Action Date |
Action |
Description |
DEC Staff |
11/17/1995 |
Leaking Underground Storage Tank Release Confirmed - Petroleum |
LUST Site created in CSP for source area ID 77980 Site added to database. |
Former Staff |
11/17/1995 |
Site Added to Database |
|
Former Staff |
1/23/1996 |
Leaking Underground Storage Tank Cleanup Initiated - Petroleum |
LUST corrective action underway. |
Former Staff |
1/23/1996 |
Underground Storage Tank Site Characterization or Assessment |
Site assessment conducted during the underground storage tank system removal. Three gasoline tanks and their piping were removed and replaced with new tanks and piping. Sampling conducted between August 29, 1995 and September 2, 1995. 0.72 mg/kg benzene and 1,100 mg/kg GRO at 10 feet below ground surface at the western dispenser. |
Former Staff |
11/20/1997 |
Update or Other Action |
ADEC sends Notification of Intent to Cost Recover Letter to Current Owner: CHEVRON PRODUCTS COMPANY, INC/PERMITS DESK |
Former Staff |
1/30/2001 |
Meeting or Teleconference Held |
Annual meeting with ADEC & Chevron reps to review AK sites and set goals for 2001. |
Linda Nuechterlein |
3/9/2003 |
Site Characterization Report Approved |
In March 2003 seven soil borings were sampled at the site. Up to 2,300 mg/kg DRO (20 feet bgs to east of tanks), and 0.30 mg/kg benzene (20 feet bgs at southeast of piping run). Six groundwater samples were collected with up to 56 mg/l DRO (near north piping run), and 19 ug/l benzene in the groundwater (north of tanks). |
Robert Weimer |
8/15/2003 |
Release Investigation |
Release investigation workplan conditionally approved for the installation of additional monitoring wells to define the extent of the groundwater contamination. |
Robert Weimer |
9/23/2003 |
Leaking Underground Storage Tank Corrective Action Underway |
Approved 2.26 cubic yards of contaminated soil to be thermally treated at ASR. |
Robert Weimer |
8/11/2004 |
Document, Report, or Work plan Review - other |
June 5, 2004 groundwater sampling. Up to 3.2 mg/l DRO in groundwater. Contaminant concentrations increased in two of the monitoring wells. |
Robert Weimer |
12/6/2004 |
Document, Report, or Work plan Review - other |
September 26, 2004 groundwater sampling. Up to 1.8 mg/l DRO in groundwater. Contaminant concentrations increased in two of the monitoring wells. |
Robert Weimer |
2/4/2005 |
Document, Report, or Work plan Review - other |
January 10, 2005 groundwater monitoring event. All 4 monitoring wells were inaccessible due to snow and ice. |
Robert Weimer |
2/23/2005 |
Meeting or Teleconference Held |
Meeting with RP's new consultant to discuss site. Need corrective action plan remaining soil contamination identified in 1995 and 2003. May also need to install additional monitoring wells to define the extent of the groundwater contamination at the site. |
Robert Weimer |
5/31/2005 |
Document, Report, or Work plan Review - other |
March 24, 2005 groundwater sampling. Up to 1.1 mg/l DRO in groundwater. Contaminant concentrations were stable in the monitoring wells this monitoring event. Three of the monitoring wells were not accessible due to ice. |
Robert Weimer |
7/19/2005 |
Document, Report, or Work plan Review - other |
May 17, 2005 groundwater sampling. Up to 3.9 mg/l DRO in groundwater. Contaminant concentrations appear to be increasing in the monitoring wells. Groundwater flow direction is to the northwest. |
Robert Weimer |
8/29/2005 |
Update or Other Action |
Reviewed draft release investigation report and discussed with consultant. |
Robert Weimer |
9/12/2005 |
Update or Other Action |
Reviewed and approved workplan for the installation of 2 additional monitoring wells to help define the extent of the soil and groundwater contamination at the site. |
Robert Weimer |
10/3/2005 |
Update or Other Action |
Approved corrective action plan for 7 drums of contaminated soil to be thermally treated at ASR. |
Robert Weimer |
11/8/2005 |
Update or Other Action |
Approved sampling to be conducted in November. Approved suspending sampling for GRO in all of the monitoring wells. |
Robert Weimer |
11/29/2005 |
Document, Report, or Work plan Review - other |
September 25, 2005 groundwater sampling. Up to 1.2 mg/l DRO in groundwater. Contaminant concentrations decreased in the monitoring wells from the previous event. Groundwater flow direction is to the northwest. Depth to groundwater is 16 to 33 feet below ground surface. |
Robert Weimer |
12/2/2005 |
Offsite Soil or Groundwater Disposal Approved |
ADEC approves treatment of a drum of contaminated purge water. |
Robert Weimer |
1/23/2006 |
Document, Report, or Work plan Review - other |
November 16, 2005 groundwater sampling. Up to 5.0 mg/l DRO in groundwater. Contaminant concentrations appear to be increasing in the monitoring wells. Groundwater flow direction is to the northwest. Depth to groundwater is 21 to 33 feet below ground surface. |
Robert Weimer |
1/23/2006 |
Site Characterization Report Approved |
Two additional monitoring wells (MW-5 and MW-6) were installed on September of 2005. Up to 7,800 mg/kg DRO and 0.06 mg/kg benzene where in the soil at the MW-5 location. |
Robert Weimer |
1/23/2006 |
Update or Other Action |
ADEC approves suspending the sampling of all monitoring wells (except MW-5) for BTEX. All 6 monitoring wells are to continue to be sampled for DRO. |
Robert Weimer |
