Action Date |
Action |
Description |
DEC Staff |
10/13/1999 |
Leaking Underground Storage Tank Release Confirmed - Petroleum |
LUST Site created in CSP for source area ID 78059 (Added by System) |
Amanda Dreyer |
10/13/1999 |
Leaking Underground Storage Tank Cleanup Initiated - Petroleum |
Contaminated soil excavated as part of UST system removal in October 1999. |
Amanda Dreyer |
10/13/1999 |
Site Added to Database |
|
Former Staff |
8/18/2000 |
Underground Storage Tank Site Characterization or Assessment |
Two 2,000 gallon gasoline tanks and their associated piping were removed in October 1999. Up to 0.652 mg/kg benzene and 651 mg/kg GRO left in the excavation. The highest contamination levels were found at the dispenser island at 4 feet below ground surface. Benzene contamination was also found above cleanup levels at the northern tank at 8 feet and 15 feet below ground surface. The south wall of the excavation had high field readings at 4 feet below ground surface, but no analytical samples were collected there. 70 cubic yards of contaminated soil was excavated and stored on the property. The full extent of the contamination has not been defined. Groundwater was not encountered during the tank removal, the deepest portion of the excavation was 15 feet below ground surface. No sampling was conducted for lead or EDB or 1,2-DCA. The tanks were installed in May 1982, due to the age of the tanks they likely to have held leaded gasoline in the past. |
Lynne Bush |
6/20/2005 |
Update or Other Action |
ADEC letter to RP requesting information on any site work since the tank removal in 1999. |
Lynne Bush |
7/12/2005 |
Update or Other Action |
Neither the owner nor the tank removal contractor have copies of the closure report. According to the contractor, the Mat-Su office issued a No Further Action letter shortly after the removal action but they have no copy of the letter. |
Lynne Bush |
7/14/2005 |
Update or Other Action |
Prospective purchaser has a copy of the tank closure site assessment and will provide it to DEC. However, he has no further information than that. |
Lynne Bush |
7/15/2005 |
Update or Other Action |
A copy of the October 1999 Underground Storage Tank Permanent Closure Assessment Report was submitted. The report identifies contamiantion remaining above site cleanup levels and a 70 cubic yard contaminated stockpile on site. |
Lynne Bush |
7/25/2005 |
Update or Other Action |
File number issued 2202.26.002 (FKA L55.380) |
Aggie Blandford |
5/9/2006 |
Update or Other Action |
Project management transferred from Bush to Weimer. |
Aggie Blandford |
5/30/2008 |
Exposure Tracking Model Ranking |
Site ranked on the new Exposure Tracking Model (ETM). The ETM is a new site ranking system that looks at, based on available data, the potential exposure pathways for the contamination remaining at the site. |
Robert Weimer |
10/13/2010 |
Update or Other Action |
Based on what information that is contained in the DEC contaminated sites files, there has been no additional site work done since the tanks were removed in 1999. The 70 cubic yard stockpile of contaminated soil needs to be assessed for remaining contamination and/or treated in accordance with an approve corrective action plan. The extent of the remaining contamination needs to be defined in the former tank system excavation. This would include the former tank area, the former dispenser, and the south sidewall that had elevated field readings. The analyticals needed would be BTEX, GRO, lead, EDB, 1,2-DCA, and naphthalene. |
Robert Weimer |
10/28/2011 |
Update or Other Action |
To date have not received documentation or work plans for further site work. Need the 70 cubic yard stockpile of contaminated soil be assessed for remaining contamination and/or treated in accordance with an approve corrective action plan, and request that the extent of the remaining contamination needs to be defined in the former tank system excavation. This would include the former tank area, the former dispenser, and the south sidewall that had elevated field readings. The analyticals needed would be BTEX, GRO, lead, EDB, 1,2-DCA, and naphthalene. |
Robert Weimer |
1/30/2014 |
Update or Other Action |
Project manager changed to Amy Dieffenbacher, transferred to Juneau |
Annie Ariel |
6/24/2014 |
Potentially Responsible Party/State Interest Letter |
Mailed PRP Notification Letter via USPS Certified Mail to RP. |
Amy Rodman |
6/26/2014 |
Update or Other Action |
Telephone conversation with RP, discussed stockpile status, existing contamination on site and updated his contact information. |
Amy Rodman |
9/2/2014 |
Update or Other Action |
release investigation/site assessment work plan request letter mailed to RP. |
Amy Rodman |
11/6/2014 |
Update or Other Action |
