Action Date |
Action |
Description |
DEC Staff |
7/6/1990 |
Underground Storage Tank Site Characterization or Assessment |
ENSR Consultants submit a workplan to ADEC for UST removal and site characterization. Approved by ADEC with stipulations. Station being upgraded. |
Former Staff |
7/9/1990 |
Leaking Underground Storage Tank Corrective Action Underway |
Gasoline and diesel contaminated soils approved by ADEC for thermal treatment at AS&G. AS&G processed 1,077 tons on 7/28/90. |
Former Staff |
7/10/1990 |
Leaking Underground Storage Tank Release Confirmed - Petroleum |
LUST Site created in CSP for source area ID 77716 Used oil, chlorinated solvents, gasoline and diesel contaminants. |
Former Staff |
7/10/1990 |
Site Added to Database |
|
Former Staff |
7/11/1990 |
Leaking Underground Storage Tank Cleanup Initiated - Petroleum |
LCAU Date changed DB conversion |
Former Staff |
9/11/1990 |
Update or Other Action |
ENSR sends lab data that shows 100 ppb tetrachloroethylene in soils. Propose to process used oil contaminated soil through AK Pollution Control. APC will thermally treat soils to a level so they can be disposed of at the Anchorage Regional Landfill. |
Former Staff |
9/21/1990 |
Update or Other Action |
Permission to transport used oil contaminated soils to AK Pollution Control in Palmer for thermal treatment granted after lab results were received. |
Former Staff |
10/2/1990 |
Document, Report, or Work plan Review - other |
ENSR consulting environmental assessment report states that contaminated soils above 100 mg/kg were removed during tank/piping excavation. Groundwater is about 10 feet below the surface and flows towards the northwest and southwest. Benzene ranging from 2.8 ug/l to 16.0 ug/l was found in the four on-site monitoring wells in August 1990. |
Former Staff |
3/22/1991 |
Update or Other Action |
ENSR submits a plan which proposes a vapor extraction system for the former pump island & gasoline tank areas. For the used oil tank area it's recommended that in situ biological treatment for the contaminated soils in that area. |
Former Staff |
11/20/1997 |
Update or Other Action |
ADEC sends Notification of Intent to Cost Recover Letter to Current Owner: TEXACO REFINING & MARKETING INC. |
Former Staff |
7/26/2000 |
Update or Other Action |
ADEC letter requesting corrective action plan for the remaining soil and groundwater contamination, and a work plan for additional monitoring well installation to help define the extent of contamination. |
Robert Weimer |
6/7/2004 |
Document, Report, or Work plan Review - other |
Reviewed quarterly groundwater monitoring report. Up to 62 ug/l benzene and 6,000 ug/l GRO in the groundwater. Contaminant concentrations are increasing in some monitoring wells and the extent of the contamination has not been defined. |
Robert Weimer |
9/29/2004 |
Document, Report, or Work plan Review - other |
Reviewed quarterly groundwater monitoring report. Up to 64 ug/l benzene and 110 ug/l GRO in the groundwater. Contaminant concentrations are increasing in one monitoring well and the extent of the contamination has not been defined. |
Robert Weimer |
11/18/2004 |
Document, Report, or Work plan Review - other |
Reviewed quarterly groundwater monitoring report. Up to 65 ug/l benzene and 110 ug/l GRO in the groundwater. Contaminant concentrations are increasing in one monitoring well and the extent of the contamination has not been defined. |
Robert Weimer |
1/21/2005 |
Document, Report, or Work plan Review - other |
Reviewed the December 1, 2004 groundwater monitoring event report. Up to 52 ug/l benzene and 170 ug/l GRO in the groundwater. Contaminant concentrations are increasing in one monitoring well and the extent of the contamination has not been defined. |
Robert Weimer |
5/13/2005 |
Document, Report, or Work plan Review - other |
Reviewed the March 8, 2005 groundwater monitoring event report. Up to 120 ug/l benzene and 530 ug/l GRO in the groundwater. Contaminant concentrations are increasing and the extent of the contamination to the west and southwest has not been defined. |
Robert Weimer |
9/16/2005 |
Document, Report, or Work plan Review - other |
Reviewed the June 8, 2005 groundwater monitoring event report. Up to 170 ug/l benzene and 1,000 ug/l GRO in the groundwater. Contaminant concentrationsare increasing and the extent of the contamination to the west and southwest has not been defined. Groundwater flow was to the northwest this monitoring event. |
