Action Date |
Action |
Description |
DEC Staff |
5/16/1989 |
Leaking Underground Storage Tank Release Confirmed - Petroleum |
LUST Site created in CSP for source area ID 76525 Arctic grade diesel contaminated soils were replaced in ground and groundwater weren't assessed during leaking underground storage tank removal of a 1,030 gallon tank. Full extent of contamination & human health impact unknown. |
Bill Petrik |
5/16/1989 |
Site Added to Database |
|
Former Staff |
5/17/1989 |
Leaking Underground Storage Tank Cleanup Initiated - Petroleum |
LUST Corrective Action Underway. |
Former Staff |
5/31/1989 |
Document, Report, or Work plan Review - other |
Shannon & Wilson "Underground Storage Tank Removal Monitoring" report dated 5/31/89 states that groundwater was encountered when tank was removed and had a heavy sheen of petroleum product on it. Soils had 1900-1060 mg/kg petroleum hydrocarbons and ethylbenzene, 0.983ppm-14.2ppm, along with lesser concentrations of aromatic hydrocarbons. |
Former Staff |
11/3/1989 |
Leaking Underground Storage Tank Corrective Action Underway |
Ron Klein's review of Shannon & Wilson report showed that backfilling of the three excavations was performed despite the fact that the few samples of soil taken indicated high levels of total petroleum hydrocarbon contamination. DEC requests that plans for assessment & remediation be submitted within 30 days of receipt of 11-3-89 letter. |
Bill Petrik |
11/7/1989 |
Update or Other Action |
Reviewed Shannon & Wilson "Disposal of Waste Soils from Air Van Lines - Group I, at 2216 Post Road, Anchorage, Alaska" report dated 11/7/89 which proposes disposal of waste soils from stockpile of an excavation of a 1,000 gallon diesel tank. No indications of soils around tank being contaminated with hazardous materials. Request that soils be burned in Anchorage Sand & Gravel's rotary kiln-approved by J. Roberts DEC 11/7/89. |
Jennifer Roberts |
4/12/1990 |
Update or Other Action |
Received Anchorage Sand & Gravel letter dated 4/9/90 stating that 257.42 tons of fuel stained soil from 2216 Post Road along with 209 & 135 Post Road were processed as 1 batch into black base material. |
Bill Petrik |
4/13/1990 |
Update or Other Action |
Formerly Air Van Lines Group 1 Partnership until 4/6/90 changed to The Sumiko Group. Correspondence received 4/13/90 from Jack Thompson Managing partner Sumiko Group, Covan International, 8am-5pm. Or 800 239 1980 ext. 2250, FAX 205 983-4717. RP provided new address via telephone. Current address is 102 Montrose Ct.; Apt. 2; Dothan, AL 36305. |
David Allen |
12/13/1990 |
Update or Other Action |
File review completed by Cindy Thomas. The department approves of the proposed additional site assessment as presented in the April 1990 Work Plan for Contamination Assessment. Two discrete samples need to be analyzed for EPH. Please provide a work schedule within ten days. |
Bill Petrik |
2/28/1991 |
Release Investigation |
Shannon & Wilson site assessment report received 4/15. Estimate of vertical extent of plume based upon the photoionization detector readings & analytical results in borings B-3 thru B-5 is estimated from 4' below ground surface to the water table at 7.5'. Thickness of diesel impacted soil zones used to estimate soil volume is 2.5' thick. |
Cindy Thomas |
4/30/1991 |
Underground Storage Tank Site Characterization or Assessment |
Reviewed a Phase 1 Site Assessment report. |
Cindy Thomas |
9/19/1991 |
Underground Storage Tank Site Characterization or Assessment |
Site assessment reviewed this date looks OK. |
Robert Weimer |
3/13/1992 |
Update or Other Action |
Changed Real Name from AM Trucking International to the current Air Van North America. Two sites were called AM Trucking International the other being Reckey # 1989210013603. |
Former Staff |
3/17/1992 |
Update or Other Action |
Real Name changed to reflect current company name to enable distinction between it and two other moving companies with similar names and reckey numbers. |
Former Staff |
5/13/1992 |
Update or Other Action |
The department received the Shannon & Wilson "April 1992 Groundwater Monitoring Results at 2216 Post Road" report dated 5/11/92. |
Bill Petrik |
6/6/1992 |
Document, Report, or Work plan Review - other |
Robert Weimer reviewed Shannon & Wilson's April 1992 "Groundwater Monitoring Report" and the files for this site. The department concurs that the analysis of the groundwater for BTEX be discontinued. Please analyze future groundwater samples for PAHs and DRO. Soil contamination has been identified in excess of cleanup levels. Please provide a corrective action plan to address the soil and groundwater contamination at your site. A possible drinking water well has been identified about 100-200 feet downgradient from the former UST site. Please conduct a well search within a quarter mile of the site to verify which wells may still be in use. |
Bill Petrik |
