Action Date |
Action |
Description |
DEC Staff |
6/28/1986 |
Underground Storage Tank Site Characterization or Assessment |
Soil borings and monitoring wells found soil and groundwater contamination at the site. |
Scott Pexton |
10/21/1986 |
Release Investigation |
RZA's report summarizing subsurface petroleum hydrocarbon contamination at the site. Groundwater is 17 to 19 feet below ground surface and flows towards the northwest. Groundwater samples from monitoring wells MW-1 through MW-4 had petroleum hydrocarbon concentration ranging from 0.29 ppm to 0.09 ppm when sampled on 12/4/86. Groundwater sample taken on 12/8/86 from well MW-2 had 1.0 ppb toluene and 1.0 ppb xylene. Soil sample MW-4, S1 taken on 12/8/86 had 13 ppb xylene. |
Former Staff |
6/27/1988 |
Leaking Underground Storage Tank Release Confirmed - Petroleum |
LUST Site created in CSP for source area ID 78067 Petroleum contaminant. |
Former Staff |
6/27/1988 |
Site Added to Database |
|
Former Staff |
6/28/1988 |
Leaking Underground Storage Tank Cleanup Initiated - Petroleum |
LCAU Date changed DB conversion |
Former Staff |
6/9/1995 |
Leaking Underground Storage Tank Corrective Action Underway |
Reviewed and approved soil disposal plan. |
Former Staff |
7/24/1995 |
Document, Report, or Work plan Review - other |
Reviewed a release investigation report. Additional monitoring wells were installed. |
Former Staff |
4/30/1997 |
Document, Report, or Work plan Review - other |
Six USTs, an oil/water separator, associated piping, and two hoists were removed in 1997. Soil (up to 10,300 mg/kg GRO, 55,900 mg/kg DRO, and 52.1 mg/kg benzene) and groundwater contamination was found at several locations. 450 cubic yards of contaminated soil was excavated and thermally treated. Remediation piping was installed when the excavations were backfilled and three new USTs were installed in 1997. |
Robert Weimer |
11/20/1997 |
Update or Other Action |
ADEC sends Notification of Intent to Cost Recover Letter to Current Owner: MILCO INC. |
Former Staff |
1/9/1998 |
Update or Other Action |
ADEC requests further release investigation and groundwater monitoring. |
Former Staff |
1/11/2001 |
Update or Other Action |
ADEC conditionally approves release investigation workplan. |
Robert Weimer |
10/11/2002 |
Update or Other Action |
Approved financial assistance program corrective action plan. |
Robert Weimer |
10/16/2002 |
Document, Report, or Work plan Review - other |
October 16, 2002 groundwater monitoring event. Up to .42 mg/l RRO in the groundwater. Concentrations appear stable. |
Robert Weimer |
1/30/2003 |
Document, Report, or Work plan Review - other |
January 30, 2003 groundwater sampling. Up to <0.09 mg/l GRO, <0.568 mg/l DRO, <1.14 mg/l RRO, and 0.00311 mg/l benzene in groundwater. Contamination levels increased in 5 of the 7 monitoring wells sampled. Groundwater flow direction is to the northwest. Depth to groundwater is 18.07 to 19.40 feet below ground surface. |
Robert Weimer |
3/21/2003 |
Update or Other Action |
Approved corrective action plan to continue to operate soil vapor extraction/venting remediation system. |
Robert Weimer |
4/11/2003 |
Document, Report, or Work plan Review - other |
April 11, 2003 groundwater sampling. Up to <0.01 mg/l GRO, <0.11 mg/l DRO, <0.21 mg/l RRO, and <0.0005 mg/l benzene in groundwater. Contamination levels decreased in 5 of the 5 monitoring wells sampled. Groundwater flow direction is to the northwest. Depth to groundwater is 18.41 to 19.75 feet below ground surface. |
Robert Weimer |
7/8/2003 |
Document, Report, or Work plan Review - other |