Robert Weimer |
12/8/2005 |
Document, Report, or Work plan Review - other |
Reviewed the 9/24/05 groundwater monitoring event report. Up to 170 ug/l benzene and 1,000 ug/l GRO in the groundwater. Contaminant concentrations are stable and the extent of the contamination to the west and southwest has not been defined. Groundwater flow was to the southwest this monitoring event. Depth to groundwater was 5 to 7 feet below ground surface. |
Robert Weimer |
1/19/2006 |
Update or Other Action |
ADEC issues approval of release investigation workplan for the installation of two additional monitoring wells located just to the west of the Service Station. |
Robert Weimer |
1/24/2006 |
Document, Report, or Work plan Review - other |
Reviewed the 12/03/05 groundwater monitoring event report. Up to 73.3 ug/l benzene and 454 ug/l GRO in the groundwater. Contaminant concentrations appear stable and the extent of the contamination to the west and southwest has not been defined. Groundwater flow was to the southwest this monitoring event. Depth to groundwater was 5 to 7 feet below ground surface. |
Robert Weimer |
5/12/2006 |
Document, Report, or Work plan Review - other |
Reviewed the 3/21/06 groundwater monitoring event report. Up to 73.3 ug/l benzene and 830 ug/l GRO in the groundwater. Contaminant concentrations appear stable and the extent of the contamination to the west and southwest has not been defined. Groundwater flow was to the southwest this monitoring event. Depth to groundwater was 6 to 9 feet below ground surface. |
Robert Weimer |
11/21/2006 |
Document, Report, or Work plan Review - other |
Reviewed the 9/25/06 groundwater monitoring event report. Up to 43.1 ug/l benzene and 168 ug/l GRO in the groundwater. Contaminant concentrations appear stable and the extent of the contamination to the west and southwest has not been defined. Groundwater flow was to the south by southwest this monitoring event. Depth to groundwater was 7 to 8 feet below ground surface. |
Robert Weimer |
3/8/2007 |
Exposure Tracking Model Ranking |
Site ranked on the new Exposure Tracking Model (ETM). The ETM is a new site ranking system that looks at, based on available data, the potential exposure pathways for the contamination remaining at the site. |
Robert Weimer |
4/10/2007 |
Document, Report, or Work plan Review - other |
Reviewed the 12/12/06 groundwater monitoring event report. Up to 17 ug/l benzene and 4,510 ug/l GRO in the groundwater. Contaminant concentrations appear to be increasing and the extent of the contamination to the west and southwest has not been defined. Groundwater flow is generally to the south by southwest. Depth to groundwater was 6.2 to 7.7 feet below ground surface. |
Robert Weimer |
5/4/2007 |
Update or Other Action |
ADEC approves request for no-purge groundwater sampling for this site. |
Robert Weimer |
12/17/2007 |
Document, Report, or Work plan Review - other |
Reviewed the 3/29/07 groundwater monitoring event report. Up to 26 ug/l benzene and 4,510 ug/l GRO (from the 12/12/06 monitoring event) in the groundwater. Contaminant concentrations appear to be increasing and the extent of the contamination to the west and southwest has not been defined. Groundwater flow is generally to the south by southwest. Depth to groundwater was 6.4 to 8.7 feet below ground surface. |
Robert Weimer |
2/4/2008 |
Document, Report, or Work plan Review - other |
Reviewed the 6/21/07 groundwater monitoring event report. Up to 40.1 ug/l benzene and 4,510 ug/l GRO (from 12/12/06 monitoring event) in the groundwater. Contaminant concentrations appear to be increasing and the extent of the contamination to the west and southwest has not been defined. Groundwater flow is generally to the south by southwest. Depth to groundwater was 6.1 to 6.34 feet below ground surface. |
Robert Weimer |
2/5/2008 |
Document, Report, or Work plan Review - other |
Reviewed the 9/26/07 groundwater monitoring event report. Up to 86.9 ug/l benzene and 194 ug/l GRO in the groundwater. Contaminant concentrations appear to be increasing and the extent of the contamination to the west and southwest has not been defined. Groundwater flow was to the west during this monitoring event. Depth to groundwater was 5.78 to 7.99 feet below ground surface. |
