Skip to content Skip to content

Site Report: H & H Contractors, Inc

Site Name: H & H Contractors, Inc
Address: 3050 Phillips Rd, Fairbanks, AK 99701
File Number: 100.26.169
Hazard ID: 24050
Status: Active
Staff: Shawn Tisdell, 9074512752 shawn.tisdell@alaska.gov
Latitude: 64.846200
Longitude: -147.801000
Horizontal Datum:

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

In 1997, a 30,000-gallon diesel fuel UST and associated lines and dispensers was removed and decommissioned along with approximately 300 CY of contaminated soil. Remedial activities conducted by AGRA Earth & Environmental (AGRA) in 1998 removed an additional 650 CY of contaminated soil. AGRA indicated a small amount of petroleum impacted soil remained near a concrete pad of the former fuel dispenser island. ICE Alaska purchased the property in 2011, without apparent knowledge of contamination issues. Former owner & RP agreed to address remaining contamination concerns - mainly petroleum in soil and groundwater near the former dispensers.

Action Information

Action Date Action Description DEC Staff
10/23/1997 Leaking Underground Storage Tank Release Confirmed - Petroleum LUST Site created in CSP for source area ID 77723 Jim Spontak with AGRA contacted officer during UST removal. Greater than 2,000 square feet of surface impacted. Primarily gravel and will be stockpiled onsite. Former Staff
10/23/1997 Site Added to Database Former Staff
12/18/1997 Underground Storage Tank Site Characterization or Assessment AGRA & Swaim complete UST removal and SA. Approximately 350 cubic yards of diesel impacted soil is removed. Levels at base of excavation include up to 32,000 ppm DRPH. Former Staff
8/11/1999 Leaking Underground Storage Tank Cleanup Initiated - Petroleum Excavation of 350 cubic yards of diesel contaminated soil treated with cold-mix asphalt and placed on site. Former Staff
1/28/2004 Update or Other Action Transferred DEC staff lead from John Carnahan Cynthia Pring-Ham
3/12/2007 Exposure Tracking Model Ranking Initial ranking completed. Tamara Cardona-Marek
6/11/2008 Update or Other Action Sent letter requesting current site status. Tamara Cardona-Marek
6/30/2008 Update or Other Action Spoke with representative from Rockwell Engineering . They have been contacted to follow up on DEC's letter of 6/2008. Tamara Cardona-Marek
9/30/2008 Document, Report, or Work plan Review - other Received and reviewed the Rockwell Engineering Groundwater Investigation report for H&H Contractors. DRO (2.84ppm) and benzene (9ppb) are above DEC cleanup levels on the well located in the source area. Two additional temporary wells were installed near the location of the Trailers. All contaminants in these two wells were non-detect. No workplan was submitted for this work. The downgradient well at Constructions Parts was not sampled. DEC requested a CSM and sampling of the Construction Parts well. Tamara Cardona-Marek
10/27/2008 Exposure Tracking Model Ranking Initial ranking with ETM completed for source area id: 77723 name: 30,000 Gallon UST Tamara Cardona-Marek
10/29/2008 Document, Report, or Work plan Review - other Spoke with consultant at Rockwell Engineering (Dave Miller). They will develop and submit a CSM and contact DEC to discuss additional actions needed at the site. Tamara Cardona-Marek
11/6/2009 Update or Other Action Transferred site management from Tamara Cardona-Marek to Jim Fish. Janice Wiegers
7/21/2011 Update or Other Action Contacted consultant for FNSB - doing Phase 1 as result of property transaction (Ice Alaska) Jim Fish
8/18/2011 Potentially Responsible Party/State Interest Letter PRP letter sent to Ice Alaska, following purchase of lots TL-812, TL-831, and TL-849. Jim Fish
9/6/2011 Meeting or Teleconference Held Met with representatives of Ice Alaska - the new site owners - to discuss contamination issues and requirements for site closure. Jim Fish
9/8/2011 Update or Other Action Letter sent to RP concerning requirements to move towards site closure. These include: •Installation of permanent monitoring wells in the vicinity of the former UST location (source area), south of the former UST, and to the northwest of the former UST; •Periodically sampling this series of monitoring wells to understanding groundwater movement and contaminant distribution; •Periodically sampling the drinking water wells on lots TL-849 and TL-831 to confirm the absence of contaminants; •Determining the fate of suspected injection wells used during hot-mix asphalt plant operations. Jim Fish
10/10/2011 Meeting or Teleconference Held Spoke with Rockell engineering concerning monitoring well placement, UICs, drinking water wells and contaminant sampling. Work Plan for Autumn 2011 pending. Jim Fish
10/31/2011 Update or Other Action Recieved and approved groundwater and drinking water well sampling plan Jim Fish