9/25/2006 |
Document, Report, or Work plan Review - other |
March 29, 2006 groundwater sampling. Up to 1.2 mg/l DRO in groundwater. Contaminant concentrations appear to be decreasing in the monitoring wells. Groundwater flow direction is to the north by northwest. Depth to groundwater is 22 to 34 feet below ground surface. |
Robert Weimer |
10/5/2006 |
Document, Report, or Work plan Review - other |
May 17, 2006 groundwater sampling. Up to 0.55 mg/l DRO in groundwater. Contaminant concentrations appear to be decreasing in the monitoring wells. Groundwater flow direction is to the north by northwest. Depth to groundwater is 21 to 33 feet below ground surface. |
Robert Weimer |
11/1/2006 |
Offsite Soil or Groundwater Disposal Approved |
ADEC approves treatment of contaminated purge water. |
Robert Weimer |
12/22/2006 |
Document, Report, or Work plan Review - other |
September 26, 2006 groundwater sampling. Up to 1.5 mg/l DRO in groundwater. Contaminant concentrations appear to be increasing in the monitoring wells. Groundwater flow direction is to the north by northwest. Depth to groundwater is 20 to 33 feet below ground surface. |
Robert Weimer |
4/2/2007 |
Meeting or Teleconference Held |
Meeting with Chevron to discuss this site. They are to continue with semi-annual monitoring and sampling. |
Robert Weimer |
10/2/2007 |
Document, Report, or Work plan Review - other |
January 17, 2007 groundwater sampling. Non-detect (<1.19 mg/l) DRO in groundwater. Contaminant concentrations appear to be decreasing in the monitoring wells. Groundwater flow direction is to the north by northwest. Depth to groundwater is 22 to 34 feet below ground surface. |
Robert Weimer |
12/12/2007 |
Document, Report, or Work plan Review - other |
March 29, 2007 groundwater sampling. Up to 2.3 mg/l DRO in groundwater. Contaminant concentrations appear to be increasing in the monitoring wells. Groundwater flow direction is to the north by northwest. Depth to groundwater is 31 to 34 feet below ground surface. |
Robert Weimer |
12/17/2007 |
Conceptual Site Model Submitted |
Reviewed preliminary conceptual site model |
Robert Weimer |
12/20/2007 |
Document, Report, or Work plan Review - other |
May 18, 2007 groundwater sampling. Up to 2.6 mg/l DRO in groundwater. Contaminant concentrations appear to be increasing in the monitoring wells. Groundwater flow direction is to the north by northwest. Depth to groundwater is 20.5 to 31.3 feet below ground surface. |
Robert Weimer |
3/5/2008 |
Meeting or Teleconference Held |
Meeting with Chevron and their consultants. Chevron to conduct and indoor air evaluation for this site. They plan to replace monitoring well MW-1, continue monitoring, and to evaluate if additional assessment is needed. |
Robert Weimer |
4/7/2008 |
Document, Report, or Work plan Review - other |
July 10, 2007 groundwater sampling. Up to 7.7 mg/l DRO and non-detect (<0.001 mg/l) benzene in groundwater. Contaminant concentrations appear to be increasing in the monitoring wells. Groundwater flow direction is to the north by northwest. Depth to groundwater is 21.2 to 33.79 feet below ground surface. |
Robert Weimer |
4/17/2008 |
Exposure Tracking Model Ranking |
Site ranked on the new Exposure Tracking Model (ETM). The ETM is a new site ranking system that looks at, based on available data, the potential exposure pathways for the contamination remaining at the site. |
Robert Weimer |
4/21/2008 |
Document, Report, or Work plan Review - other |
ADEC approves workplan for the abandonment of monitoring well MW-1 and the installation of a replacement monitoring well near that location. The monitoring well is being abandoned due to insufficient water. The replacement monitoring well will have a longer and deeper screened interval. |
Robert Weimer |
5/5/2008 |
Document, Report, or Work plan Review - other |
September 20, 2007 groundwater sampling. Up to 0.69 mg/l DRO and non-detect (<0.001 mg/l) benzene in groundwater. Results are biased low due to failure to keep the samples chilled. Contaminant concentrations appear to be decreasing in the monitoring wells. Groundwater flow direction is to the northwest. Depth to groundwater is 21.96 to 33.92 feet below ground surface. |
Robert Weimer |
8/5/2008 |
Offsite Soil or Groundwater Disposal Approved |
ADEC approves treatment of contaminated purge water. |
Robert Weimer |
9/8/2008 |
Document, Report, or Work plan Review - other |
March 28, 2008 groundwater sampling. Up to 0.391 mg/l DRO and non-detect (<0.0005 mg/l) benzene in groundwater. Contaminant concentrations appear to be decreasing in the monitoring wells. Groundwater flow direction is to the northwest. Depth to groundwater is 22.21 to 33.85 feet below ground surface. |
Robert Weimer |
9/25/2008 |
Offsite Soil or Groundwater Disposal Approved |
ADEC approves treatment of contaminated purge water. |
Robert Weimer |
9/30/2008 |
Offsite Soil or Groundwater Disposal Approved |
ADEC approves treatment of additional drums of contaminated purge water. |
Robert Weimer |
10/20/2008 |
Update or Other Action |
ADEC approves reducing the monitoring of monitoring wells MW-1, MW-2, MW-3, MW-5, and MW-6 to semi-annual for DRO; monitoring well MW-5 to annual for BTEX; and suspending sampling of MW-4. |
Robert Weimer |
11/17/2008 |
Offsite Soil or Groundwater Disposal Approved |
ADEC approves treatment of contaminated purge water. |