Robert Weimer |
4/28/2008 |
Document, Report, or Work plan Review - other |
Reviewed the 12/13/07 groundwater monitoring event report. Up to 45.2 ug/l benzene and 290 ug/l GRO in the groundwater. Contaminant concentrations increased in one of the three monitoring well sampled. The extent of the contamination to the west and southwest has not been defined. Groundwater flow was to the northwest during this monitoring event. Depth to groundwater was 6.51 to 7.85 feet below ground surface. |
Robert Weimer |
4/28/2008 |
Document, Report, or Work plan Review - other |
A property transfer Phase II environmental assessment was conducted on January 25-29, 2008. Five soil borings were drilled and one groundwater sample was collected. The soil borings had 1.8 mg/kg benzene, 60.8 mg/kg GRO, 64.5 mg/kg DRO, 82.5 mg/kg RRO and up to 7.22 mg/kg lead in the areas sampled. The groundwater samples had non detect (<0.5 ug/l) benzene, non detect (<0.8 mg/l) GRO, non detect (<0.667 mg/l) DRO, and non detect (<0.8 mg/l) RRO. Groundwater results are biased low due to headspace in the sample vials and not preserved in the field (high pH). |
Robert Weimer |
11/4/2008 |
Document, Report, or Work plan Review - other |
Reviewed the 3/25/08 groundwater monitoring event report. Up to 10.2 ug/l benzene and 21.4 ug/l MTBE (470 ug/l cleanup level) in the groundwater. Contaminant concentrations increased in one of the three monitoring well sampled. The extent of the contamination to the west and southwest has not been defined. Groundwater flow was to the west during this monitoring event. Depth to groundwater was 6.01 to 8.06 feet below ground surface. |
Robert Weimer |
11/13/2008 |
Document, Report, or Work plan Review - other |
Reviewed the 6/13/08 groundwater monitoring event report. Up to 15 ug/l benzene and 450 ug/l GRO in the groundwater. Contaminant concentrations increased in one of the four monitoring well sampled. The extent of the contamination to the west and southwest has not been defined. Groundwater flow was to the northwest during this monitoring event. Depth to groundwater was 4.74 to 6.75 feet below ground surface. |
Robert Weimer |
1/5/2009 |
Document, Report, or Work plan Review - other |
Reviewed the 9/16/08 groundwater monitoring event report. Up to 25 ug/l benzene and non detect (<100 ug/l) GRO in the groundwater. Contaminant concentrations increased in one of the five monitoring well sampled. The extent of the contamination to the west and southwest has not been defined. Groundwater flow was to the northwest during this monitoring event. Depth to groundwater was 5.15 to 7.40 feet below ground surface. |
Robert Weimer |
4/1/2009 |
Document, Report, or Work plan Review - other |
Reviewed the 12/1/08 groundwater monitoring event report. Up to 26 ug/l benzene and 460 ug/l GRO in the groundwater. Contaminant concentrations increased in two of the two monitoring well sampled. The extent of the contamination to the west and southwest has not been defined. Groundwater flow was to the westerly direction during this monitoring event. Depth to groundwater was 6.68 to 7.58 feet below ground surface. |
Robert Weimer |
4/1/2009 |
Meeting or Teleconference Held |
Discussed with Texaco's consultant that they are working on getting site access for the off property monitoring wells. They hope to get access and install them in the summer of 2009. |
Robert Weimer |
7/27/2009 |
Document, Report, or Work plan Review - other |
Reviewed the 3/23/09 groundwater monitoring event report. Up to 53 ug/l benzene and 460 ug/l GRO in the groundwater. Contaminant concentrations increased in two of the two monitoring well sampled. The extent of the contamination to the west and southwest has not been defined. Groundwater flow was to the westerly direction during this monitoring event. Depth to groundwater was 6.32 to 7.23 feet below ground surface. |
Robert Weimer |
8/21/2009 |
Document, Report, or Work plan Review - other |
Reviewed the 6/12/09 groundwater monitoring event report. Up to 100 ug/l benzene, 350 ug/l GRO, 150 ug/l TBA, and 10 ug/l MTBE in the groundwater. Contaminant concentrations increased in two of the four monitoring wells sampled. The extent of the contamination to the west and southwest has not been defined. Groundwater flow was to the westerly direction during this monitoring event. Depth to groundwater was 6.04 to 8.07 feet below ground surface. |
