.3 mg/kg. |
Kim DeRuyter |
9/12/2005 |
Document, Report, or Work plan Review - other |
Results of August, 2005 Well Water Sampling, none of the analytes tested in the sample and field duplicate were detected in excess of their practical quantitation limit. |
Kim DeRuyter |
12/20/2011 |
Update or Other Action |
Site management staff changed to IC Unit.
|
Evonne Reese |
12/20/2011 |
Institutional Control Compliance Review |
IC review conducted, follow up requirements added, updated reminder system. |
Evonne Reese |
7/29/2014 |
Institutional Control Update |
An IC reminder letter was issued to the responsible party on this date. |
Kristin Thompson |
11/10/2014 |
Document, Report, or Work plan Review - other |
Reviewed drinking water well monitoring results for 2008. All contaminants of concern were non-detect therefore future drinking water sampling is not required. All other institutional control requirements will remain in place. |
Evonne Reese |
8/29/2019 |
Institutional Control Compliance Review |
An Institutional Controls reminder letter e-mailed to the landowner/responsible party on this date. |
Mossy Mead |
7/11/2024 |
Institutional Control Compliance Review |
IC compliance review completed on this date. An IC reminder letter was e-mailed to the landowner. The next review will be in five years’ time. |
Gaige Robinson |