Skip to content Skip to content

Site Report: Texaco - #18 (former)

Site Name: Texaco - #18 (former)
Address: 4409 Lake Otis Parkway, Anchorage, AK 99502
File Number: 2100.26.110
Hazard ID: 24012
Status: Cleanup Complete
Staff: No Longer Assigned, 9074655229 dec.icunit@alaska.gov
Latitude: 61.181159
Longitude: -149.837625
Horizontal Datum:WGS84

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

During a facility upgrade and removal of a used oil tank in 1996, 45 cubic yards of petroleum contaminated soil was excavated and transported off-site for thermal treated. Monitoring wells were installed in 1997 and 1999 to evaluate the nature and extent of contamination from the release. In 2005 the remaining three gasoline tanks and one diesel tank and their associated piping were removed. During the 2005 removal, 50 cubic yards of petroleum contaminated soil was excavated and transported off-site for thermal treated. Later in 2005 the site monitoring well were decommissioned in accordance with an approved plan. In 2013, five soil borings and temporary monitoring wells were sampled. All samples (including groundwater samples for MTBE) met default cleanup levels. Groundwater samples collected from the wells contained up to 2.77 mg/l DRO, 21.9 mg/l GRO, 1,160 ug/l benzene, 20.4 ug/l 1-2 Dichloroethane, and 95.8 ug/l MTBE. Previous soil samples on property had contained up to 7,880 mg/kg DRO, 34,600 mg/kg RRO, 253 mg/kg GRO, and 0.22 mg/kg benzene. Groundwater samples collected in 2005 and 2013 did not contain contaminants above cleanup levels. Water samples collected from the nearby drinking water well did not contain detectable concentrations of petroleum contaminants. Soil samples collected in 2005 and 2013 from soil borings on the property did not contain contaminants above cleanup levels. Five borings was sampled on the property on April 22 and April 23, 2013. Groundwater amples were collected from temporary monitoring wells after they were developed and purged. Soil and groundwater samples were collected at each location. All samples meet default cleanup levels. Based on available sample data all soil and groundwater on the property meets default cleanup levels. On May 3, 2010 through May 7, 2010 contamination was found in the road right of way during the installation of new storm sewer pipe to the west of the 4409 Lake Otis property. The contamination extended in the new right of way from west of the former dispenser island to an old log crib that was connected to the former service station to the east. Between October 15, 2012 and October 23, 2012 nine soil borings were sampled in the Lake Otis Parkway right-of-way to the west of the 4409 Lake Otis property. Up to 5,900 mg/kg GRO, 2,800 mg/kg DRO, 2,700 mg/kg RRO, 1.1 mg/kg benzene, 46 mg/kg toluene, 61 mg/kg ethybenzene, 500 mg/kg xylenes, 1.6 mg/kg 1,1,2-TCA, 1.5 mg/kg carbon tetrachloride, 0.61 bromodichloromethane, and 0.23 1,2-DCA. PCE and PCBs were non detect. The metals appeared to be at naturally occuring concentrations. Contamination was found in the borings between 5 feet and 34 feet below ground surface and appears to extent to groundwater at several locations. Historically groundwater has been encountered at 21 to 27 feet below ground surface with a flow direction to the northeast. This right-of-way contamination is managed under a separate contaminated site (file number 2100.38.542).