Robert Weimer |
1/5/2010 |
Document, Report, or Work plan Review - other |
Reviewed the 9/14/09 groundwater monitoring event report. Up to 78 ug/l benzene, non detect (<100 ug/l) GRO, 540 ug/l TBA, and 40 ug/l MTBE in the groundwater. Contaminant concentrations increased in 3 of the 4 monitoring wells sampled. The extent of the contamination to the west and southwest has not been defined. Groundwater flow was to the westerly direction during this monitoring event. Depth to groundwater was 5.79 to 8.06 feet below ground surface. |
Robert Weimer |
3/22/2010 |
Document, Report, or Work plan Review - other |
Reviewed the 12/9/09 groundwater monitoring event report. Up to 61 ug/l benzene and non detect (<100 ug/l) GRO in the groundwater. Contaminant concentrations decreased in the 4 monitoring wells sampled. The extent of the contamination to the west and southwest has not been defined. Groundwater flow was to the westerly direction during this monitoring event. Depth to groundwater was 5.51 to 7.78 feet below ground surface. |
Robert Weimer |
5/5/2010 |
Document, Report, or Work plan Review - other |
Reviewed the 3/19/10 groundwater monitoring event report. Up to 51 ug/l benzene and 2.3 mg/l GRO in the groundwater. Contaminant concentrations increased in 1 of the 4 monitoring wells sampled. The extent of the contamination to the west and southwest has not been defined. Groundwater flow was to the west by northwest direction during this monitoring event. Depth to groundwater was 6.91 to 8.18 feet below ground surface. Need to continue quarterly groundwater monitoring until extent of groundwater contamination has been defined and stable trends have been demonstrated. |
Robert Weimer |
5/4/2011 |
Document, Report, or Work plan Review - other |
Reviewed the 5/16/10 groundwater monitoring event report. Up to 31 ug/l benzene and non detect (<0.1 mg/l) GRO in the groundwater. Contaminant concentrations increased in 0 of the 4 monitoring wells sampled. The extent of the contamination to the west and southwest has not been defined. Groundwater flow was to the southwest direction during this monitoring event. Depth to groundwater was 4.95 to 7.05 feet below ground surface. |
Robert Weimer |
7/21/2011 |
Document, Report, or Work plan Review - other |
Reviewed the 9/21/10 and 11/2/10 groundwater monitoring events report. Up to 2,000 ug/l benzene and non detect (<0.046 mg/l) GRO in the groundwater. Contaminant concentrations increased in 3 of the 4 monitoring wells sampled. The extent of the contamination to the west and southwest has not been defined. Groundwater flow was to the northwest direction during these monitoring events. Depth to groundwater was 4.64 to 6.82 feet below ground surface. |
Robert Weimer |
12/19/2011 |
Document, Report, or Work plan Review - other |
March 5, 2011 groundwater monitoring event report. Up to 8.67 ug/l benzene and 0.363 mg/l GRO in the groundwater. Contaminant concentrations increased in 1 of the 3 monitoring wells sampled. The previously most contaminated monitoring well (DMW-1) was not sampled this event. The extent of the contamination to the west and southwest has not been defined. Groundwater flow was to the northwest direction during this monitoring event. Depth to groundwater was 7.20 to 8.30 feet below ground surface (bgs). One monitoring well was no assessible because of snow and another monitoring well (DMW-1) was not sampled due to an obstruction at 5.25 feet bgs. |
Robert Weimer |
12/20/2011 |
Document, Report, or Work plan Review - other |
May 24, 2011 groundwater monitoring event report. Up to 136 ug/l benzene and 5.31 mg/l GRO in the groundwater. Contaminant concentrations increased in 2 of the 4 monitoring wells sampled. The extent of the contamination to the west and southwest has not been defined. Groundwater flow was to the south direction during this monitoring event. Depth to groundwater was 5.02 to 6.14 feet below ground surface (bgs). One monitoring well was no assessible because of snow. |
Robert Weimer |
12/21/2011 |
Update or Other Action |
ADEC approves reduction in groundwater monitoring at this site from quarterly to semi-annual and reduce analytical sampling to: DMW-1 and DMW-4C to just BTEX and GRO on a semi-annual basis, and DMW-2 and DMW-5 to just BTEX on a semi-annual basis.
