Site Report: Kenai Airport Fuel Service

Site Name: Kenai Airport Fuel Service
Address: 409 Willow Street, Kenai, AK 99611
File Number: 2320.26.012
Hazard ID: 23460
Status: Active
Staff: Peter Campbell, 9072623412 peter.campbell@alaska.gov
Latitude: 60.566900
Longitude: -151.245100
Horizontal Datum:NAD83

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

On October 18 and 19, 1993 three 10,000-gallon jet aviation fuel, aviation gasoline and 100 low lead gasoline, and one 1,000-gallon regular unleaded gasoline underground storage tanks were removed. Free product was observed on the groundwater during tank removals, and approximately 600 gallons of free product was skimmed off the water surface into a pumper truck. The groundwater is approximately 6.5 to 7 feet below ground level. Levels of 1.2 dichloroethane in two of the test pits also exceeded the maximum contaminant levels of 0.005 parts per million (ppm). Levels of extractable petroleum hydrocarbons (EPH) in soil exceed the allowable level based on the matrix score sheet. On March 18, 1992, the Department sent a Notice of Release letter to Mr. Dan Pitts (contact person) requesting corrective action be taken at this site. June 1999, 220 cubic yards of contaminated soil is transported to a temporary soil burning facility on K Beach Rd, then thermally remediated.