Robert Weimer |
11/21/2008 |
Offsite Soil or Groundwater Disposal Approved |
Review and approve treatment of two contaminated drill cuttings. The cuttings were generated in September 2008 during the installation of the replacement monitoring well MW-1R. |
Robert Weimer |
1/30/2009 |
Document, Report, or Work plan Review - other |
June 9, 2008 groundwater sampling. Up to 0.32 mg/l DRO, non-detect (<0.01 mg/l) GRO, and non-detect (<0.001 mg/l) benzene in groundwater. Contaminant concentrations increased in 1 of the 5 monitoring wells sampled. Groundwater flow direction is to the northwest. Depth to groundwater is 21.00 to 33.08 feet below ground surface. |
Robert Weimer |
2/25/2009 |
Meeting or Teleconference Held |
Meeting with Chevron and their consultants. Chevron to conduct and indoor air evaluation for this site. Chevron to do additional evaluation on the source of the contamination found in monitoring well MW-1R. |
Robert Weimer |
2/26/2009 |
Document, Report, or Work plan Review - other |
September 15, 2008 and October 28, 2008 groundwater sampling. Up to 0.63 mg/l DRO, 0.01 mg/l GRO, and non-detect (<0.001 mg/l) benzene in groundwater. Contaminant concentrations increased in 4 of the 6 monitoring wells. Groundwater flow direction is to the northwest. Depth to groundwater is 30.55 to 33.90 feet below ground surface. |
Robert Weimer |
2/27/2009 |
Document, Report, or Work plan Review - other |
On October 23, 2008 a replacement monitoring well was installed MW-1R, and monitoring well MW-1 was decommissioned. The decommissioned monitoring well was installed to 23.25 feet below ground surface (bgs) but historically contained insufficient groundwater for sampling. Soil samples were collected during the installation of the replacement monitoring well, up to 4.1 mg/kg benzene (at 21 feet bgs), 9.1 mg/kg GRO, and 52 mg/kg DRO in the soil samples collected. These results are biased low because an air rotary rig was used to drill the monitoring well.
Perched groundwater was encountered at 19 feet bgs, with a clay layer at 20 to 21.5 feet bgs. The replacement monitoring well was screened from 25 to 40 feet bgs, and has static water at 30.55 feet bgs. This replacement monitoring well is sampling groundwater in the 2nd aquifer which the other site monitorings wells are sampling. |
Robert Weimer |
6/17/2009 |
Offsite Soil or Groundwater Disposal Approved |
ADEC approves treatment of one drum of contaminated purge water. |
Robert Weimer |
10/1/2009 |
Document, Report, or Work plan Review - other |
May 6, 2009 groundwater sampling. Up to 1.5 mg/l DRO, and non-detect (<0.005 mg/l) benzene in groundwater. Contaminant concentrations increased in 2 of the 5 monitoring wells sampled. Groundwater flow direction is to the north by northwest. Depth to groundwater is 30.63 to 33.72 feet below ground surface. |
Robert Weimer |
1/29/2010 |
Document, Report, or Work plan Review - other |
September 14, 2009 groundwater sampling. Up to 1.1 mg/l DRO, 0.010 mg/l GRO, and <0.005 mg/l benzene in groundwater. Contaminant concentrations increased in 2 of the 5 monitoring wells sampled. Groundwater flow direction is to the north by northwest. Depth to groundwater is 30.68 to 34.17 feet below ground surface. |
Robert Weimer |
3/11/2010 |
Meeting or Teleconference Held |
Meeting with Chevron and their consultants on 3/10/10. We discussed that there were documented releases at this site found in 1995 and 2003, Chevron will submit a workplan for collecting confirmation soil samples at those locations. We discussed that groundwater samples for volatiles should not be collected with bailers or peristaltic pumps due to the loss of volatiles, Chevron is to provide a workplan specifying how groundwater samples will be collected in the future. |
Robert Weimer |
4/13/2010 |
Update or Other Action |
During the April 2010 groundwater monitoring event HydraSleeve(TM) samplers will be used for VOC sampling at this site. |
Robert Weimer |
8/23/2010 |
Offsite Soil or Groundwater Disposal Approved |
ADEC approves treatment of contaminated purge water. |
Robert Weimer |
8/27/2010 |
Offsite Soil or Groundwater Disposal Approved |
ADEC approves treatment of contaminated purge water. |
Robert Weimer |
2/15/2011 |
Document, Report, or Work plan Review - other |
April 21, 2010 groundwater sampling. Up to 1.1 mg/l DRO, 0.12 mg/l GRO, and non-detect (<0.005 mg/l) benzene in groundwater. Contaminant concentrations increased in 2 of the 4 monitoring wells sampled. Groundwater flow direction is to the northwest. Depth to groundwater is 30.30 to 33.04 feet below ground surface. |
Robert Weimer |
2/23/2011 |
Meeting or Teleconference Held |
Meeting with Chevron and their consultants on 2/23/11. We discussed that there were documented releases at this site found in 1995 and 2003, and 4.1 mg/kg benzene identified in 2008 at the site. Chevron will submit a workplan for collecting confirmation soil samples at the site to assess the current soil contamination levels and extent at the site so the site can be evaluated for Corrective Action Complete with ICs. The site will also be reviewed for reducing groundwater monitoring from semi-annual to annual. |
Robert Weimer |
3/2/2011 |
Document, Report, or Work plan Review - other |
ADEC approves temporary storage of any purgewater generated in 2011 at the secure area at 1441 C Street. |
Robert Weimer |