|
Robert Weimer |
7/17/2012 |
Document, Report, or Work plan Review - other |
July 29, 2011 groundwater monitoring event report. Up to 92 ug/l benzene and 43.9 ug/l MTBE in the groundwater. Contaminant concentrations increased in 2 of the 4 monitoring wells sampled. The extent of the contamination to the south and west has not been defined. Groundwater flow was to the west direction during this monitoring event. Depth to groundwater was 5.37 to 7.61 feet below ground surface (bgs). One monitoring well was no assessible. |
Robert Weimer |
7/17/2012 |
Document, Report, or Work plan Review - other |
October 12, 2011 groundwater monitoring event report. Up to 166 ug/l benzene and 2.53 mg/l GRO in the groundwater. Contaminant concentrations increased in 3 of the 4 monitoring wells sampled. The extent of the contamination to the south and west has not been defined. Groundwater flow was to the north west direction during this monitoring event. Depth to groundwater was 5 to 8 feet below ground surface (bgs). One monitoring well was no assessible. |
Robert Weimer |
2/13/2013 |
Document, Report, or Work plan Review - other |
April 25, 2012 groundwater monitoring event report. Up to 23 ug/l benzene and 0.718 mg/l GRO in the groundwater. Contaminant concentrations increased in 3 of the 4 monitoring wells sampled. The extent of the contamination to the south and west has not been defined. Groundwater flow was to the northwest direction during this monitoring event. Depth to groundwater was 4 to 7 feet below ground surface (bgs). One monitoring well was no assessible. |
Robert Weimer |
3/22/2013 |
Update or Other Action |
DEC request that all sites where there has been no purge groundwater sampling conducted during the last year, that for the next sampling event that they do both no purge then purge sampling from each monitoring well, so we evaluate on a site specific basis whether no purge sampling has provided comparable data. The post purge well sampling for VOCs would need to be conducted via hydrasleeve, bladder pump, or in well pump. Non VOC sampling can be collected with a bailer or peristaltic pump (in addition to the VOC methods) if desired. The specific sampling methods will need to be documented in the report and included field notes.
If there is not enough time to do this adjustment for the planned sample event of March 26-April 4, then DEC requests that it be done on the following event. |
Robert Weimer |
4/1/2013 |
Update or Other Action |
Approved request to conduct the first semi-annual monitoring event each year in May instead of seasonal March/April because of snow cover over some of the monitoring wells. |
Robert Weimer |
8/16/2013 |
Document, Report, or Work plan Review - other |
Conditionally approved the proposed 2013 release investigation work under the following conditions:
1. Based on historical groundwater at the site being as shallow as 4 feet below ground surface (bgs), the screen intervals for the monitoring wells need to start at 4 feet bgs.
2. Many of the areas where soil samples are to be collected were excavated previously and filled with clean backfill. In those areas the samples need to be collected from non backfill soils unless there are higher field readings at shallower depths in the boring.
3. The highest field reading depth needs to be sampled in each boring. You may substitute one of the deepest proposed sample depths for that sample.
The plan includes installing two additional long term monitoring wells, one temporary monitoring well, and collecting soil samples from 6 soil borings.
|
Robert Weimer |
10/8/2013 |
Document, Report, or Work plan Review - other |
October 3, 2012 groundwater monitoring event report. Up to 46 ug/l benzene and 0.240 mg/l GRO in the groundwater. Contaminant concentrations increased in 4 of the 4 monitoring wells sampled. The extent of the contamination to the south and west has not been defined. Groundwater flow was to the northwest direction during this monitoring event. Depth to groundwater was 4 to 6 feet below ground surface (bgs). One monitoring well was not assessible (DMW-3). Groundwater samples were collected with Hydrasleeves without purging. Sampling interval information was not provided, results may be biased low if correct interval was not sampled. |
Robert Weimer |
3/7/2014 |
Document, Report, or Work plan Review - other |
June 7, 2013 groundwater monitoring event report. Up to 11.1 ug/l benzene, 0.505 mg/l GRO, non detect (<0.762 mg/l) DRO, non detect (<1.0 mg/l) RRO, and 15.2 ug/l MTBE in the groundwater. Contaminant concentrations increased in 2 of the 4 monitoring wells sampled. The extent of the contamination to the south and west has not been defined. Groundwater flow was to the northwest direction during this monitoring event. Depth to groundwater was 4 to 6 feet below ground surface (bgs). One monitoring well was not assessible (DMW-3). Groundwater samples were collected with Hydrasleeves without purging. Sampling interval information was not provided, results may be biased low if correct interval was not sampled. |