1/19/2012 Document, Report, or Work plan Review - other Groundwater monitoring report received from Ice Alaska. Jim Fish
2/3/2012 Meeting or Teleconference Held Meeting held with ICE Alaska & consultant representing H&H Contractors, Inc. Groundwater sampling results, Additional site characterization identified for surface soil, Record of Decision, and Environmental Mananagement Plan discussed. Location of MW-1, and original UST location questioned. Jim Fish
2/13/2012 Meeting or Teleconference Held Met with consultant to discuss ROD and acutal location of original UST and subsequent monitoring wells. Jim Fish
10/16/2012 Meeting or Teleconference Held Met Nortech - taking over as lead consultant (from Rockwell); will develop workplan and try to identify exact location of former dispenser island. Jim Fish
10/26/2012 Update or Other Action Work plan received from NORTECH Jim Fish
10/31/2012 Site Characterization Workplan Approved Work plan approved. Jim Fish
7/25/2013 Update or Other Action Received assessment report and work plan for Ice Alaska property/former excavation & dispenser island. Jim Fish
7/29/2013 Cleanup Plan Approved Cleanup Plan (proposed excavation and land farming) approved. Groundwater monitoring will also be conducted after new monitoring well installations. Jim Fish
7/16/2014 Update or Other Action Consultant indicated report of excavation, moniotring well installations, and land farm construction pending. Jim Fish
9/18/2014 Document, Report, or Work plan Review - other Site characterization report received today. Jim Fish
6/17/2015 Update or Other Action Received a September 2014 Bio-Cell Field Screening Results Report and an October 2014 Groundwater Monitoring Report from consultant (Nortech) Jim Fish
7/6/2015 Update or Other Action Received a soil boring report for 2014 activities to characterize remaining soil contamination and groundwater elevations. Jim Fish
1/8/2021 Meeting or Teleconference Held DEC staff teleconference with consultant, discussed current site conditions and additional site activities. Landfarming management was the primary focus of the discussion, as the landfarm had not been tilled for some time and it no longer had a functioning cover. Frequent tilling over the entire depth was recommended. PID headspace sampling was conducted last year. Only a small area of soil near the bottom of the 18" layer had elevated headspace readings (500 to 700 ppm). The consultant will work with the RP to plan multiple tilling events this next summer and contact the DEC with the proposed plan. The consultant also reported that no additional groundwater monitoring had been conducted since the last report in 2014. Shawn Tisdell
9/15/2022 Site Characterization Workplan Approved Work plan for soil sampling the landfarm originally received 8/4/2022 was approved following revision updates. This plan presents a multi-incremental sampling strategy to provide data to determine if prior fertilizing and tiling activities have sufficiently remediated the soil and allow for closure of the landfarm. Shawn Tisdell
3/20/2023 Site Characterization Report Approved The revised Former Underground Storage Tank landspread Stockpile Sample Results Report submitted by Nortech on March 7, 2023 has been reviewed and approved. This report indicated incremental sampling of the landfarm and discrete sampling of the surface soil beneath the landfarm liner was conducted during September and November of 2022. Sample results indicate that the landfarm soil and the soil immediately beneath the landfarm were all below the DEC cleanup criteria for unrestricted use. The DEC requested a work plan be prepared that identifies a strategy to characterize data gaps remaining at the site. Shawn Tisdell
10/4/2023 Site Characterization Workplan Approved Work plan objectives include current evaluation of the groundwater contamination and contaminant trends, complete a relative elevation survey and determine the groundwater gradient, and collect water quality and geochemistry parameters, which include dissolved oxygen, nitrate, ferrous iron, sulfate, methane, oxidation-reduction potential, pH, temperature and conductivity. Seven wells will be sampled in October 2023 and results will be provided in a report within 6 weeks of the completion of the fieldwork. Shawn Tisdell

Contaminant Information

Name Level Description Media Comments

Control Type

Type Details

Requirements

Description Details

No associated sites were found.

Missing Location Data

Because the GIS location data for this site has not been entered, we cannot direct you to its position on the map. Click "Continue" to proceed to the Contaminated Sites Web Map or "Close" to return to the site report.
Continue     Close