4/8/2011 |
Update or Other Action |
ADEC approves request for annual groundwater monitoring. |
Robert Weimer |
6/16/2011 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 77980 1995 UST release. |
Bill O'Connell |
6/28/2011 |
Document, Report, or Work plan Review - other |
July 22, 2010 groundwater sampling. Up to 0.8 mg/l DRO, non-detect (<0.01 mg/l GRO), and non-detect (<0.0005 mg/l) benzene in groundwater. Contaminant concentrations increased in 1 of the 5 monitoring wells sampled. Groundwater flow direction is to the northwest. Depth to groundwater is 30.50 to 33.23 feet below ground surface. Chevron's consultant recommends continued groundwater monitoring to evaluate site groundwater conditions. |
Robert Weimer |
9/1/2011 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 77980 1995 UST release. |
Robert Weimer |
10/26/2011 |
Offsite Soil or Groundwater Disposal Approved |
ADEC approves treatment of contaminated purge water. |
Robert Weimer |
3/7/2012 |
Meeting or Teleconference Held |
Meeting with Chevron and their consultants on 2/28/12. Chevron's request for cleanup complete with IC's was not appoved. Chevron is conducting semi-annual groundwater monitoring of monitoring well MW-3. The site monitoring wells are not approved to be decommissioned. We discussed that there was high field reading soils left at the southern product piping that will need to be assessed and cleaned up when it becomes accessible in the future. |
Robert Weimer |
8/17/2012 |
Offsite Soil or Groundwater Disposal Approved |
ADEC approves offsite treatment of contaminated purge water. |
Robert Weimer |
9/17/2012 |
Offsite Soil or Groundwater Disposal Approved |
ADEC approves offsite treatment of contaminated purge water. |
Robert Weimer |
1/15/2013 |
Document, Report, or Work plan Review - other |
August 3, 2011 groundwater sampling. Up to 1.7 mg/l DRO (MW-3, the highest concentrations since 2003), 0.014 mg/l GRO, and non-detect (<0.0005 mg/l) benzene in groundwater. Contaminant concentrations increased in 4 of the 5 monitoring wells sampled. Groundwater flow direction is to the northwest. Depth to groundwater is 30.67 to 32.10 feet below ground surface. Chevron's consultant recommends continued groundwater monitoring to evaluate site groundwater conditions. |
Robert Weimer |
1/15/2013 |
Document, Report, or Work plan Review - other |
May 30, 2012 groundwater sampling. Up to 1.6 mg/l DRO (MW-5, the highest concentrations since 2005), non-detect (<0.010 mg/l) GRO, and non-detect (<0.0005 mg/l) benzene in groundwater. Contaminant concentrations increased in 2 of the 5 monitoring wells sampled. Groundwater flow direction is to the northwest. Depth to groundwater is 29.95 to 31.61 feet below ground surface. |
Robert Weimer |
1/29/2013 |
Document, Report, or Work plan Review - other |
August 23, 2012 groundwater sampling. Up to 1.1 mg/l DRO, non-detect (<0.010 mg/l GRO), and non-detect (<0.0005 mg/l) benzene in groundwater. Contaminant concentrations increased in 1 of the 5 monitoring wells sampled. Groundwater flow direction is to the northwest. Depth to groundwater is 30.25 to 33.28 feet below ground surface. The consultant recommends continued semi-annual groundwater monitoring. |
Robert Weimer |
2/27/2013 |
Meeting or Teleconference Held |
Meeting with Chevron and their consultants on 2/26/13. Chevron proposes to continue to conduct semi-annual groundwater monitoring to monitor for natural attenuation and trends. Chevron is going to submit a plan for the installation and sampling of at least 3 monitoring wells near (2, 3, 5) to assess the shallow groundwater contamination trends and migration. The shallow groundwater was encountered around 20 feet below ground surface, all existing monitoring wells are sampling the deeper groundwater at 30 to 33 feet below ground surface. The next groundwater sampling event they will sample both using no purge and purge help evaluate that the past no purge results were providing comparable data. We discussed that all semi-annual monitoring events need to be at least 120 days apart. |
Robert Weimer |
3/26/2013 |
Update or Other Action |
DEC conditionally approves the use of a portable activated carbon (gac) filter system for this site to treat water generated during groundwater monitoring. The storage of water at the site or the secure storage area at 1441 C Street is also approved. |
Robert Weimer |
1/15/2014 |
Document, Report, or Work plan Review - other |
May 6, 2013 groundwater sampling. Up to 1.8 mg/l DRO, 0.013 mg/l GRO, and 0.00067 mg/l benzene in groundwater. The 1.8 mg/l DRO result was the highest concentration in MW-5 since 2005. Contaminant concentrations increased in 5 of the 5 monitoring wells sampled. Groundwater flow direction is to the northwest. Depth to groundwater is 29.96 to 32.04 feet below ground surface. The consultant recommends continued semi-annual groundwater monitoring. The samples were collect by both no-purge (Hydrasleeve for volatiles and bailer for non-volatiles) and purge (bladder pump). The Hydrasleeve/bailer samples were collected from the top of water column. Since the sampling interval for the bladder pump was not documented its results are biased low and the no purge sampling may not be representative. |
Robert Weimer |
2/27/2014 |
Meeting or Teleconference Held |