Action Information

Action Date Action Description DEC Staff
9/25/1990 Leaking Underground Storage Tank Release Confirmed - Petroleum LUST Site created in CSP for source area ID 77769 ADD; Former Staff
9/25/1990 Site Added to Database Former Staff
9/26/1990 Underground Storage Tank Site Characterization or Assessment SA1R; :Action Date changed DB conversion 1/11/11 Former Staff
9/26/1990 Update or Other Action NOR; :Action Date changed DB conversion 1/11/11 Former Staff
9/26/1990 Leaking Underground Storage Tank Cleanup Initiated - Petroleum LCAU; :LCAU Date changed DB conversion Former Staff
3/18/1992 Update or Other Action Monica English sent a Notice of Release Letter after reviewing the Phase I December 1991 UST Site Assessment Report, dated December 1991, from Northern Test Labs. Alyce Hughey
8/13/1992 Update or Other Action Monica Englsih sent a letter requesting a Corrective Action Plan. Alyce Hughey
5/11/1993 Document, Report, or Work plan Review - other Monica English sent a letter requesting a Corrective Actin Plan, and provided review comments after reviewing the Kenai Airport Fuel Service UST Removal & Site Assessment Work Plan,, from Northern Test Lab, dated September 23, 1992. Alyce Hughey
10/19/1993 Leaking Underground Storage Tank Emergency Response SC; During the removal of UST's at this facility, free product was encountered on the groundwater and resulted in free product recovery. Former Staff
10/20/1993 Site Visit RECN; FI conducted during UST removal. Former Staff
11/12/1993 Site Visit FI; Site inspection conducted to inspect the stockpiling of the contaminated soils removed during the tank excavation. Former Staff
7/18/1994 Leaking Underground Storage Tank Corrective Action Underway CAPR; CAPR approved for the investigation of contaminated soils that were identified during tank removals at this facility. Former Staff
7/19/1994 Update or Other Action Monica English sent an approval letter after reviewing the Request to Backfill UST Pit, dated July 18, 1994, from Rozak Engineering. Alyce Hughey
11/20/1997 Update or Other Action ADEC sends Notification of Intent to Cost Recover Letter to Current Owner: KENAI AIRPORT FUEL SERVICES INC Former Staff
3/3/1999 Update or Other Action Colin Basye sent a follow up letter after a phone call with Ron Rozak from Rozak Engineering addressing the needs for the site to meet regulatory requirements. Alyce Hughey
6/4/1999 Update or Other Action Colin Basye sent a letter after a meeting with Ron Rozak to address the remaining issues from a March 3, 1999 letter. Alyce Hughey
8/31/1999 Underground Storage Tank Site Characterization or Assessment Interim Remedial Action Report submitted by Rozak Engineering. Monica English
9/14/1999 Document, Report, or Work plan Review - other Stockpile Remedial Action Report by Rozak Engineering. Monica English
9/28/1999 Underground Storage Tank Site Characterization or Assessment Interim Remedial Action Report #2 submitted by Rozak Engineering. Monica English
10/25/1999 Document, Report, or Work plan Review - other Colin Basye sent a letter after reviewing the Stockpile Remedial Action Report and the Interim Remedial Action Report #2, from Rozak Engineering dated Aug 31, 1999 and Sept 14, 1999. Alyce Hughey
12/16/1999 Update or Other Action Colin Basye sent a letter stating that the stockpiled soils were inadequately tested fro DRO. Alyce Hughey
1/10/2000 Update or Other Action Colin Basye sent a letter of response after reviewing the Post-Remediation Sampling of Contaminated Soil from Rozak Engineering, dated December 29, 1999. Alyce Hughey
5/5/2000 Update or Other Action Colin Basye sent an approval letter after reviewing the Porposed Plan fro DRO Sampling of Thermally Remediated soil, from Rozak Engineering, dated May 3, 2000. Alyce Hughey
7/20/2000 Update or Other Action Colin Basye sent a letter that the Thermaly Processed soil could be closed out and no further action is required, after reviewing the DRO Sampling of Thermally Processed Soil from Rozak Engineering dated July 17, 2000. Alyce Hughey
4/23/2001 Underground Storage Tank Site Characterization or Assessment Interim Remedial Action Report #3 submitted by Rozak Engineering. Monica English
5/21/2001 Update or Other Action Met with Dan Pitts and Ron Rozak today regarding latest report. They want to develop a workplan for long term GW monitoring. Colin Basye
5/25/2001 Update or Other Action Colin Basye sent a letter to follow up on a meeting. Alyce Hughey
2/5/2002 Update or Other Action ADEC Conditional Approval for Interim Action Plan with Revision #1. Monica English
4/11/2002 Update or Other Action Monica English sent a letter requesting the implamentation of the Corrective Action Plan and provide for the construction and operation of an Air Sparge trench and installation of a 10th monitor well fro the Interim Remedial Action Plan. Alyce Hughey
5/6/2002 Update or Other Action Meeting in office with Dan Pitts, Dean Eichholz, Paul Horwath and Monica English. Discuss need for additional assessment and cleanup of soil and groundwater. Also mention FAP grant program. Monica English
5/8/2002 Update or Other Action ADEC Conditional Approval of Interim Remedial Action Plan Revision #2 from Rozak Engineering, dated May 7, 2002. Approval to install an 11th monitoring well, and to excavate as much as possible below the water table without causing the slopes to slough. Monica English
8/14/2002 Site Visit ADEC staff inspect evaporation treatment pond during period of heavy rain fall. Monica English
8/23/2002 Underground Storage Tank Site Characterization or Assessment Interim Remedial Action Report #4 submitted by Rozak Engineering. Monica English
10/4/2002 Document, Report, or Work plan Review - other Monica English sent a letter of response after reviewing the Kenai Airport Fuel Service Interim Remedial Action Report #4, from Rozak Engineering, dated Aug 23, 2002. The letter requested additional sampling from MW's due to the migration of contamination under the terminal building and to submit a corrective action plan. Alyce Hughey