Robert Weimer |
3/12/2014 |
Document, Report, or Work plan Review - other |
On September 6-11, 2013 seven soil borings were sampled, and three of them were converted into monitoring wells (MW-6, MW-7, and MW-8). Up to 0.189 mg/kg benzene (MW-6 at 10 feet bgs), non detect (<35.7 mg/kg) GRO, 11.0 mg/kg DRO, 97.6 mg/kg RRO, 0.0673 mg/kg EDB (MW-7 at 13 feet bgs - 0.00016 mg/kg cleanup level), 0.0451 mg/kg EDC (MW-7 at 13 feet bgs - 0.016 mg/kg cleanup level), non detect (<0.135 mg/kg) PCE, non detect (<0.135 mg/kg) MTBE, 6.65 mg/kg arsenic, 53.4 mg/kg chromium, and 5.84 mg/kg total lead. Groundwater was encountered at 5.2 to 6.95 feet below ground surface (bgs) in the soil borings. Monitoring well DMW-3 could not be located. Several of the sample locations were adjusted in the field because of utility/product piping/sve piping. MW-6 further to the south, MW-7 east by 7 feet, SB-6 south by 3 feet, and SB-5 to the west. |
Robert Weimer |
6/9/2014 |
Document, Report, or Work plan Review - other |
October 17-21, 2013 groundwater monitoring event report. Up to 15.3 ug/l benzene, 0.358 mg/l GRO, 1.34 mg/l DRO, non detect (<2.0 ug/l) lead, and 1.71 mg/l RRO in the groundwater (MTBE analysis was not conducted during this event). The groundwater sampling included the three new monitoirng wells (MW-6, MW-7, and MW-8). Contaminant concentrations increased in 3 of the 7 monitoring wells sampled. The extent of the contamination to the south and west has not been defined. Groundwater flow was to the northeast direction during this monitoring event. Depth to groundwater was 3.92 to 7.07 feet below ground surface (bgs). One monitoring well (DMW-3) was not assessible. Groundwater samples were collected with Hydrasleeves without purging and bladder pump after pumping. For both no-purge and purge sampling the sample interval information was not provided, results may be biased low if correct interval was not sampled. |
Robert Weimer |
10/20/2014 |
Offsite Soil or Groundwater Disposal Approved |
ADEC approves request to treat 1 drum of contaminated purge water. |
Robert Weimer |
6/23/2015 |
Document, Report, or Work plan Review - other |
April 8, 2014 groundwater monitoring event (monitoring well DMW-1 was sampled on June 17, 2014 because it was iced in) report. Up to 13 ug/l benzene, 0.708 mg/l GRO, 0.152 mg/l DRO, non detect (<2.0 ug/l) lead, and 0.207 mg/l RRO in the groundwater (MTBE analysis was not conducted during this event). Contaminant concentrations increased in 1 of the 7 monitoring wells sampled. The extent of the contamination to the south and west has not been defined. Groundwater flow was to the northwest direction during this monitoring event. Depth to groundwater was 6.44 to 8.12 feet below ground surface (bgs). One monitoring well (DMW-3) was not assessible. Groundwater samples were collected bladder pump after pumping. The samples were collected from near the soil/water interface as required in 4 of the monitoring wells. The depth to the intake for the bladder pump was not documented correctly (the depth was above the groundwater) on monitoring wells DMW2, MW7, and MW8 so the results for those monitoring wells are considered biased low. |
Robert Weimer |
7/24/2015 |
Document, Report, or Work plan Review - other |
October 7, 2014 groundwater monitoring event report. Up to 8.48 ug/l benzene, 0.995 mg/l GRO, 0.644 mg/l DRO, non detect (<10 ug/l) lead, and 0.197 mg/l RRO in the groundwater (MTBE analysis was not conducted during this event). Contaminant concentrations increased in 7 of the 7 monitoring wells sampled. The extent of the contamination to the south and west has not been defined. Groundwater flow was to the northwest direction during this monitoring event. Depth to groundwater was 4.52 to 7.04 feet below ground surface (bgs). One monitoring well (DMW-3) was not assessible. Groundwater samples were collected bladder pump after pumping. The samples were collected from near the soil/water interface as required. |
Robert Weimer |
11/2/2015 |
Offsite Soil or Groundwater Disposal Approved |
ADEC approves request to treat 1 drum of contaminated purge water at NCR's facility at 2020 Viking Drive. |
Robert Weimer |
1/27/2016 |
Document, Report, or Work plan Review - other |
April 14, 2015 groundwater monitoring event report. Up to 34.9 ug/l benzene, 1.08 mg/l GRO, 2.49 mg/l DRO, non detect (<1 ug/l) lead, and 2.21 mg/l RRO in the groundwater (MTBE analysis was not conducted during this event). Contaminant concentrations increased in 7 of the 7 monitoring wells sampled. The extent of the contamination to the south and west has not been defined. Groundwater flow was to the west during this monitoring event. Depth to groundwater was 5.52 to 8.23 feet below ground surface (bgs). One monitoring well (DMW-3) was not located. Groundwater samples were collected bladder pump after purging. The samples were collected from near the soil/water interface as required. The groundwater samples for monitoring wells DMW-1, DMW-4C, MW5, MW6, and MW7 are considered biased low because they arrived at the laboratory 3 to 4 days after sampling over temperature (7.7 degrees C). The over temperature was noted on the QA/QC checklist but not in the data quality section of the report. |