July 8, 2003 groundwater sampling. Up to <0.01 mg/l GRO, <0.11 mg/l DRO, <0.21 mg/l RRO, and <0.0005 mg/l benzene in groundwater. Contamination levels increased in 0 of the 7 monitoring wells sampled. Groundwater flow direction is to the northwest. Depth to groundwater is 18.20 to 19.49 feet below ground surface. |
Robert Weimer |
9/24/2003 |
Site Characterization Report Approved |
September 24, 2003 groundwater sampling. Up to <0.01 mg/l GRO, <0.11 mg/l DRO, <0.21 mg/l RRO, and <0.0005 mg/l benzene in groundwater. Contamination concentrations increased in 0 of the 7 monitoring wells sampled. Groundwater flow direction is to the northwest. Depth to groundwater is 18.74 to 20.07 feet below ground surface. |
Robert Weimer |
9/25/2003 |
Update or Other Action |
ADEC staff changed from Weimer to Harwood |
Dennis Harwood |
5/26/2004 |
Update or Other Action |
Letter sent to Milco, Inc. with reminder of grant termination date of June 30, 2004 for grant #15248333. |
Scott Pexton |
8/23/2004 |
Update or Other Action |
Sent letter to Gerald Millette, President of Milco, Inc. requesting information about his intentions to complete corrective actions and groundwater monitoring. Site transferred from Dennis Harwood to Jim Frechione. |
Scott Pexton |
10/6/2004 |
Update or Other Action |
ADEC staff changed from Frechione to Weimer |
Robert Weimer |
12/2/2005 |
Update or Other Action |
Have not received reports on site monitoring and operation of the remediation system. |
Robert Weimer |
8/24/2006 |
Update or Other Action |
RP's consultant called to say that they were preparing a workplan for groundwater monitoring and remediation of the site. |
Robert Weimer |
6/2/2008 |
Exposure Tracking Model Ranking |
Site ranked on the new Exposure Tracking Model (ETM). The ETM is a new site ranking system that looks at, based on available data, the potential exposure pathways for the contamination remaining at the site. |
Robert Weimer |
10/24/2008 |
Update or Other Action |
ADEC requests a groundwater monitoring event before the end of 2008. All monitoring wells are to be sampled for BTEX, GRO, DRO, and RRO. Monitoring wells 2,3, and 7 to be sampled for HVOCs in addition. |
Robert Weimer |
2/25/2009 |
Meeting or Teleconference Held |
Meeting with Chevron and their consultants. They are to conduct an evaluation of indoor air at this site. Chevron is to contact current owner to get site access to conduct quarterly groundwater monitoring (all monitoring wells for BTEX/GRO/DRO/RRO, plus HVOC's in monitoring wells MW2, MW3, and MW7) and operation/monitoring of the remediation system. |
Robert Weimer |
6/4/2009 |
Meeting or Teleconference Held |
Discussed site status with RPs consultant (CRA). Could only sample monitoring wells MW2/5/7, these monitoring wells need to have their vaults replaced. MW3&6 appear to have been abandoned, and MW4 is obstructed. The soil vapor extraction system is currently operating on a pulsed system, but needs safety upgrades. CRA will provide recommendations on which wells should be abandoned and which wells should be replaced. |
Robert Weimer |
6/17/2009 |
Document, Report, or Work plan Review - other |
ADEC approves treatment of one drum of contaminated purge water. |
Robert Weimer |
10/12/2009 |
Site Characterization Report Approved |
May 6, 2009 groundwater sampling. Up to 0.014 mg/l GRO, <0.11 mg/l DRO, <0.21 mg/l RRO, and <0.0005 mg/l benzene in groundwater. Contamination concentrations increased in 1 of the 4 monitoring wells sampled. Groundwater flow direction is to the northwest. Depth to groundwater is 19.25 to 20.60 feet below ground surface. |
Robert Weimer |
10/26/2009 |
Document, Report, or Work plan Review - other |
ADEC approves request for treatment of one drum of monitoring well purge water. |
Robert Weimer |
2/1/2010 |