Meeting with Chevron and their consultants on February 27, 2014. Because of problems with last year’s purge/no-purge sampling the next groundwater sampling event they will sample both using no purge and purge help evaluate that the past no purge results were providing comparable data or they will switch to no purge for future sampling events. We discussed that the groundwater samples need to be collected as close as possible to the soil/water interface, with the pump intake within a foot of the soil/water interface at the time of the sampling. We discussed that since the correct depth as required in the sampling work plan was not sampled the results are considered biased low and won’t be used for site closure evaluation or trend analysis. Chevron directed their consultant to document the sampling depth in future sampling events and to collected the water samples from as close as possible to the soil/water interface within the top foot in the monitoring wells as specified in the sampling work plan. The consultant will provide more information in their site reports in accordance with DEC’s 9/23/2009 Site Characterization Work Plan and Reporting Guidance for Investigation of Contaminated Sites. |
Robert Weimer |
5/6/2014 |
Document, Report, or Work plan Review - other |
September 16, 2013 groundwater sampling. Up to 0.85 mg/l DRO, non-detect (<0.05 mg/l) GRO, and 0.00038 mg/l benzene in groundwater. Contaminant concentrations increased in 0 of the 5 monitoring wells sampled. Groundwater flow direction was to the north by northwest. Depth to groundwater was 30.09 to 32.54 feet below ground surface. The consultant recommends continued semi-annual groundwater monitoring. The samples were collected with a bladder pump after purging. Since the sampling interval for the bladder pump was not documented its results are considered biased low. |
Robert Weimer |
2/11/2015 |
Document, Report, or Work plan Review - other |
April 30, 2014 groundwater sampling. Up to 0.79 mg/l DRO, non-detect (<0.05 mg/l) GRO, and non-detect (<0.00015 mg/l) benzene in groundwater. Contaminant concentrations increased in 0 of the 4 monitoring wells sampled. Monitoring well MW-3 could not be sampled due to ice in the well. Groundwater flow direction was to the north by northwest. Depth to groundwater was 30.27 to 31.39 feet below ground surface. The samples were collected with a bladder pump after purging. Since the sampling interval for the bladder pump was not near the soil/water interface (Up to 1.92 feet below the water surface in monitoring wells MW-1R and MW5) the results are considered biased low. |
Robert Weimer |
2/12/2015 |
Document, Report, or Work plan Review - other |
October 1, 2014 groundwater sampling. Up to 1.0 mg/l DRO, non-detect (<0.05 mg/l) GRO, and 0.58 ug/l benzene in groundwater. Contaminant concentrations increased in 5 of the 5 monitoring wells sampled. Groundwater flow direction was to the north by northwest. Depth to groundwater was 30.20 to 32.92 feet below ground surface. The samples were collected with a bladder pump after purging. Since the sampling interval for the bladder pump was not near the soil/water interface in all of the monitoring wells (Up to 2.38 feet below the water surface in monitoring wells MW2) the results are considered biased low. |
Robert Weimer |
2/23/2015 |
Update or Other Action |
As discussed with CRA and Chevron in the February 2014 meeting it is critical to have sampling data with good QA/QC to make decisions regarding monitoring frequency and possible site closure. We discussed that there were past problems with documenting the depth of sampling in the monitoring wells at this site and that the groundwater samples needs to be collected as close as possible to the soil/water interface, with the pump intake within a foot of the soil/water interface at the time of the sampling. In that meeting Chevron directed their consultant to document the sampling depth in future sampling events and to collected the water samples from as close as possible to the soil/water interface within the top foot in the monitoring wells as specified in the sampling work plan.
Because of problems with not collecting samples from the as close as possible to the soil/water interface as required (for the 4/30/2014 and 10/1/2014 sampling events the pump intake was up to 2.38 feet below the soil/water interface), the request for a reduction of sampling frequency to an annual basis is not approved. Once we have a monitoring event where the intake for the bladder pump is within 1 foot of the soil/water interface at the time of the sampling in each monitoring well and no other QA/QC problems DEC can review this site for reduction to annual basis for those monitoring wells.
|
Robert Weimer |
4/22/2015 |
Document, Report, or Work plan Review - other |
DEC review of the 2015 Groundwater Monitoring and Sampling Work Plan for the Chevron Station 91252 site located at 11836 Old Glenn Highway. As discussed this morning and as discussed in previous meetings, it is critical to have sampling data with good QA/QC to make decisions regarding future monitoring frequency and possible site closure.
For next monitoring event DEC requests that all of the site monitoring wells (MW-1R, MW-2, MW-3, MW-4, MW-5, and MW-6) be sampled and analyzed for BTEX, GRO, and DRO. Based on the results of that sampling we can evaluate reductions in groundwater sampling at this site.