10/24/2002 Update or Other Action Monica English sent a letter approving an extention to submit a CAP, but didn't approve the extention of resampling of the monitoring wells. Alyce Hughey
12/12/2002 Document, Report, or Work plan Review - other Interim Remedial Action Report #5. Monica English
12/18/2002 Underground Storage Tank Site Characterization or Assessment Submittal of Interim Remedial Action Report #5 by Rozak Engineering. Monica English
12/23/2002 Update or Other Action Remedial Action Workplan. Monica English
1/23/2003 Update or Other Action ADEC comments to Remedial Action Workplan Monica English
2/24/2003 Update or Other Action Consultant submitts additional information for the Remedial Action Workplan. Monica English
3/4/2003 Update or Other Action ADEC approval for Remedial Action Workplan. Monica English
7/27/2003 Update or Other Action Detailed Remedial Action Workplan review. Monica English
7/30/2003 Update or Other Action ADEC approval of Detailed Remedial Action Workplan. Monica English
10/28/2003 Update or Other Action Remedial Action - Project Status Inquiry by ADEC. Monica English
11/21/2003 Document, Report, or Work plan Review - other Interim Remedial Action Report #6 for Detailed Work Plan. Monica English
1/21/2004 Update or Other Action ADEC requests update on status of plan submittal for proposed treatment system. Monica English
2/17/2004 Update or Other Action Remedial Action Work plan #2 Monica English
3/18/2004 Update or Other Action Remedial Action Work Plan #2R (Revised) Monica English
4/5/2004 Update or Other Action Additional information submitted by RP to support work plan. Monica English
4/6/2004 Update or Other Action ADEC approval for SVE Pilot test study. Monica English
5/6/2004 Document, Report, or Work plan Review - other Installation and Sampling of Groundwater Monitoring wells 12 and 13 - Interim Remedial Action Report #7 Monica English
5/11/2004 Document, Report, or Work plan Review - other Soil Vapor Extraction Pilot Test Report. Monica English
5/13/2004 Update or Other Action Site visit conducted to post Public Notice regarding proposed AS/SVE treatment system. Met with personnel of local business (AFN and Yukon Air) to discuss proposed remediation. Monica English
5/19/2004 Update or Other Action Conditional Approval of Remedial Action Work Plan #2R(Revised). Monica English
6/14/2004 Update or Other Action General email correspondence with RP regarding grant funding and cost recovery on site. Monica English
7/7/2004 Site Visit Drive by site to see if AS/SVE system is operational. Note: discharge stack not at approved height. Monica English
7/9/2004 Update or Other Action Contact consultant regarding remediaiton system. Request system status update and explanation of any deviations to approved plan. Monica English
7/10/2004 Update or Other Action Consultant informs dept. that SVE system is running and being optimized. AS wells are plugged and need to be reworked due to lack of air flow. ADEC requests system installation/startup report. Monica English
7/30/2004 Update or Other Action AS wells pulled and reslotted to attempt to improve air flow. Only the SVE portion of system operating. Exhaust stack adjusted to meet approved plan height. Monica English
9/8/2004 Update or Other Action File number assigned and entered into the Fileroom DB and LUST DB. Alyce Hughey
9/12/2004 Update or Other Action Consultant working on AS blower. Blower runs hot and continues to shut off. A timer was installed to get system operational until troubleshooting reveals problem. Monica English
9/14/2004 Update or Other Action ADEC requests that the system installation and startup report be submitted for review. Monica English
2/3/2005 Update or Other Action ADEC provides comments for the Remedial Action Report #1. Additional clarification is requested (response due 3-31-05). Monica English
3/8/2005 Update or Other Action Monica English sent a letter requesting a response from her February 3, 2005 letter. Alyce Hughey
2/14/2006 Update or Other Action Using Figrue 1-1 and 1-2 from a Remedial Action Work Plan, Kenai Airport Fuel Service, from Rozak Engineering, dated December 2002, in conjunction with TopoZone Pro and the KPB Parcel Lookup, entered the coordinates for this site. Metadata includes No Topo Basemap, TopoZone Pro Street Maps, Black and White Aerial Photo, on a Medium Size Map, View Scale 1:10,000, Coordinate Datum NAD83. High degree of confidence in accuracy of locaion. Alyce Hughey
10/9/2006 Update or Other Action Project manager changed from Monica English to Don Fritz, per Paul Horwath. Alyce Hughey
12/7/2006 Update or Other Action Letter sent to RP's requesting additional infromation regarding remedial activities. Don Fritz
3/22/2007 Exposure Tracking Model Ranking Initial Site Ranking using the ETM Don Fritz
7/14/2008 Document, Report, or Work plan Review - other Remedial action report received, submited by Mark Prieksat. The treatment system operated from April ot November, when it was shut down due to freeze up. Don Fritz
11/16/2011 Update or Other Action Site transferred from Don Fritz to Peter Campbell per Paul Horwath. Alyce Hughey
6/2/2016 Update or Other Action Letter to the responsible party requesting a site status report, groundwater monitoring update and work plan. Peter Campbell

Contaminant Information

Name Level Description Media Comments

Control Type

Type Details

Requirements

Description Details

No associated sites were found.

Missing Location Data

Because the GIS location data for this site has not been entered, we cannot direct you to its position on the map. Click "Continue" to proceed to the Contaminated Sites Web Map or "Close" to return to the site report.
Continue     Close