Site Characterization Report Approved |
September 14, 2009 groundwater sampling. Up to <0.050 mg/l GRO, <0.11 mg/l DRO, <0.21 mg/l RRO, <0.0005 mg/l MTBE, and <0.0005 mg/l benzene in groundwater. Contamination concentrations stable in all 3 of the monitoring wells sampled. Groundwater flow direction is to the northwest. Depth to groundwater is 19.25 to 20.34 feet below ground surface. |
Robert Weimer |
3/11/2010 |
Meeting or Teleconference Held |
Meeting with Chevron and their consultants on 3/10/10. Chevron will submit a workplan for confirmation samples in 2010. Based on the results the SVE system will be upgraded and restarted or site clusure will be requested. We discussed that groundwater samples for volatiles should not be collected with bailers or peristaltic pumps due to the loss of volatiles, Chevron is to provide a workplan specifying how groundwater samples will be collected in the future. |
Robert Weimer |
4/14/2010 |
Site Characterization Report Approved |
DEC review of 2/25/10 Vapor Intrusion Evaluation. Occupied buildings identified near where past soil sampling identified volatile contamination remaining (up to 10,300 mg/kg GRO, 55,900 mg/kg DRO, and 52.1 mg/kg benzene). The groundwater at 18 to 20 feet below ground surface has been below cleanup levels during recent monitoring events. Based on the results of confirmation soil sampling to be conducted in 2011, further vapor intrusion site work may be required. |
Robert Weimer |
5/20/2010 |
Update or Other Action |
Approved, until further notice, no-purge groundwater sampling at this site. |
Robert Weimer |
6/17/2010 |
Site Visit |
Site visit to observe ground water sampling using no purge strategy and hydra sleeve sampling equipment. |
Brenton Porter |
2/17/2011 |
Site Characterization Report Approved |
June 17, 2010 groundwater sampling. Up to <0.05 mg/l GRO, <0.0005 mg/l MTBE, and <0.0005 mg/l benzene in groundwater. Contamination concentrations stable in all 3 of the monitoring wells sampled. Monitoring well MW4 was full of sediment and not sampled. Groundwater flow direction is to the northwest. Depth to groundwater is 18.68 to 19.70 feet below ground surface. |
Robert Weimer |
3/2/2011 |
Document, Report, or Work plan Review - other |
ADEC approves temporary storage of any purgewater generated in 2011 at the secure area at 1441 C Street. |
Robert Weimer |
4/25/2011 |
Site Characterization Report Approved |
November 14, 2010 groundwater sampling. Up to <0.01 mg/l GRO, <0.0005 mg/l MTBE, and <0.0005 mg/l benzene in groundwater. Contamination levels stable in all 3 of the monitoring wells sampled. Monitoring well MW4 was full of sediment and not sampled. Groundwater flow direction is to the southwest. Depth to groundwater is 19.48 to 20.72 feet below ground surface. |
Robert Weimer |
5/9/2011 |
Site Characterization Workplan Approved |
ADEC conditionally approves the “Revised Site Assessment Workplan” from CRA for this site. The workplan proposes to install one replacement monitoring well, and to collect confirmation soil samples from 10 soil borings at the above referenced site. The workplan is approved with the following modifications:
1. Confirmation samples collected in previously excavated areas are to be collected from native (non-backfilled) soil at about 1 foot below the previous sample depth that exceeded cleanup levels at the base of the excavation, the highest field screening depth, and the soil/water interface.
2. Confirmation samples collected in other areas are to be collected from native (non-backfilled) soil at the same depth that samples were previously collected that exceeded cleanup levels, the highest field screening depth, and the soil/water interface.