|
Robert Weimer |
4/13/2016 |
Document, Report, or Work plan Review - other |
May 6, 2015 groundwater sampling. Up to 1.3 mg/l DRO, non-detect GRO and benzene in groundwater. Contaminant concentrations increased in 3 of the 6 monitoring wells sampled. Groundwater flow direction was to the north by northwest. Depth to groundwater was 30.50 to 33.56 feet below ground surface. The samples were collected with a bladder pump after purging. The sampling interval for the bladder pump was near the soil/water interface as required. |
Robert Weimer |
11/14/2016 |
Document, Report, or Work plan Review - other |
October 20, 2015 groundwater sampling. Up to 2.0 mg/l DRO, 0.017 mg/l GRO and non-detect benzene in groundwater. Contaminant concentrations increased in 2 of the 6 monitoring wells sampled. Groundwater flow direction was to the north by northwest. Depth to groundwater was 30.25 to 33.24 feet below ground surface. The samples were collected with a bladder pump after purging. The sampling interval for the bladder pump was near the soil/water interface as required. |
Robert Weimer |
1/25/2017 |
Document, Report, or Work plan Review - other |
May 19, 2016 groundwater sampling. Up to 1.6 mg/l DRO, 0.014 mg/l GRO and non-detect benzene in groundwater. Contaminant concentrations increased in 3 of the 5 monitoring wells sampled. Groundwater flow direction was to the north by northwest. Depth to groundwater was 31.20 to 33.69 feet below ground surface. The samples were collected with a bladder pump after purging. The sampling interval for the bladder pump was near the soil/water interface as required. |
Robert Weimer |
2/23/2017 |
Document, Report, or Work plan Review - other |
September 28, 2016 groundwater sampling. Up to 1.6 mg/l DRO, 0.014 mg/l GRO and non-detect benzene in groundwater. Contaminant concentrations increased in 4 of the 5 monitoring wells sampled. Groundwater flow direction was to the north by northwest. Depth to groundwater was 30.36 to 33.56 feet below ground surface. The samples were collected with a bladder pump after purging. The sampling interval for the bladder pump was near the soil/water interface as required. |
Robert Weimer |
2/28/2017 |
Update or Other Action |
DEC approves request to suspend, until further notice, BTEX (8021) and GRO sampling of the current site monitoring wells and DRO sampling in monitoring wells MW-1R, MW-4, and MW-6. For next monitoring event DEC requests that all of the site monitoring wells (MW-1R, MW-2, MW-3, MW-4, MW-5, and MW-6) be sampled and analyzed for full VOCs (8260) and PAH. DEC also request that monitoring wells MW-2, MW-3, and MW-5 be sampled for DRO. Based on the results of that sampling we can evaluate further reductions in groundwater sampling at this site. |
Robert Weimer |
10/30/2017 |
Document, Report, or Work plan Review - other |
May 22, 2017 groundwater sampling. Up to 2.3 mg/l DRO and non-detect benzene in groundwater. Contaminant concentrations increased in 2 of the 3 monitoring wells sampled for DRO. Groundwater flow direction was to the north by northwest. Depth to groundwater was 30.33 to 32.94 feet below ground surface. Six monitoring wells were sampled for PAHs and full VOCs. All detected PAHs and VOCs were below current cleanup levels. The samples were collected with a bladder pump after purging. The sampling interval for the bladder pump was near the soil/water interface as required. Naphthalene results were not reported in the 8260 analysis as required. |
Robert Weimer |
3/30/2018 |
Document, Report, or Work plan Review - other |
October 16, 2017 groundwater sampling. Up to 1.8 mg/l DRO and non-detect benzene in groundwater. Contaminant concentrations increased in 0 of the 3 monitoring wells sampled for DRO. Groundwater flow direction was to the north by northwest. Depth to groundwater was 30.34 to 33.41 feet below ground surface. The samples were collected with a bladder pump after purging. The sampling interval for the bladder pump was near the soil/water interface as required. |
Robert Weimer |
6/21/2018 |
Document, Report, or Work plan Review - other |
April 19, 2018 groundwater sampling. Up to 1.5 mg/l DRO in groundwater. Contaminant concentrations increased in 2 of the 3 monitoring wells sampled for DRO. Groundwater flow direction was to the north by northwest. Depth to groundwater was 30.27 to 32.72 feet below ground surface. The samples were collected with a bladder pump after purging. The sampling interval for the bladder pump was near the soil/water interface as required. |
Robert Weimer |
11/21/2018 |
Document, Report, or Work plan Review - other |
September 4, 2018 groundwater sampling. Up to 3.4 mg/l DRO in groundwater. Contaminant concentratons increased in 2 of the 3 monitoring wells sampled for DRO. Groundwater flow direction was to the north by northwest. Depth to groundwater was 30.34 to 33.34 feet below ground surface. The samples were collected with a bailer after purging. |
Robert Weimer |
9/23/2019 |
Update or Other Action |
ADEC requests for this site that the monitoring wells are purged prior to sampling, and that the intake of the bladder pump/in-well pump be documented in the field notes to be within the top foot of the water column at the time of the sampling. Also VOC sampling needs to include the full 8260 VOC list including naphthalene. |
Robert Weimer |
11/5/2019 |
Document, Report, or Work plan Review - other |
Meeting with Chevron's consultant. They will provide a work plan for installing monitoring wells to assess the shallower aquifer at the site. This would include soil and quarterly groundwater samples in the areas near monitoring wells MW1R, MW2, MW3, and MW5. Soil and groundwater sampling would include full VOCs, PAH, GRO, and DRO analysis. DEC requested that site reports be submitted within 60 days of sampling, VOC analysis include naphthalene, and groundwater monitoring figure include diagram showing historic groundwater flow direction. DEC requested that the next groundwater monitoring event include analysis for full VOCs in monitoring wells MW2, MW3, and MW5. The mentioned that monitoring well MW3 has been damaged so it will need to be replaced. |
Robert Weimer |
1/7/2020 |
Document, Report, or Work plan Review - other |
April 8, 2019 groundwater sampling. Up to 0.92 mg/l DRO. Contaminant concentrations increased in 0 of the 2 monitoring wells sampled for DRO. Monitoring well MW-3 was sampled because it was purged dry and did not recharge. Groundwater flow direction was to the north by northwest. Depth to groundwater was 30.27 to 32.72 feet below ground surface. The samples were collected with a bladder pump after purging. The sampling interval for the bladder pump was near the soil/water interface as required. |