9/9/1992 |
Document, Report, or Work plan Review - other |
Robert Weimer reviewed the Shannon & Wilson, 8/21/92 report, "Water Well Search Results for 2216 Post Road". The report indicates two nearby wells down gradient of the former UST. The department requests that these two wells be sampled for potential impacts from your site along with the next monitoring well sampling event. Please sample the two water wells for BTEX, PNA, and TPH and submit the results with the next quarterly groundwater monitoring report. |
Bill Petrik |
10/20/1992 |
Update or Other Action |
The department received the Shannon & Wilson report, "September 1992 Groundwater Monitoring Results for 2216 Post Road". |
Bill Petrik |
5/10/1993 |
Update or Other Action |
Robert Weimer received the Shannon & Wilson report, "Results of the April 1993 Groundwater Monitoring at 2216 Post Road" dated 5/7/93. |
Bill Petrik |
7/7/1993 |
Leaking Underground Storage Tank Corrective Action Underway |
Reviewed and approved the Shannon & Wilson work plan, "Contaminated Soil Removal from the Former Diesel UST at 2216 Post Road, Anchorage, Alaska", dated 6/23/93, received by the department 6/28/93. Plan to excavate contaminated soils, thermally treat at ASR or CleanSoils, and take confirmation samples from the excavation. |
Robert Weimer |
9/30/1993 |
Release Investigation |
SA2R; Reviewed a phase 2 site assessment report. |
Former Staff |
10/22/1993 |
Update or Other Action |
Received a letter dated 10/16/93 from Alaska Soil Recycling indicating the 7/24/93 receipt of 487.96 tons of petroleum impacted soil from this site. On 8/31/93 thermal remediation was completed and post treatment analysis submitted. Treated soils met regulatory cleanup levels. |
Robert Weimer |
1/25/1994 |
Leaking Underground Storage Tank Corrective Action Underway |
The department reviewed Shannon & Wilson's "September 1993 Contaminated Soil Cleanup at 2216 Post Road, Anchorage, Alaska". 325 cubic yards of contaminated soils excavated from smear zone at groundwater in July of 1993. High levels of diesel contamination remain (up to 8400 ppm DRO). The department requested a corrective action plan to address the remaining contamination. |
Robert Weimer |
5/13/1994 |
Update or Other Action |
Received the Shannon & Wilson "Corrective Action Plan for 2216 Post Road, Anchorage, Alaska" dated 5/13/94. |
Robert Weimer |
6/12/1996 |
Leaking Underground Storage Tank Corrective Action Underway |
Reviewed the Shannon & Wilson's 1/12/96 report and proposed actions. Approved a Soil Respiration Test and Request for Corrective Action Plan, Air Van Lines, 2216 Post Road, Anchorage". The department requests a corrective action plan to address the remaining contamination at the site by 8/15/96. |
Robert Weimer |
8/15/1996 |
Update or Other Action |
Received the Shannon & Wilson "Corrective Action Plan for the Diesel Impacted Smear Zone at 2216 Post Road, Anchorage, Alaska; File #: L55.42", dated 8/14/96. |
Robert Weimer |
9/30/1996 |
Document, Report, or Work plan Review - other |
Reviewed the Shannon & Wilson "Corrective Action Plan for the Diesel Impacted Smear Zone at 2216 Post Road, Anchorage, Alaska; File #: L55.42", dated 8/14/96. |
Robert Weimer |
9/16/1997 |
Leaking Underground Storage Tank Corrective Action Underway |
Reviewed the Shannon & Wilson 12/11/96 Corrective Action Plan for this site. Conditional Approval of Corrective Action Plan letter sent. Requested scope be expanded to include all areas where contamination is identified. Per R. Weimer. |
Robert Weimer |
11/20/1997 |
Update or Other Action |
ADEC sends Notification of Intent to Cost Recovery Letter to Current Owner: SUMIKO Group. |
Former Staff |
8/27/1999 |
Long Term Monitoring Established |
Submitted Remediation System & Monitoring Status Report. |
Mike Mooney |
2/22/2001 |
Update or Other Action |
Sent letter to RP requesting monitoring reports due since 8/27/99. CC to Shannon & Wilson. Letter was undeliverable and returned to DEC on 5/6/01. |
Mike Mooney |
3/30/2001 |
Update or Other Action |
Second letter requesting information this date. This letter was undeliverable and returned to DEC on 4/12/01. Consultant is looking for correct address. |
Mike Mooney |
5/11/2001 |
Document, Report, or Work plan Review - other |
5/4/01 Received report from S&W summarizing remedial work. Approved plan to continue monitoring of Natural Attenuation of DRO on 5/11/01. |
Mike Mooney |
12/21/2001 |
Update or Other Action |
Sundet is the new project manager. |
Lynne Bush |
2/4/2003 |
Update or Other Action |
Project manager changed from Sundet to Egbejimba. |
Beatrice Egbejimba |
2/4/2003 |
Document, Report, or Work plan Review - other |
ADEC reviewed groundwater monitoring report received August 22, 2002. A phone call was made to the consultant. |
Beatrice Egbejimba |
2/5/2003 |
Update or Other Action |