Action Information

Action Date Action Description DEC Staff
8/25/1996 Site Added to Database Former Staff
8/25/1996 Leaking Underground Storage Tank Release Confirmed - Petroleum LUST Site created in CSP for source area ID 77975 Contamination found during facility upgrade. Robert Weimer
8/25/1996 Underground Storage Tank Site Characterization or Assessment Contamination found during facility upgrade. Robert Weimer
8/30/1996 Leaking Underground Storage Tank Corrective Action Underway ADEC approved 45 cubic yards of contaminated soil to be thermally treated at ASR. Robert Weimer
11/20/1997 Update or Other Action ADEC sends Notification of Intent to Cost Recover Letter to Current Owner: TEXACO REFINING & MARKETING INC. Former Staff
3/25/1998 Leaking Underground Storage Tank Cleanup Initiated - Petroleum Former Staff
6/1/1999 Release Investigation An additional monitoring well was installed to help define the extent of the contamination at the site. Robert Weimer
7/26/2000 Update or Other Action ADEC again requests submittal of a corrective action plan for the remaining contaminated soil and groundwater at the site. Former Staff
9/15/2003 Update or Other Action Approved reduction in groundwater monitoring. Robert Weimer
6/8/2004 Document, Report, or Work plan Review - other Reviewed quarterly groundwater monitoring report. Up to <1.0 ug/l benzene. Contaminant levels appear to be declining. Robert Weimer
10/21/2004 Document, Report, or Work plan Review - other Reviewed 6/7/04 quarterly groundwater monitoring results. Up to 770 ug/l benzene. Contaminant levels have increased significantly in southern most monitoring well (MW-5). This monitoring well was resampled on 8/4/04 and found to have 683 ug/l benzene. Robert Weimer
11/19/2004 Document, Report, or Work plan Review - other Reviewed 9/1/04 quarterly groundwater monitoring results. Up to 270 ug/l benzene. Contaminant levels have increased significantly in northern most monitoring well (MW-4). Robert Weimer
1/25/2005 Document, Report, or Work plan Review - other Reviewed 12/1/04 quarterly groundwater monitoring results. Up to 2.6 ug/l benzene. Contaminant levels have decreased in the southern most monitoring well (MW-5). The previously most contaminated monitoring well (MW-4) was not sampled this quarter but is to be sampled next quarter. Groundwater flows to the north. Robert Weimer
4/26/2005 Document, Report, or Work plan Review - other Reviewed UST Closure report for the January 2005 removal of three gasoline and one diesel UST systems. Closure sampling identified up to .2 mg/kg benzene remaining at the base of the former tank excavation at 14 feet below ground surface. The excavated soil was used as backfill, 50 cubic yards of the soil (.0277 mg/kg) was over the benzene cleanup levels and was placed in a liner in the southeast corner. Robert Weimer
5/2/2005 Update or Other Action ADEC letter requesting workplan for release investigation and corrective action for the remaining contamination at the site. Work needs to be done soon because of the pending road work in the area. Robert Weimer
5/25/2005 Document, Report, or Work plan Review - other Reviewed 3/12/05 quarterly groundwater monitoring results. Up to 2.1 ug/l benzene. Contaminant levels have decreased in the southern most monitoring well (MW-5). The previously most contaminated monitoring well (MW-4) was destroyed during the January 2005 tank removal. Groundwater flows to the northeast. Robert Weimer
9/7/2005 Update or Other Action Conditionally approved workplan to decommission monitoring wells, excavate and treat contaminated soil, take confirmation samples from the excavation and from soil borings. Robert Weimer
9/20/2005 Update or Other Action Reviewed, discussed with consultant and approved thermal treatment request for soil to be excavated in the next few days. Robert Weimer
9/21/2005 Document, Report, or Work plan Review - other Reviewed 6/8/05 quarterly groundwater monitoring results. Up to 3.1 ug/l benzene in the groundwater. Contaminant levels have decreased in the southern most monitoring well (MW-5). The previously most contaminated monitoring well (MW-4) was destroyed during the January 2005 tank removal. Groundwater flows to the northeast. Robert Weimer
10/21/2005 Update or Other Action All of the remaining monitoring wells were decommissioned . A temporary monitoring well was placed in the area of MW-4, sampled, then abandoned. No monitoring wells remain at the site. Robert Weimer
1/20/2006 Document, Report, or Work plan Review - other Reviewed 9/1/05 quarterly groundwater monitoring results. Up to 1.59 ug/l benzene and 95.8 ug/l MTBE in the groundwater. Contaminant levels appear to be decreasing. A temporary replacement well (MW-4A) located at the previously most contaminated area had 1.59 ug/l benzene (5 ug/l cleanup level) and 95.8 ug/l MTBE (470 ug/l proposed cleanup level). This well was sampled once then abandoned. All of the other wells have also been abandoned. Groundwater flows to the northeast. Depth to groundwater ranges from 22 to 25 feet below ground surface. Robert Weimer
