Site Report: Suburban Propane Sales -Rampart Dr.
Site Name: | Suburban Propane Sales -Rampart Dr. |
---|---|
Address: | 3107 Rampart Dr.; , Anchorage, AK 99501 |
File Number: | No file num |
Hazard ID: | 23853 |
Status: | Cleanup Complete |
Staff: | No Longer Assigned, 9074655229 dec.icunit@alaska.gov |
Latitude: | 61.223134 |
Longitude: | -149.821835 |
Horizontal Datum: | WGS84 |
![]() | ![]() |
![]() | ![]() |
We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.
Problems/Comments
Last staff assigned was Bailey.
Action Information
Action Date | Action | Description | DEC Staff |
---|---|---|---|
3/27/1990 | Leaking Underground Storage Tank Release Confirmed - Petroleum | LUST Site created in CSP for source area ID 76551 ADD; Diesel contamination. | Former Staff |
3/27/1990 | Site Added to Database | Former Staff | |
3/30/1990 | Site Visit | FI; J. Halverson & S. Home observed deep sheen on the yard & were informed by B. Halterman that diesel nozzle w/faulty backflow shut off had just been replaced @ 3107 Rampart Dr. | Former Staff |
4/24/1990 | Leaking Underground Storage Tank Corrective Action Underway | RAPR; Martech USA Inc. sends workplan to DEC their project manager is Craig Losby. R. Sundet verbally approved Martech's 5-1-90 more detailed workplan w/5 more conditions(5-21-90 letter to Suburban). | Former Staff |
5/21/1990 | Long Term Monitoring Established | MS; Martech USA sends more detailed workplan for sampling on 5/1/90. Approval granted contingent on 5 conditions included in letter sent by DEC. | Former Staff |
6/19/1990 | Update or Other Action | REM; Martech sends cleanup report to DEC. Contaminated soil from excavation moved to 3300 Mountain View Dr. for temporary storage. Contaminated groundwater collected from excavation was disposed of at Ak Pollution Control. Excavation was filled with clean backfill. | Former Staff |
11/20/1990 | Update or Other Action | REM; Letter to Bill Halterman requesting that interim progress reports be sent until cleanup/disposal of contaminated soil has been completed. Need disposal options sent to DEC within 7 days & may stockpile properly covered soil until 8-10-91 if no public health threat is apparent. | Former Staff |
5/27/1992 | Update or Other Action | UPD; 390 tons of contaminated soil (2100 ppm TPH) was moved to 3300 Mountain View [without prior department approval] and mixed with other contaminated soils from that site in a bioremediation treatment cell. All work is done except for the final treatment/disposal of the 390 tons of contaminated soil. | Former Staff |
3/31/1993 | Leaking Underground Storage Tank Cleanup Initiated - Petroleum | LCAU; | Former Staff |
5/20/1993 | Leaking Underground Storage Tank Corrective Action Underway | LCAR; Conditionally approved bioremediated soils to be spread on-site. | Former Staff |
11/1/1993 | Long Term Monitoring Complete | Former Staff | |
11/1/1993 | Site Closure Approved | CLOS; Soils have been bioremediated and spread at 3300 Mountainview. No further action. | Former Staff |
Contaminant Information
Name | Level Description | Media | Comments |
---|---|---|---|
For more information about this site, contact DEC at (907) 465-5390. |
Control Type
Type | Details |
---|---|
No ICs Required |
Requirements
Description | Details |
---|---|
Advance approval required to transport soil or groundwater off-site. |
There are no documents for this site report.