Robert Weimer |
3/12/2020 |
Update or Other Action |
ADEC requests for this site that the monitoring wells are purged prior to sampling, and that the intake of the bladder pump/in-well pump be documented in the field notes to be within the top foot of the water column at the time of the sampling. Needs to include the requested full VOC (8260) analysis, including naphthalene in monitoring wells MW2, MW3, and MW5. ADEC is also requesting that all reports be submitted within 60 days of the sampling and the groundwater monitoring figure include a diagram showing historic groundwater flow directions. |
Robert Weimer |
3/17/2020 |
Document, Report, or Work plan Review - other |
DEC reviewed 2020 groundwater sampling plan and provided the following comments: For all future monitoring events please make sure that the field notes document the measurement of the pump intake that is within the top foot of the water column at the time of the sampling unless the top of the well screened interval is deeper, then in that case from the top foot of that screened interval. For all future monitoring events any monitoring well where BTEX or HVOC sampling is proposed it needs to be the full VOC (method 8260) list, including naphthalene. The field QC samples are per day of sampling at a site. For all future monitoring events all reports be submitted within 60 days of the sampling and the groundwater monitoring figure include a diagram showing historic groundwater flow directions. For all future monitoring events if a monitoring well is low yield and purges dry then a sample will still need to be collected that monitoring event once the monitoring well has recharged to approximately 80% of its pre-purge volume. If it has not returned to 80% of its pre-purged volume during that sampling day DEC requests that you return to the site early the next day to attempt to collect the water sample. DEC also requested full VOC for monitoring wells MW2, MW3, and MW5. |
Robert Weimer |
11/23/2020 |
Document, Report, or Work plan Review - other |
October 2, 2020 groundwater sampling. Monitoring wells MW-2, MW-3 and MW-5 were sampled for DRO and VOCs. The following analytes were detected DRO (up to 1.46 mg/L), benzene (0.000291 mg/L), EDC (0.000733 mg/L). Duplicate sample was collected from MW-5. Groundwater flow direction was to the north by northwest. Depth to groundwater was 30.20 to 33.48 feet below ground surface. Sample was collected with a bladder pump after purging with the sampling interval near the soil/water interface. |
Rebekah Reams |
12/11/2020 |
Document, Report, or Work plan Review - other |
April 1, 2020 groundwater sampling. Monitoring wells MW-2 and MW-5 were obstructed by ice and could not be sampled. MW-3 was sampled, DRO and VOCs were analyzed and no analytes were detected. The blind duplicate from well MW-3 was attempted but not collected due to slow well recharge. Groundwater flow direction was to the north by northwest. Depth to groundwater was 30.50 to 33.88 feet below ground surface. Sample was collected with a bladder pump after purging with the sampling interval near the soil/water interface. |
Rebekah Reams |
12/11/2020 |
Document, Report, or Work plan Review - other |
September 9, 2019 groundwater sampling. Up to 1.7 mg/L DRO. Contaminant concentrations increased at 1 of the 2 monitoring wells sampled for DRO. Monitoring well MW-3 was not sampled because it was purged dry and did not recharge. Groundwater flow direction was to the north by northwest. Depth to groundwater was 30.51 to 33.97 feet below ground surface. Samples were collected with a bladder pump after purging with the sampling interval near the soil/water interface. |
Rebekah Reams |
1/15/2021 |
Meeting or Teleconference Held |
DEC staff met with Chevron Environmental Management Company (CEMC) and Arcadis to discuss Chevron sites located in Alaska during the Annual Portfolio Meeting on January 14th and 15th, 2021. |
Rebekah Reams |
2/2/2021 |
Document, Report, or Work plan Review - other |
DEC provided comments on the Second Semi-Annual Groundwater Monitoring Report submitted by Arcadis on November 23, 2020. |
Rebekah Reams |
2/2/2021 |
Workplan Requested |
DEC provided a response to the Monitoring Well Technical Memorandum submitted by Arcadis on March 17, 2020 that addressed a request for the installation of shallow monitoring wells to evaluate hydrocarbon impacts within a perched aquifer believed to be present at the site. The DEC maintains that this data gap needs to be addressed, which can be completed through the installation of shallow monitoring wells or the advancement of additional soil borings at the site. Site work should include the evaluation of VOCs and PAHs, which have not been analyzed in previous soil samples collected at the site. |
Rebekah Reams |
5/13/2021 |
Document, Report, or Work plan Review - other |
DEC provided comments on the Monitoring Well Installation and Soil Boring Work Plan submitted on April 13, 2021. This document outlines plans to install three monitoring wells and one soil boring to establish if a confined shallow aquifer is present at the site, to assess contaminant attenuation at locations with former cleanup level exceedances, and to analyze samples for Contaminants of Potential Concern (COPCs) that have not previously been assessed at the site. |
Rebekah Reams |
6/7/2021 |
Document, Report, or Work plan Review - other |
April 6, 2021 groundwater sampling. Monitoring wells MW-3 and MW-5 were sampled for DRO and VOCs. Monitoring wells MW-2 and MW-6 were frozen at roughly 2 feet below top of casing and were not sampled. Groundwater flow direction was to the northwest. Depth to groundwater was 30.35 to 33.99 feet below ground surface. |
Rebekah Reams |
7/28/2021 |
Site Characterization Workplan Approved |
DEC provided conditional approval for the Revised Monitoring Well Installation and Soil Boring Work Plan. This document outlines plans to advance soil borings to confirm contaminant concentrations near former sample location MW-5 and DI1A-S2 and to evaluate whether a confined shallow aquifer is present at the site by installing and sampling three shallow monitoring wells. |
Rebekah Reams |
10/29/2021 |
Document, Report, or Work plan Review - other |
