Action Date |
Action |
Description |
DEC Staff |
1/31/1992 |
Leaking Underground Storage Tank Release Confirmed - Petroleum |
LUST Site created in CSP for source area ID 77790 ADD; |
Former Staff |
1/31/1992 |
Site Added to Database |
|
Former Staff |
2/1/1992 |
Leaking Underground Storage Tank Cleanup Initiated - Petroleum |
LCAU; LCAU Date changed DB conversion |
Former Staff |
2/1/1992 |
Update or Other Action |
CAPR; :Action Date changed DB conversion 1/11/11 |
Former Staff |
2/1/1992 |
Release Investigation |
RELR; :Action Date changed DB conversion 1/11/11 |
Former Staff |
7/14/1992 |
Leaking Underground Storage Tank Corrective Action Underway |
ADEC's Monica English sent work plan review comments to the Tesoro Alaska Petroleum Company, after reviewing their Corrective Action Plan. |
Alyce Hughey |
1/28/1997 |
Update or Other Action |
Monica English sent a letter requesting a Corrective Action Plan Report. |
Alyce Hughey |
3/21/1997 |
Update or Other Action |
Monica English sent a letter requesting additional corrective action report information. |
Alyce Hughey |
9/19/1997 |
Release Investigation |
ADEC's Paul Horwath sent a letter with review comments and a conditional work plan approval decision, after reviewing the Release Investigation Work Plan, Risk Assessment Work Plan, and Corrective Action Plan prepared by Oasis Environmental, dated August 12, 1997. |
Alyce Hughey |
10/10/1997 |
Update or Other Action |
Paul Horwath sent a letter of response after reviewing the letter dated October 9, 1997 from Oasis Environmental. |
Alyce Hughey |
11/20/1997 |
Update or Other Action |
ADEC sends Notification of Intent to Cost Recover Letter to Current Owner: TESORO ALASKA PETROLEUM CO |
Former Staff |
1/8/1998 |
Update or Other Action |
Monica English sent a letter requesting the removal of fuel lines for the former UST system, as they had not been removed, as required by Alaska law. |
Alyce Hughey |
1/28/1998 |
Update or Other Action |
Paul Horwath sent a letter requesting a water sample be collected from the private drinking water well located approximately 300 feet west of the site. |
Alyce Hughey |
6/4/1998 |
Update or Other Action |
Paul Horwath sent a letter to Tesoro, containing ADEC review comments pertaining to Tesoro's risk assessment work plan. Private environmental consultant/contractor David Brailey assisted ADEC with its review of this work plan. |
Alyce Hughey |
6/19/1998 |
Release Investigation |
Monica English sent a review comments letter after reviewing the Release Investigation Addendum Report. |
Alyce Hughey |
6/22/1998 |
Risk Assessment |
Monica English sent a letter with ADEC's review comments, after reviewing the Risk Assessment Work Plan dated September 10, 1997, prepared by Environmental Fate and Risk, Inc., on behalf of Tesoro. |
Alyce Hughey |
6/26/1998 |
Update or Other Action |
Paul Horwath sent a follow-up letter after the June 24, 1998 meeting with Tesoro. |
Alyce Hughey |
12/23/1998 |
Update or Other Action |
Paul Horwath sent a questions/comments/requests letter regarding the September 1, 1998, Environmental Fate and Risk, Inc., letter providing results of the Aug 1998 Release Investigation, and a letter recommending a monitoring schedule for the residential well serving the Cook Inlet Bluff fronting property, owned by the Bellmore family. |
Alyce Hughey |
2/4/1999 |
Release Investigation |
Paul Horwath sent an approval letter for the Release Investigation Work Plan dated January 15, 1999 from Oasis Environmental. |
Alyce Hughey |
5/21/1999 |
Leaking Underground Storage Tank Corrective Action Underway |
Paul Horwath sent a letter requesting a Corrective Action Plan and additional response measures, based on the confirmed contamination of the Bellmore's private drinking water well. |
Alyce Hughey |
5/26/1999 |
Update or Other Action |
Paul Horwath sent an approval letter in response to Tesoro's work plan proposing a pilot test of a soil vapor extraction treatment system. |
Alyce Hughey |
7/23/1999 |
Leaking Underground Storage Tank Corrective Action Underway |
Paul Horwath sent a letter to Tesoro requesting the preparation and submittal of a Corrective Action Plan. |
Alyce Hughey |
9/17/1999 |
Update or Other Action |
Paul Horwath sent a conditional approval letter to Tesoro, providing for the sampling of the Bellmore's water well No. 2. |
Alyce Hughey |
9/17/1999 |
Update or Other Action |