3. Add EDB and 1,2-DCA analysis to all analytical samples collected in boring SVP1.
4. Add EDB and 1,2-DCA analysis to the most likely contaminated one sample collected from the used oil tank, the most likely one contaminated sample from MW1, the most likely one contaminated sample from B4MWR, and the most likely one contaminated sample from the B7MW locations.
5. PAH analysis is only requested in 10% of the analytical samples, with a minimum of 1 per source area (Heating Oil tank, Used Oil tank, near the USTs, and near the dispenser island). They are to be collected at the location of most likely contamination for each source area.
6. The following proposed (8) boring locations may be deleted: SVP3, B2MW, north of the used oil tank, B6MW, B1MW, SVP2, SVP4, and north of the USTs.
7. The following (6) boring locations are requested: SVP1, MW1, B4MWR, at the used oil tank, at the heating oil tank, and B7MW.
8. The following proposed (1) monitoring well location may be deleted: B4MWR.
9. The following (3) boring locations are requested to be completed as monitoring wells: SVP1, MW1, and at the used oil tank.
|
Robert Weimer |
5/20/2011 |
Update or Other Action |
ADEC approves request to transport super sacks/drums of drill cuttings and vacuum truck pre-drilling soil from Chevron 30-6454 to 1441 C Street for temporary storage. ADEC requested that the total volume of soil be provided once delivery has been completed. |
Robert Weimer |
5/20/2011 |
Document, Report, or Work plan Review - other |
ADEC approves request to transport drums of decontamination and development water from Chevron 30-6454 to 1441 C Street for temporary storage. ADEC requested that the total number of drums be provided once delivery has been completed. |
Robert Weimer |
6/2/2011 |
Update or Other Action |
ADEC receives documentation that one drum of decontamination and development water and 7 drums plus 5 super sacks of contaminated drill cuttings from Chevron 30-6454 was transported to 1441 C Street for temporary storage. |
Robert Weimer |
7/26/2011 |
Offsite Soil or Groundwater Disposal Approved |
ADEC approves treatment of contaminated purge water. |
Robert Weimer |
7/28/2011 |
Offsite Soil or Groundwater Disposal Approved |
ADEC approves treatment of contaminated decon water. |
Robert Weimer |
7/28/2011 |
Offsite Soil or Groundwater Disposal Approved |
Approved request for thermal treatment of 7 drums and 5 super sacks of contaminated soil generated during the site investigation work in the summer of 2011. |
Robert Weimer |
8/16/2011 |
Document, Report, or Work plan Review - other |
ADEC approves request to purge monitoring wells prior to sampling. Purging and sampling will be conducted using a bladder pump. |
Robert Weimer |
10/31/2011 |
Document, Report, or Work plan Review - other |
DEC approves the September 9, 2011 Monitoring Well and Conduit Decommissioning Workplan for Chevron Site 30-6454, ADEC File ID: 2107.26.007. The work plan proposes to decommission monitoring well MW-3 and an unknown schedule 40 PVC pipe located in the northwest corner of the property. |
Robert Weimer |
11/21/2011 |
Offsite Soil or Groundwater Disposal Approved |
ADEC approves treatment of contaminated purge water |
Robert Weimer |
2/3/2012 |
Site Characterization Report Approved |
June 9, 2011 groundwater sampling. Up to 0.016 mg/l GRO, <0.0005 mg/l MTBE, and <0.0005 mg/l benzene in groundwater. Contamination concentrations increased in 1 of the 6 monitoring wells sampled. Monitoring well MW4 was replaced with MW10. Groundwater flow direction is to the southwest. Depth to groundwater is 18.80 to 20.50 feet below ground surface. A bladder pump was used to collect the groundwater samples. Report approved. |
Robert Weimer |
7/31/2012 |
Document, Report, or Work plan Review - other |
DEC receives documentation that monitoring well MW-3 and an unknown schedule 40 PVC pipe located in the northwest corner of the property were decommissioned on 11/2/2011. The unknown pipe is throught to be former monitoring well MW-1. |
Robert Weimer |
8/17/2012 |