Received Closure Request report from AlaskChem Engineering. |
Amy Rodman |
12/10/2014 |
Update or Other Action |
RI/SA work plan request letter mailed to RP and emailed to AlaskChem Engineering. Mailed Notice of Environmental Contamination (NEC) document to Anchorage Department of Natural Resources Recorder's office to be recorded as deed notice. |
Amy Rodman |
12/16/2014 |
Update or Other Action |
Telephone call to Mr. Hulbert (consulting engineer). Discussed applicable regulations for site contaminants and contaminant pathways that still need addressing for closure purposes. |
Amy Rodman |
12/22/2014 |
Update or Other Action |
Mailed third Site Assessment/Release Investigation work plan request letter to RP. Emailed copy to Mr. Hulbert. |
Amy Rodman |
1/13/2015 |
Update or Other Action |
Work plan received from AlaskChem Engineering via email. |
Amy Rodman |
5/8/2015 |
Update or Other Action |
Mailed Closure Investigation Work Plan Approval Letter to Mr. Montgomery via USPS Certified Mail and email copy to AlaskChem Engineering. |
Amy Rodman |
7/23/2015 |
Document, Report, or Work plan Review - other |
received "Closure Investigation Report" from consultant, with permission from RP, via email. review "Closure Investigation Report" dated July 2015. |
Amy Rodman |
8/28/2015 |
Update or Other Action |
DEC project manager mailed (to RP) & emailed (to consultant) report approval to July 2015 "Big Lake Texaco Closure Investigation Report" submitted by AlaskChem Engineering. |
Amy Rodman |
5/20/2016 |
Update or Other Action |
Mailed 2014 NEC document to Palmer Department of Natural Resources Recorder's office. |
Amy Rodman |
5/11/2017 |
Update or Other Action |
Property Boundary Groundwater Delineation Work Plan Request letter mailed via USPS Certified Mail & emailed to RP, consultant. Due date for submission of work plan to ADEC is June 15, 2017. |
Amy Rodman |
5/26/2017 |
Potentially Responsible Party/State Interest Letter |
Mailed new landowner a PRP letter, as well as a work plan request letter with the June 15, 2017 deadline. emailed AlaskChem Engineering a copy of the work plan request letter addressed to the new landowner. |
Amy Rodman |
6/15/2017 |
Update or Other Action |
Received "Property Boundary Groundwater Delineation Work Plan" PDF from AlaskChem Engineering via email. |
Amy Rodman |
7/19/2017 |
Site Characterization Workplan Approved |
Groundwater Delineation work plan conditional approval letter mailed. Installation of two groundwater monitoring wells proposed. Groundwater samples will be analyzed for GRO and BTEX, and samples exceeding CL by 20% will be analyzed for lead and PAH. Conditions: consultant will provide 48 hour notice to ADEC prior to field work; soil samples collected from installation of two groundwater monitoring wells will be analyzed for GRO, BTEX and lead; groundwater installation details will be provided in report; groundwater samples collected from new source area well will be analyzed for PAH, lead and VOC. |
Amy Rodman |
9/12/2017 |
Update or Other Action |
Follow-up letter mailed from ADEC staff to RP summarizing telephone conversation with ADEC staff emphasizing site characterization requirements in July 2017 "Property Boundary Groundwater Delineation Work Plan Approval" letter. Specific tasks include sampling of existing groundwater monitoring well, MW-N, and installation/sampling of groundwater monitoring well that is downgradient of W-N. Purpose of required activities are to determine stable or declining trend of onsite groundwater contamination confirmed during 2015 field activities. |
Amy Rodman |
3/5/2018 |
Site Characterization Workplan Approved |
Work plan approved. Proposed activities generally consist of installation of a new groundwater monitoring well near the property boundary, field screening, soil and groundwater sampling. |
Amy Rodman |
5/23/2019 |
Update or Other Action |
Status of ADEC-approved 2018 work plan requested from RP and consultant. Letter mailed to RP and emailed to consultant. Response due by June 30, 2019. Consultant replied via email that no contact from RP has been received and that the property is vacant. |
Amy Rodman |
12/16/2019 |
Enforcement Action |
ADEC approved a work plan in March 2018. No work has been conducted and no report has been submitted to ADEC as of date. Field work is due June 30, 2020 and report submittal, documenting 2020 field work, is due by August 1, 2020. Failure to meet these two deadlines will result in a Notice of Violation letter and referral to the Department of Law. |
Amy Rodman |
7/20/2022 |
Potentially Responsible Party/State Interest Letter |
Mailed new landowner a PRP letter. |
Alena Voigt |
1/3/2023 |
Potentially Responsible Party/State Interest Letter |
PRP letter sent to Mr. and Mrs. Jillson. |
Alena Voigt |