Action Date |
Action |
Description |
DEC Staff |
8/1/1997 |
Leaking Underground Storage Tank Release Confirmed - Petroleum |
LUST Site created in CSP for source area ID 77851 (Added by System) |
David Allen |
8/1/1997 |
Leaking Underground Storage Tank Cleanup Initiated - Petroleum |
|
Former Staff |
8/1/1997 |
Site Added to Database |
|
Former Staff |
10/1/1997 |
Underground Storage Tank Site Characterization or Assessment |
Excess of 200 cy of soils stockpiled at site, widespread contamination remains in all 5 tank excavations. GW at 18 to 28 feet. |
Robert Weimer |
3/17/1999 |
Update or Other Action |
DEC letter requesting RI (WP due 4/30/99), and meeting to discuss CA at this site. |
Robert Weimer |
8/1/2002 |
Update or Other Action |
Site transferred from Weimer to Dreyer |
Amanda Dreyer |
8/14/2002 |
Update or Other Action |
Spoke with Michael Erdman 376-6989 he said he would mail sampling results. |
Amanda Dreyer |
8/16/2004 |
Update or Other Action |
Left message for Scott Eubanks about current site conditions and upcoming work required to meet regulations. |
Lynne Bush |
9/21/2004 |
Update or Other Action |
Met with Frechione to discuss this site and future Department expectations. |
Lynne Bush |
5/9/2006 |
Update or Other Action |
Project management transferred from Bush to Horwath. |
Aggie Blandford |
5/9/2006 |
Update or Other Action |
File number issued 2268.26.005 (FKA L55.326). |
Aggie Blandford |
5/30/2006 |
Update or Other Action |
Project manager changed from Paul Horwath to Don Fritz, per Paul Horwath. |
Alyce Hughey |
5/30/2006 |
Update or Other Action |
Using Figure 1 from an Underground Storage Tank Closure Assessment, Willow Creek Mine, from Shannon & Wilson, dated October 1997, in conjunction with TopoZone Pro, entered the coordinates for this site. Metadata includes USGS Topo Maps 1:63K, TopoZone Pro Street Maps, on a Medium Size map, View Scale 1:50,000, Coordinate Datum NAD83. Moderate to high degree of confidence in accuracy of location. |
Alyce Hughey |
6/2/2006 |
Update or Other Action |
Phone call with Scott Eubanks who confirmed that Alaska Hardrock Inc. owned the property due to a land swap with DNR. Scott told me that he had an engineering firm out there two or three years ago, and that the stockpiled soils tested clean. Scott said that a report had been submitted to “Amanda”. Scott told me that he had put approx. $100,000 into cleanup actions so far. Scott told me that the mill had been sold 2 years ago, and had been torn down and hauled off site. The bunkhouse has been converted to a bed and breakfast while mining operations were slow, but the site is now leased out. Scott stated that no milling has occurred since 1991. Scott told me that he would provide me with the information available. |
Don Fritz |
7/28/2006 |
Update or Other Action |
Reviewed report regarding sampling of stockpile of contaminated soil. Work was conducted by Alaska Chem Engineering (Ralph Hubert). This report identified another missing report that was preparred by Erdman and Associates. Left a message with Scott Eubanks. |
Don Fritz |
5/11/2007 |
Exposure Tracking Model Ranking |
Site Ranked |
Don Fritz |
5/11/2007 |
Update or Other Action |
Letter sent to the RP requesting additional information/release investigation plan |
Don Fritz |
5/29/2009 |
Update or Other Action |
File transferred to Anchorage from Soldotna 6-1-09. Project Manager changed from Don Fritz to Linda Nuechterlein. |
Alyce Hughey |
6/26/2009 |
Update or Other Action |
Spoke with William Scott Eubanks, owner of Alaska Hardrock Inc. He will send in the 2000 Erdman report that is missing in the file. He will also send in the groundwater monitoring reports. Mr. Eubanks explained that ADEC had suggested using a nitrogen based fertilizer in the excavation pits and the stockpiles as a way to expedite natural attenuation. |
Pam Clemens |
6/26/2009 |
Document, Report, or Work plan Review - other |
Reviewed the 2004 report from AlaskChem Engineering titled: Fuel Contaminated Soil Stockpile Sampling and Closure Recommendation (received in the Kenai Office June 2006). The testing of the stockpiles showed non-detect for GRO and BTEX. DRO ranged from non-detect to 97.6 mg/kg in the five stockpile soil samples taken in September 2004. Mr. Eubanks said that they landspread the stockpiles after the results came in. The AlaskChem report estimates the stockpiles to be almost 500 cubic yards. |