August 25, 2021 groundwater sampling. Monitoring wells MW-2, MW-3 and MW-5 were sampled for DRO and VOCs. Groundwater flow direction was to the north by northwest. Depth to groundwater was 30.16 to 33.38 feet below ground surface. |
Rebekah Reams |
12/10/2021 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 77980 1995 UST release. |
Rebekah Reams |
1/18/2022 |
Document, Report, or Work plan Review - other |
Subsurface soil investigation was completed on September 29th through October 1st, 2021 to determine whether groundwater and soil impacts are present within a potential perched aquifer, to confirm current contaminant concentration, and to evaluate additional constituents of potential concern at the site. Monitoring well MW-7 through MW-9 were planned to be installed to investigation whether a perched aquifer is present at the site at soil borings SB-8 and SB-9 were planned to confirm former exceedances present near MW-5 and DI1A-S2, respectively. Due to refusal, SB-9 and MW-7 were not able to be advanced. Soil samples were analyzed for GRO, DRO, VOC, PAHs, and total lead. All analytical soil sample results were below cleanup levels. |
Rebekah Reams |
4/8/2022 |
Offsite Soil or Groundwater Disposal Approved |
DEC approved transport of 0.8 cubic yards of soil and 130 gallons of water generated during fall 2021 site investigations. |
Rebekah Reams |
6/9/2022 |
Document, Report, or Work plan Review - other |
March 30, 2022 groundwater sampling. Monitoring wells MW-2 and MW-5 were sampled for DRO and VOCs. All analytes were not detected or were detected below cleanup levels. The well casings of MW-1R and MW-3 was frozen. MW-8 was not located due to ice and snow, and MW-9 was dry. Groundwater flow direction was to the north by northwest. Depth to groundwater was 31.00 to 33.15 feet below ground surface. |
Rebekah Reams |
9/29/2022 |
Document, Report, or Work plan Review - other |
ADEC provided comments on the Treatment of Purge Water Utilizing Granular Activated Carbon (GAC) at Chevron Environmental Management Company Sites which includes standard operating procedures and breakthrough estimates proposed for use at this site. |
Rebekah Reams |
12/23/2022 |
Offsite Soil or Groundwater Disposal Approved |
DEC approved transport of one 55-gallon drum of purge water for offsite disposal |
Rebekah Reams |
12/23/2022 |
Document, Report, or Work plan Review - other |
DEC provided comments on the Conceptual Site Model Summary Report which summarizes the site history, evaluates potential exposure pathways, and recommends next steps for the site. |
Rebekah Reams |
3/3/2023 |
Long Term Monitoring Workplan or Report Review |
ADEC approved the Groundwater Sampling Reduction Request Work Plan Addendum for this site. Future groundwater monitoring under this approved addendum will include quarterly monitoring at wells MW-2 through MW-6, MW-8, and MW-9. Samples will be analyzed for DRO, BTEX, EDB, EDC, PAHs, and lead. |
Rebekah Reams |
5/29/2024 |
Long Term Monitoring Workplan or Report Review |
2023 First Quarter groundwater monitoring event was conducted on March 23, 2023. Monitoring wells MW-2, MW-3, MW-4, MW-5, and MW-6 were sampled for DRO, BTEX, EDB, EDC, PAHs, and lead. All results were below cleanup levels. Monitoring wells MW-8 and MW-9 contained insufficient water to sample. Groundwater flow direction was to the northwest. Depth to groundwater was 16.22 to 33.75 feet below ground surface. |
Rebekah Reams |
5/31/2024 |
Long Term Monitoring Workplan or Report Review |
2023 Third Quarter groundwater monitoring event was conducted on August 9, 2023. Monitoring wells MW-2, MW-3, MW-4, and MW-5 were sampled for DRO, BTEX, EDB, EDC, PAHs, and lead. Monitoring wells MW-8 and MW-9 contained insufficient water to sample. MW-6 was not gauged or sampled as the vault was flooded. Groundwater flow direction was to the north-northwest. Depth to groundwater was 15.83 to 16.12 feet below ground surface (bgs) in the perched wells and 30.09 to 32.84 ft bgs in the deeper wells. |
Rebekah Reams |
7/18/2024 |
Document, Report, or Work plan Review - other |
ADEC reviewed the Revised Conceptual Site Model Report which summarizes the site history, evaluates potential exposure pathways, recommends next steps for the site, and addresses ADEC comments. |
Rebekah Reams |
7/24/2024 |
Long Term Monitoring Workplan or Report Review |
2024 Second Quarter groundwater monitoring event was conducted on May 1, 2024. Monitoring wells MW-2, MW-3, MW-4, MW-5, and MW-6 were sampled for DRO, BTEX, EDB, EDC, PAHs, and lead. Monitoring wells MW-8 and MW-9 contained insufficient groundwater volume to sample. Groundwater flow direction was to the north-northwest. Depth to groundwater was 15.40 to 15.98 feet below ground surface (bgs) in the perched wells and 29.06 to 30.84 ft bgs in the deeper wells. |
Rebekah Reams |
7/31/2024 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 77980 1995 UST release. |
Rebekah Reams |
9/25/2024 |
Meeting or Teleconference Held |
ADEC staff met with Chevron and their consultant for an annual portfolio meeting to discuss site status, upcoming document submittals, pending reviews, and general updates for Chevron's contaminated sites throughout the state. |
Rebekah Reams |
10/21/2024 |
Document, Report, or Work plan Review - other |
ADEC provided correspondence in response to the Closure Request report which summarizes the site history, discusses potential exposure pathways and receptors, presents cumulative risk calculations, and requests approval to close the site with institutional controls.
ADEC concurred with the determination that this site is ready for closure and recommended closure without institutional controls based on the determination that (1) Method 2 Table B1 human health and Table B2 ingestion and inhalation exposure pathway cleanup levels have been achieved to a depth of 15 feet, and CSP has determined the migration to groundwater exposure pathway to be incomplete because contaminants in soil have achieved steady-state equilibrium, will not migrate to groundwater, and do not pose an unacceptable risk for migration to groundwater. (2) Remaining contaminant concentrations in groundwater meet Table C cleanup levels. (3) Cumulative risk standards have been met for an unrestricted residential land use scenario based on the most current, representative data available for the site. |
Rebekah Reams |
10/28/2024 |
Offsite Soil or Groundwater Disposal Approved |
ADEC approved transport of 110 gallons of purge water generated during routine groundwater monitoring at this site |
Rebekah Reams |