4/3/2006 Update or Other Action Talked with RP's consultant. They plan to submit the results of the Fall 2005 soil excavation work by the end of April. He indicated that all of the excavation soil samples meet default cleanup levels, and they would be recommending the site for closure. All groundwater samples also meet cleanup levels. Robert Weimer
4/5/2006 Update or Other Action Meeting regarding the proposed road work at Lake Otis and Tudor in 2008+. Robert Weimer
4/16/2008 Exposure Tracking Model Ranking Site ranked on the new Exposure Tracking Model (ETM). The ETM is a new site ranking system that looks at, based on available data, the potential exposure pathways for the contamination remaining at the site. Robert Weimer
5/1/2008 Update or Other Action ADEC approves Lake Otis and Tudor intersection improvements corrective action plan. The plan calls for storing and assessing any soils excavated near the site as part of the intersection improvements. Soils meeting default cleanup levels can be reused, soil exceeding default cleanup levels will require treatment. Robert Weimer
3/18/2009 Update or Other Action Discuss site status with RP's consultant (Delta). We discussed waiting until the intersection work is completed to do the site closure review. Robert Weimer
5/8/2010 Update or Other Action On May 3, 2010 through May 7, 2010 contamination was found in the road right of way during the installation of new storm sewer pipe to the west of the 4409 Lake Otis property. The contamination extended in the new right of way from west of the former dispenser island to an old log crib that was connected to the former service station to the east. Between October 15, 2012 and October 23, 2012 nine soil borings were sampled in the Lake Otis Parkway right-of-way to the west of the 4409 Lake Otis property. Up to 5,900 mg/kg GRO, 2,800 mg/kg DRO, 2,700 mg/kg RRO, 1.1 mg/kg benzene, 46 mg/kg toluene, 61 mg/kg ethybenzene, 500 mg/kg xylenes, 1.6 mg/kg 1,1,2-TCA, 1.5 mg/kg carbon tetrachloride, 0.61 bromodichloromethane, and 0.23 1,2-DCA. PCE and PCBs were non detect. The metals appeared to be at naturally occuring concentrations. Contamination was found in the borings between 5 feet and 34 feet below ground surface and appears to extent to groundwater at several locations. Historically groundwater has been encountered at 21 to 27 feet below ground surface with a flow direction to the northeast. Robert Weimer
10/11/2010 Site Visit Site visit to observe current site conditions. Robert Weimer
12/21/2010 Exposure Tracking Model Ranking A new updated ranking with ETM has been completed for source area 77975 1996 UST contamination. Robert Weimer
6/13/2013 Meeting or Teleconference Held Meeting with prospective purchaser of the property and his consultant. They sampled 5 borings on the property on April 22 and April 23, 2013. Soil and groundwater samples were collected at each location. All samples (including groundwater samples for MTBE) met default cleanup levels. Groundwater samples were collected from temporary monitoring wells after they were developed and purged. They property is being replatted to include the property to the north and east. The remaining contaminated area is off property to the west in the Lake Otis road right-of-way which is owned by the Municipality of Anchorage. Equilon Enerprises LLC dba Shell Oil Products US retains liability for that contamination. Robert Weimer
6/14/2013 Update or Other Action Based on available sample data all soil and groundwater on the property meets default cleanup levels. Site recommended for closure and Corrective Action Complete status. Robert Weimer
6/14/2013 Exposure Tracking Model Ranking A new updated ranking with ETM has been completed for source area 77975 1996 UST contamination. Robert Weimer
6/21/2013 Site Visit Site visit to observe current site conditions. Robert Weimer
6/24/2013 Cleanup Complete Determination Issued Robert Weimer

Contaminant Information

Name Level Description Media Comments
GRO < Method 2 Most Stringent Soil
GRO < Table C Groundwater
1,2-Dichloroethane < Table C Groundwater
Benzene < Table C Groundwater
Benzene < Method 2 Most Stringent Soil
MTBE < Table C Groundwater
DRO < Table C Groundwater
DRO < Method 2 Most Stringent Soil
RRO < Method 2 Most Stringent Soil

Control Type

Type Details
No ICs Required

Requirements

Description Details
Advance approval required to transport soil or groundwater off-site.
Hazard ID Site Name File Number
26073 Lake Otis Parkway Right of Way 2100.38.542

Missing Location Data

Because the GIS location data for this site has not been entered, we cannot direct you to its position on the map. Click "Continue" to proceed to the Contaminated Sites Web Map or "Close" to return to the site report.
Continue     Close