Paul Horwath sent a work plan approval decision for the Work Plan Addendum from Oasis Environmental for the purpose of delineating the south and west edges of the groundwater contamination plume. |
Alyce Hughey |
9/20/1999 |
Update or Other Action |
Paul Horwath sent a review comments letter after reviewing the Remediation System Design and Installation Procedures Work Plan. |
Alyce Hughey |
10/1/1999 |
Update or Other Action |
Paul Horwath sent a conditional approval letter for the Tesoro North Road Property Work Plan Addendum that provided for the installation, development and sampling of 4 additional groundwater monitoring wells, and the pilot testing of fuel-vapor emissions/exhaust. |
Alyce Hughey |
10/22/1999 |
Update or Other Action |
Paul Horwath sent a work plan approval decision to Tesoro, for the installation, development, and sampling & analysis of three additional groundwater monitoring wells. |
Alyce Hughey |
11/12/1999 |
Update or Other Action |
Paul Horwath issued a letter requesting the completion of the final design of a soil and groundwater remediation system, after reviewing the Delineation Results letter-report. |
Alyce Hughey |
12/10/1999 |
Leaking Underground Storage Tank Corrective Action Underway |
Paul Horwath issued a work plan approval decision for the Remediation System Design and Installation Procedures Corrective Action Plan. It presents the design and installation procedures for a soil and groundwater remediation system utilizing air sparging, and soil vapor extraction systems. |
Alyce Hughey |
2/7/2000 |
Leaking Underground Storage Tank Corrective Action Underway |
Paul Horwath issued a letter regarding the implementation of the Corrective Action Plan (CAP) and requiring that the final CAP be submitted for approval by they department. |
Alyce Hughey |
2/23/2000 |
Leaking Underground Storage Tank Corrective Action Underway |
Paul Horwath issued a conditional Corrective Action Plan Approval decision. |
Alyce Hughey |
8/24/2000 |
Leaking Underground Storage Tank Corrective Action Underway |
Paul Horwath issued a modification to the Conditional Corrective Action Plan Approval decision. |
Alyce Hughey |
1/15/2003 |
Leaking Underground Storage Tank Corrective Action Underway |
Tesoro purchased the adjacent private property from the Bellmore's about 1999-2000. Additional assessment resulted in the finding that contaminated GW from the site had migrated to Cook Inlet, directly under the Bellmore's house. Tesoro installed a SVE and Air Sparge treatment system and continues to operate these systems into the year 2003. Air sparge systems appear to be intercepting and treating the dissolved BTEX plume. The SVE system at the former tank sites is aimed at reducing subsurface soil contamination that remains over the groundwater in that area. |
Paul Horwath |
9/23/2004 |
Update or Other Action |
File number assigned and entered into the Fileroom DB and LUST DB. |
Alyce Hughey |
9/13/2005 |
Update or Other Action |
Paul Horwath issued an ADEC review comments letter after reviewing the 2004 Groundwater Monitoring Report, North Bay Property. |
Alyce Hughey |
4/6/2006 |
Document, Report, or Work plan Review - other |
Reviewed Kent & Sullivan's 2005 groundwater monitoring report and corrective action report. The air sparge groundwater treatment systems are proving effective in removing BTEX from the groundwater. Tesoro installed new air sparge wells to treat the source area now that the downgradient dissolved groundwater concentrations has been diminished. Air sparge SVE treatment will continue in and near the source area, with semi-annual groundwater monitoring. PDH |
Paul Horwath |
7/26/2006 |
Update or Other Action |
Using Figures 1 and 2 from the 2000 Investigation and Corrective Action Report, North Bay Project, by Kent and Sullivan, Inc., in conjunction with TopoZone Pro and the KPB Parcel Lookup, entered the Lat/Long coordinates for this site. Metadata includes No Topo Basemap, TopoZone Pro Street Maps, Black and White Aerial Photo, on a Medium Size Map, View Scale 1:10,000, Coordinate Datum WGS84. High degree of confidence in accuracy of location. |
Alyce Hughey |
3/29/2007 |
Exposure Tracking Model Ranking |
Initial ETM Ranking completed. |
Paul Horwath |
2/19/2008 |
Leaking Underground Storage Tank Corrective Action Underway |
Reviewed and approved the Kent & Sullivan work plan for calendar year 2008. Reviewed the Kent & Sullivan groundwater monitoring report covering year 2007 GW sampling events. GW conditions continue to improve. Treatment system will be turned off to see if GW concentrations remain within ADEC GW cleanup levels without active GW treatment. |