Robert Weimer |
3/4/2016 |
Document, Report, or Work plan Review - other |
October 20, 2015 groundwater monitoring event report. Up to 31.1 ug/l benzene, 0.904 mg/l GRO, 1.06 mg/l DRO, 2.3 ug/l lead, and 1.28 mg/l RRO in the groundwater (MTBE analysis was not conducted during this event). Contaminant concentrations increased in 4 of the 7 monitoring wells sampled. The extent of the contamination to the south and west has not been defined. Groundwater flow was to the west during this monitoring event. Depth to groundwater was 5.00 to 6.60 feet below ground surface (bgs). One monitoring well (DMW-3) was not located. Groundwater samples were collected submersible pump after purging. The samples were collected from near the top of the water column as required. |
Robert Weimer |
3/15/2016 |
Meeting or Teleconference Held |
Teleconference with Shell and their consultant (GES) to discuss future site work for site closure. They will submit a work plan for the 2016 groundwater monitoring that will include analysis for PAHs. We discussed that the extent of the soil and groundwater contamination has not been defined and they will submit a work plan for soil borings and monitoring wells along the property boundary to the south and west or off-property monitoring wells in those directions (such as across Dimond Boulevard). DEC requested rose diagrams showing historical groundwater flow directions be included in future site monitoring report maps. |
Robert Weimer |
5/27/2016 |
Update or Other Action |
Because of the past halogenated organic contamination at this site ADEC requested that the next groundwater monitoring event at this site include VOC analysis for EPA Method 8260. After the receiving the results of that sampling ADEC is requesting in 2016 an evaluation for the potential for BTEX, PAH, and VOC to impact to indoor air be conducted for this site. |
Robert Weimer |
7/27/2016 |
Document, Report, or Work plan Review - other |
DEC requested revised work plan for PAH sampling of selected monitoring wells at this site to help assess current concentrations in the groundwater. |
Robert Weimer |
8/3/2016 |
Meeting or Teleconference Held |
Teleconference with Shell and their consultant (GES) to discuss future site work for site closure. They will submit a revised work plan for the September/October 2016 groundwater monitoring to include PAHs. Rose diagrams showing historical groundwater flow directions are to be included in future site monitoring report maps. They will document which monitoring wells are damaged or not accessible, so they can be repaired, decommissioned, or possibly replaced. We discussed that the extent of the soil and groundwater contamination has not been defined and they will submit a work plan for soil borings and monitoring wells along the property boundary to the south and west or off-property monitoring wells in those directions (such as across Dimond Boulevard). |
Robert Weimer |
10/27/2016 |
Document, Report, or Work plan Review - other |
April 2, 2016 groundwater monitoring event report. Up to 30.5 ug/l benzene, 0.642 mg/l GRO, 2.08 mg/l DRO, and 2.32 mg/l RRO in the groundwater (Lead and MTBE analysis was not conducted during this event). Contaminant concentrations increased in 4 of the 7 monitoring wells sampled. The extent of the contamination to the south and west has not been defined. Groundwater flow was to the northwest during this monitoring event. Depth to groundwater was 5.41 to 8.32 feet below ground surface (bgs). One monitoring well (DMW-3) was not located. Groundwater samples were collected submersible pump after purging. The samples were collected from near the top of the water column as required. One of the two coolers arrived at the lab 4 days after sampling over temperature (7.7 degrees C) so those samples are considered biased low. |
Robert Weimer |
12/15/2016 |
Document, Report, or Work plan Review - other |
Review of work plan for installation of monitoring wells to help define the extent of the soil and groundwater contamination to the south, west, and northwest of the contaminated areas. Need a revised work plan that includes the following: Full PAH analysis, soil and groundwater transport forms, 3 additional monitoring wells, soil sample at soil/water interface and another depth if it appears more contaminated, and don't hand auger to the soil/water interface. |
Robert Weimer |
12/15/2016 |
Document, Report, or Work plan Review - other |
Teleconference with Shells consultant (GES) to discuss future site work for site closure. We discussed that the extent of the soil and groundwater contamination needs to be characterized before a site can be considered for closure. They will submit a proposal for DEC approval regarding future groundwater monitoring. They will submit and updated PAH sampling report with method detection limits.
