Site Report: Thompson's Soldotna Gas Station

Site Name: Thompson's Soldotna Gas Station
Address: 44224 Sterling Highway, Soldotna, AK 99669
File Number: 2333.26.041
Hazard ID: 23311
Status: Cleanup Complete
Staff: No Longer Assigned, 9074655229 dec.icunit@alaska.gov
Latitude: 60.484400
Longitude: -151.064300
Horizontal Datum:NAD83

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

During tank upgrade activities, gasoline contaminated soil was reported at fill pipe end and between the two 10,000-gallon gasoline tanks. Additional assessment activities were not conducted to determine extent of soil and/or groundwater impacts . State funds were spent to determine potential of groundwater impacts from UST system. Analytical results for groundwater monitoring were below the established cleanup levels for GRO and benzene. State funds used to decommission the monitor wells.

Action Information

Action Date Action Description DEC Staff
5/28/1999 Site Added to Database Former Staff
5/28/1999 Leaking Underground Storage Tank Release Confirmed - Petroleum LUST Site created in CSP for source area ID 76156 NORL issued 5/28/99. Former Staff
10/11/1999 Leaking Underground Storage Tank Cleanup Initiated - Petroleum During fill pile replacement, contaminated soil encountered between tanks. Approx. 45 cy contaminated soil excavated and treated. Former Staff
10/26/1999 Update or Other Action CAP requested. Monica English
9/4/2000 Update or Other Action Colin Basye sent a letter requesting information regarding the additional remediation work needing to be done. Alyce Hughey
12/4/2000 Update or Other Action Letter from RP's accountant stating that RP is out of state but intends to conduct work in Spring of 2001. Monica English
12/5/2000 Update or Other Action Memo to file. Project manager called RP's accountant. Jackson Const. To do work in spring 2001, Rozak Engr to draft workplan. Monica English
5/21/2002 Update or Other Action Updated GIS information. Accuracy Information (for those who want it): Method: MAP INTERPOLATION - Kenai Peninsula Borough Tax Parcels Map 1999 Scale of Source: approximately 1:24,000 Datum: Nad27 Accuracy: Approx 500 meters (some may be better but I wouldn't claim better accuracy without seeing the physical site files and double-checking to see if the locations were on the correct tax parcel) Cynthia Pring-Ham
5/21/2002 Update or Other Action Updated GIS information. Accuracy Information (for those who want it): Method: MAP INTERPOLATION - Kenai Peninsula Borough Tax Parcels Map 1999 Scale of Source: approximately 1:24,000 Datum: Nad27 Accuracy: Approx 500 meters (some may be better but I wouldn't claim better accuracy without seeing the physical site files and double-checking to see if the locations were on the correct tax parcel) Cynthia Pring-Ham
5/30/2002 Update or Other Action New project manager. Request for CAP. Monica English
7/25/2002 Update or Other Action Warning Letter - Requirement for a CAP. Monica English
8/12/2002 Update or Other Action Warning Letter - Requirement for a Corrective Action Plan. Monica English
8/15/2002 Update or Other Action RP comes to office for unscheduled meeting. Discuss reasons for required CAP. RP states he doesn't have money. Ultimately says he will hire Rozak to install some borings. Says he will be out of state next month until 9/10/02. Monica English
8/26/2002 Update or Other Action RP sends letter stating that he met with Rozak Engineering regarding the required CAP. RP requests a one year extension to submit CAP due to costs. Monica English
9/9/2002 Update or Other Action Letter to RP: Notification of State Lead Assessment. Monica English
2/26/2003 Update or Other Action ADEC mails Site Access Authorization form and Cost Estimate proposal for State Lead Work to RP. Monica English
3/12/2003 Update or Other Action RP in office to meet with staff. RP won't sign Site Access Authorization form. Discuss environmental issues remaining at this site. RP wants to discuss ADOT site across street. RP finally states that he will give staff an answer by March 17th. Monica English
3/18/2003 Update or Other Action Site Access Authorization form received from RP for State to conduct release investigation activities. Monica English
4/1/2003 Release Investigation State spends funds to install monitor wells to investigate potential for groundwater impact. Analytical results for monitor wells are below cleanup levels. Monica English
11/26/2003 Conditional Closure Approved NFRAP letter sent by project manager on 11/26/03. Alyce Hughey
11/26/2003 Institutional Control Record Established Note to database documenting that contaminated soils exceeding the established cleanup level for GRO and benzene remains around the existing tanks. The owner will be required to conduct assessment and/or cleanup activities when the UST system is upgraded, modified or replaced. Monica English
4/26/2004 Update or Other Action Four monitor wells installed by the state are decommissioned. Monica English
10/15/2004 Update or Other Action File number 2333.26.041 assigned and entered into the Fileroom DB and LUST DB. Alyce Hughey
6/18/2007 Update or Other Action Contaminated sites staff met with Ron Rozak (Rozak Engineering) regarding the Thompson's Soldotna Gas Station. Mr. Rozak oversaw the removal of the two UST systems, and encountered approximately 25 cubic yards of contaminated soil during removal activities. The deepest contamination extended below the UST systems was approximately 7 feet. Contaminated soils were bioremediated and approval was granted to use the soils that were excavated from the tank excavation as a topping coat for the alley immediately behind the facility. Don Fritz
10/19/2010 Document, Report, or Work plan Review - other Reviewed the Site Assesssment Report for Closure of UST Facility ID #1172 Thompson's Soldotna Gas Station, dated July 29, 2010, from Rozak Engineering, The results of the Site Assessment Report during the removal the two underground storage tanks associated piping and dispenser indicates that the upper 12 feet of soil located in the former underground storage tank area, and the associated piping and dispenser areas has been remediated to below the soil cleanup levels. All the excavated soil has been properly bio-remediated and used as a topping coat for the alley immediately behind the facility. The site conditions demonstrated within the Site Assessment Report for Closure indicates that this site will be considered for a Corrective Action Complete Determination following ADEC’s review of the information submitted to date. Alyce Hughey
11/3/2010 Cleanup Complete Determination Issued Corrective Action Complete Determination letter issued. Paul Horwath
11/4/2010 Institutional Control Record Removed Institutional Controls Removed. A Corrective Action Complete Determination was issued for the site on November 3, 2010. Paul Horwath

Contaminant Information

Name Level Description Media Comments
BTEX < Method 2 Most Stringent SoilSoil

Control Type

Type Details
No ICs Required

Requirements

Description Details
Advance approval required to transport soil or groundwater off-site.

No associated sites were found.