Offsite Soil or Groundwater Disposal Approved |
ADEC approves offsite treatment of contaminated purge water. |
Robert Weimer |
11/5/2012 |
Site Characterization Report Approved |
August 24, 2011 groundwater sampling. Up to <0.010 mg/l GRO, <0.0005 mg/l MTBE, and <0.0005 mg/l benzene in groundwater. Contamination concentrations increased in none of the 6 monitoring wells sampled. Monitoring well MW4 was replaced with MW10. Groundwater flow direction is to the west. Depth to groundwater is 18.52 to 20.21 feet below ground surface. A bladder pump was used to collect the groundwater samples. Report approved. |
Robert Weimer |
11/28/2012 |
Offsite Soil or Groundwater Disposal Approved |
ADEC approves offsite treatment of contaminated purge water. |
Robert Weimer |
12/27/2012 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 78067 1986/1997 contamination. |
Bill O'Connell |
12/28/2012 |
Document, Report, or Work plan Review - other |
Reviewed Site Assessment Report and Cleanup Complete with Institutional Controls Request submitted on November 1, 2011. Six soil borings were advanced in 2011 and three of the borings were completed as monitoring wells. Soil borings were placed in areas noted be contaminated based on the results of the 1997 UST Closure Assessment including the dispenser area and former waste oil tank area. Soil samples collected from borings contained GRO up to 340 mg/kg at 5 feet bgs at the former dispenser area and DRO at 420 mg/kg in the same sample. No other soil samples contained contaminants above cleanup levels and groundwater samples collected from the newly installed wells did not contain contaminants above cleanup levels. |
Bill O'Connell |
1/3/2013 |
Cleanup Complete Determination Issued |
The Alaska Department of Environmental Conservation, Contaminated Sites Program (ADEC) has completed a review of the environmental records associated with the Frontier Texaco (Former Unocal #5773) located at 11301 Old Glenn Highway in Eagle River, Alaska. Based on the information provided to date, it has been determined that the contaminant concentrations remaining on site do not pose an unacceptable risk to human health or the environment and no further action is required as long as the site is in compliance with established institutional controls (ICs) |
Bill O'Connell |
2/27/2013 |
Meeting or Teleconference Held |
Meeting with Chevron and their consultants on 2/26/13. Chevron proposes to decommission the , monitoring wells, well points, and surface portions of the remediation system by July 31, 2013. |
Robert Weimer |
6/28/2013 |
Document, Report, or Work plan Review - other |
Reviewed work plan for monitoring well and remediation system decommissioning. Monitoring wells will be filled with bentonite and the upper blank casing will be removed, soil vapor probes will be filled with bentonite and then gravel, and the remediation system components will be filled with bentonite and cut off at the surface. The surface will be repaired with asphalt or concrete as appropriate. Horizontal components that do not contact groundwater will be left in place and cut off at the surface. |
Bill O'Connell |
7/5/2013 |
Document, Report, or Work plan Review - other |
Reviewed Monitoring Well and Remediation System Decommissioning work plan. Monitoring wells, SVE wells and soil vapor probes will be filled with bentonite to within 1 foot of the surface and the upper blank casing will be removed. Horizontal piping will be left in place. |
Bill O'Connell |
1/2/2014 |
Document, Report, or Work plan Review - other |
Monitoring Wells B2MW, B5MW, B7MW, B8MW, B9MW,and B10MW were decommissioned by removing the top 5 feet of casing and filling the remaining borehole with bentonite. Soil-vapor probes SVP1 through SVP4 and extraction well VEW-1 could not be located and are presumed to have been destroyed. Remediation system piping was decommissioned by cutting the piping off six inches bgs and filling with bentonite. |
Bill O'Connell |
8/7/2015 |
Update or Other Action |
This file has been archived at Alaska Archive
Barcode: 587286 Box 353 |
Susan Carberry |