ADEC called RP to verify address because previous letters sent by ADEC and reports sent by consultant had been returned. During telephone conversation RP provided current address as 102 Montrose Ct. Apt 2, Dothan, AL 36305. ADEC passed on information to consultant. |
Beatrice Egbejimba |
2/6/2003 |
Document, Report, or Work plan Review - other |
ADEC reviewed and approved groundwater monitoring report. |
Beatrice Egbejimba |
2/10/2003 |
Update or Other Action |
ADEC reviewed file, made phone calls to consultant and sent letter approving August 2002 Groundwater Monitoring Report. |
Beatrice Egbejimba |
9/2/2003 |
Document, Report, or Work plan Review - other |
ADEC reviewed and sent letter regarding groundwater monitoring report received August 20, 2003. The report contained results of the November 2002 and April 2003 monitoring effort by Shannon and Wilson for the Sumiko group. ADEC approved the letter and requested continued monitoring because the April 2003 monitoring event reported 2.41mg/kg DRO and 6.41mg/kg DRO for B7MW and B22MW respectively. The November 2002 monitoring event did not indicate elevated levels of any of the contaminants of concern. |
Beatrice Egbejimba |
8/12/2004 |
Institutional Control Record Established |
Elevated concentrations of DRO remaining in soil of 8400 mg/kg and 26.5 mg/L in groundwater. Cleanup levels for DRO is established at 250 mg/kg for soil and 1.5 mg/L for water. Cleanup actions to date have effectively reduced the risk to human health and the environment. Groundwater monitoring plan is in effect until DEC determines there is no longer a risk to groundwater quality. Transport of soils or groundwater from this site requires prior ADEC approval. Any future owners or operators of the property should be aware of environmental and safety requirements. |
Jim Frechione |
8/12/2004 |
Conditional Closure Approved |
Major sources of contamination removed. The soil contamination remaining is considered minimal and its location in the smear zone will not require further remedial action based on groundwater monitor results. Continued groundwater monitoring required by ADEC. Transport of soils or groundwater from this site requires prior ADEC approval. |
Jim Frechione |
9/27/2004 |
Update or Other Action |
Added Bond, Stephens & Johnson as RP based on a 9/14/04 letter from John W. Abbott who formerly represented the Sumiko Group. This letter was received by DEC on 9/22/04. |
David Allen |
4/26/2005 |
Underground Storage Tank Site Characterization or Assessment |
Letter sent by Jim Frechione to approve the workplan submitted for DEC review by the RP consultant Shannon & Wilson, dated April 18, 2005. The Well Installation and Groundwater Sampling Workplan addresses the conditions of the No Further Remedial Action Planned (NFRAP) decision outlined in the August 12, 2004 Record of Decision letter from DEC. |
Bill Petrik |
10/4/2005 |
Update or Other Action |
Project Manager changed from Eric Henry to Bill Petrik. |
Sarah Cunningham |
1/19/2006 |
Update or Other Action |
Used TopoZone Pro, Anchorage Area Atlas, and site map to update erroneous latitude and longitude and street address. Added legal property description. Used web and file map resources. Coordinates in decimal degrees and degrees, minutes, and seconds obtained using TopoZone Pro Large Map at 1:3,333 Scale, NAD 83, on a Hi-Res Urban Aerial photo. Very high degree of confidence in the accuracy of the coordinates. |
Bill Petrik |
8/2/2006 |
Update or Other Action |
Letter from Nuechterlein on this date stating "In conclusion, ADEC issued a Record of Decision for this site in August 2004 approving closure (with conditions). If you wish to consider site closure (without conditions), a soil sample plan should be prepared (and submitted for ADEC approval) that would demonstrate any remaining soil contamination is below the established cleanup levels for this site. In addition, further groundwater monitoring is not required and B1MW may be decommissioned in accordance with ADEC standards." |
Keather McLoone |
8/11/2006 |
Update or Other Action |
Project manager changed from Petrik to Nuechterlein. |
Bill Petrik |
11/4/2008 |
Update or Other Action |
Receipt of Well Decommissioning, 2216 Post Road from Shannon & Wilson. B1MW was decommissioned and B11MW, the only other well remaining on site could not be located so was not decommissioned. Decommissioning of the well was approved according to January 2, 2007 cost recovery memo. |
Keather McLoone |
12/13/2011 |
Institutional Control Compliance Review |
IC review conducted and the staff name was changned to IC Unit. |
Evonne Reese |
12/13/2011 |
Institutional Control Record Removed |
This site meets the 2009 closure policy therefore further ICs are not needed. The defeault requirement of no offsite transport of soil or groundwater will remain. |
Evonne Reese |
12/13/2011 |
Long Term Monitoring Complete |
Administrative action on 5/1/2013. |
Kristin Thompson |