Pam Clemens |
7/3/2009 |
Document, Report, or Work plan Review - other |
Reviewed Erdman & Associates report dated September 11, 2000 which was received via email 6-29-09. Six soil samples were collected from the areas identified as having the highest contaminant levels in the UST Closure Assessment by Shannon & Wilson dated October 1997. DRO levels were significantly reduced in all areas with the highest remaining level at 826 mg/kg near the location of the former UST #4. Further excavation is not practical due to the proximity of the shop building. The highest level of GRO was 35.4 mg/kg, this sample was also taken from the location of the former UST #4. Benzene and toluene were not detected in the six samples. Ethylbenzene and xylene were detected at 0.177 mg/kg and 0.262 mg/kg respectively which are well below cleanup levels. RRO had not been analyzed until the Erdman report in 2000, it was found in concentrations up to 126 mg/kg, which is well below the cleanup level. Two samples were collected from the stockpiled soil, in 2000, these samples showed that DRO was up to 299 mg/kg; GRO was up to 9.74 mg/kg; benzene, toluene, and ethylbenzene were not detected; and xylene was detected in only one sample at 0.242 mg/kg. |
Pam Clemens |
7/10/2009 |
Document, Report, or Work plan Review - other |
Attempted contact with Mr. Eubanks to let him know someone was going out to Hatcher's Pass area, no contact made. Todd Blessing went by the site and took pictures to try to determine the status of the stockpile. Photos are under the attachments tab. All photos were taken from the road. Reviewed the Underground Storage Tank Closure Assessment, Willow Creek Mine, from Shannon & Wilson, dated October 1997. Briefly reviewed the Erdman 2000, and the AlaskChem 2004 reports. Spoke with the UST program about the tanks 1-5 closure in 1997 and the status of tank 6. There is also information about two other tanks (tanks 7 & 8) owned by Mr. Eubanks or Alaska Hardrock Inc. The UST program will follow up on tanks 6, 7, and 8.
|
Pam Clemens |
7/10/2009 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 77851 Willow Creek Mill Site. |
Pam Clemens |
7/24/2009 |
Cleanup Complete Determination Issued |
ROD - Corrective Action Complete Determination-Institutional Controls approved 7-23-09, see attachments. |
Pam Clemens |
7/24/2009 |
Institutional Control Record Established |
Institutional Controls established and entered into the database. |
Pam Clemens |
10/5/2009 |
Update or Other Action |
Filed a letter from the UST program: No Further Action Required, Underground Storage Tanks, ADEC Facility #2743 for Tanks 7 & 8. These two tanks are not regulated and do not require a certified UST worker to decommission them. Tank #6 is still in place and regulated by the UST program. |
Pam Clemens |
7/21/2010 |
Update or Other Action |
Sent email requesting that the Institutional Controls (IC) Agreement Page be signed and returned. |
Pam Clemens |
7/26/2010 |
Update or Other Action |
Received the signed IC Agreement Page. I will attach it here. |
Pam Clemens |
2/16/2012 |
Update or Other Action |
Staff changed from Pam Clemens to IC Unit. |
Kristin Thompson |
5/1/2013 |
Institutional Control Compliance Review |
IC compliance review conducted and reminder system set up for 2014 follow up regarding site conditions. |
Evonne Reese |
8/15/2014 |
Institutional Control Update |
An IC reminder letter was issued to the responsible party on this date. |
Kristin Thompson |
12/10/2019 |
Institutional Control Compliance Review |
An Institutional Controls reminder letter mailed to the landowner on this date. |
Mossy Mead |
1/13/2020 |
Institutional Control Compliance Review |
The landowner/responsible party called to update the affiliate information on this date. |
Mossy Mead |
9/24/2024 |
Institutional Control Compliance Review |
IC compliance review completed on this date. An IC reminder letter was issued to the landowner. The next review will be in five years’ time. |
Gaige Robinson |