Paul Horwath |
7/30/2008 |
Leaking Underground Storage Tank Corrective Action Underway |
ADED received a 2008 Well Abandonment Plan, which was prepared by Kent & Sullivan, Incorporated. The plan included GW quality data from a May, 2008 GW sampling event as well as a Quality Assurance Summary and the ADEC Laboratory Data Review Checklist. Based on this water quality report, approval was issued to decomission all monitoring and treatment wells located to the west of GW monitoring well B-12. |
Paul Horwath |
2/13/2009 |
Update or Other Action |
The groundwater contaminant plume is now restricted to the former gas station property boundaries, and no longer extends to the west of the property. The on-property treatment system remains operational. |
Paul Horwath |
3/5/2009 |
Document, Report, or Work plan Review - other |
Reviewed the 2008 Groundwater Monitoring Report, dated February 11, 2009, from Kent & Sullivan for Paul Horwath and provided him with a summary for his review and oversight. Site conditions remain stable with the groundwater concentrations remaining below the groundwater cleanup levels for two years now. Fifteen monitoring wells and three air sparge wells were decommissioned in August of 2008. Tesoro would like to remove all remaining monitoring and remediation wells upon receiving approval from ADEC. A final report will be submitted to ADEC documenting all work that has been performed at the site, and the final well decommissioning. |
Alyce Hughey |
9/1/2009 |
Document, Report, or Work plan Review - other |
Reviewed and issued approval of the August 31, 2009 Shallow Soil Investigation Workplan, prepared by Kent & Sullivan. |
Paul Horwath |
11/1/2009 |
Site Characterization Report Approved |
ADEC has received and reviewed multiple release investigation reports over the years. Site characterization is now considered complete. |
Paul Horwath |
12/22/2009 |
Long Term Monitoring Complete |
All groundwater monitoring wells have been decomissioned, except wells B-1 and B-30, which could not be located. No further groundwater quality sampling is planned. |
Paul Horwath |
2/22/2010 |
Conceptual Site Model Submitted |
A conceptual site model was received within the Kent & Sullivan, Inc., Site Closure Activities Report, North Bay Site, submitted to ADEC's Soldotna office on February 22, 2010. |
Paul Horwath |
4/8/2010 |
Document, Report, or Work plan Review - other |
Reviewed the Site Closure Activities Report, dated February 22, 2010, from Kent & Sullivan for Paul Horwath. The results of the Site Closure Activities indicates that the upper 12 feet of soil located in the former underground storage tank area has been remediated to non-detect for BTEX, GRO, and EDC. All the monitoring wells have been decommissioned according to ADEC’s Monitoring Well Guidance, other than B-001, and B-030, because they couldn’t be located. They may have been covered or damaged during snow/ice removal. |
Alyce Hughey |
7/12/2010 |
Final Cleanup Report Reviewed |
Reviewed the Kent & Sullivan, Inc., Site Closure Activities Report, North Bay Site, which was submitted to ADEC on February 22, 2010. |
Paul Horwath |
7/20/2010 |
Cleanup Complete Determination Issued |
A Corrective Action Complete decision letter was issued to Mr. Peter Ribbens, Tesoro's project manager. No institutional controls were required, as soil and groundwater both meet ADEC cleanup levels. |
Paul Horwath |
4/21/2011 |
Update or Other Action |
Received e-mail confirmation that the two remaining monitoring wells B-1 and B-30 could not be located to be abandoned. Well B-1 actual location was never verified in the field, and was not located. Well B-30 is believed to have been destroyed during excavation of the closure sampling test pits, which were dug to a depth of at least 12 feet below the ground surface. |
Paul Horwath |
4/16/2018 |
Update or Other Action |
Attached three reports to this site entry, for public availability thru ADEC's Contaminated Site Program internet website.
The Kenai Peninsula Borough informed us today that they have plans to sell the 5 acre parcel of Borough owned land bordering the west property boundary of the former gas station property. The three informational reports will now be accessible to interested prospective purchaser's of the Borough property. |
Paul Horwath |