DEC is requesting a revised work plan for the installation of additional monitoring wells. |
Robert Weimer |
4/3/2017 |
Document, Report, or Work plan Review - other |
October 4, 2016 groundwater monitoring event report. Up to 41.3 ug/l benzene, 0.374 mg/l GRO, 0.869 mg/l DRO, 1.4 ug/l naphthalene, 3.1 ug/l 1-methylnaphthalene, 37.6 ug/l MTBA, 0.34 ug/l 1,2-DCA, 93.2 ug/l (15 ug/l cleanup level) 1,2,4-trimethylbenzene, and 0.634 mg/l RRO in the groundwater. Contaminant concentrations increased in 6 of the 7 monitoring wells sampled. The extent of the contamination to the south and west has not been defined. Groundwater flow was to the west during this monitoring event. Depth to groundwater was 5.40 to 7.78 feet below ground surface (bgs). One monitoring well (DMW-3) was not located. Groundwater samples were collected submersible pump after purging. The samples were collected from near the top of the water column as required. Sample MW-6 was not properly preserved (pH >2) in the field so it is considered biased low. |
Robert Weimer |
4/3/2017 |
Update or Other Action |
DEC approves reduction in groundwater monitoring to the following sample analysis:
DMW-1: DRO, RRO, full VOC (8260), and PAHs
DMW-2: full VOC (8260)
DMW-4C: full VOC (8260), and PAHs
DMW-5: full VOC (8260)
No analytical sampling is requested for monitoring wells DMW-6, DMW-7, and DMW-8.
|
Robert Weimer |
8/7/2017 |
Document, Report, or Work plan Review - other |
April 18-19, 2017 groundwater monitoring event. Up to 5.81 ug/l benzene, 0.134 mg/l GRO, 0.850 mg/l DRO, 0.570 mg/l RRO in the groundwater. The other VOCs and PAHs were either non-detect or below current cleanup levels. Contaminant concentrations increased in 3 of the 5 monitoring wells sampled. The extent of the contamination to the south and west has not been defined. Groundwater flow was to the west during this monitoring event. Depth to groundwater was 3.86 to 8.10 feet below ground surface (bgs). Monitoring well (DMW-1) was not sampled, it was full of ice. Monitoring well MW-8 was not sampled due to failure of the sampling pump. Groundwater samples were collected submersible pump after purging. Since the samples were received over temperature at 7.1 degrees C five days after sampling the results are considered biased low. |
Robert Weimer |
8/8/2017 |
Meeting or Teleconference Held |
Meeting with Shell with Shells consultant (GES) to discuss future site work for site closure. We discussed that they will continue to attempt to get off property access to define the extent of the soil and groundwater contamination at the site, if they are not able to get access then DEC could contact the property owner to see if it can help get access. Full VOC groundwater sampling to be conducted soon, may need vapor intrusion assessment of on-property building depending on the VOC results. |
Robert Weimer |
12/4/2017 |
Document, Report, or Work plan Review - other |
October 3, 2017 groundwater monitoring event. Up to 14.6 ug/l benzene, 0.726 mg/l DRO, 2.0 mg/l RRO, 0.65 ug/l Naphthalene, 14.8 ug/l MTBE, and 0.88 ug/l 1-Methylnapthalene in the groundwater. The other VOCs and PAHs were either non-detect or below current cleanup levels. Contaminant concentrations increased in 3 of the 4 monitoring wells sampled. The extent of the contamination to the south and west has not been defined. Groundwater flow was to the west during this monitoring event. Depth to groundwater was 5.30 to 7.15 feet below ground surface (bgs). Groundwater samples were collected submersible pump after purging. |
Robert Weimer |
12/22/2017 |
Meeting or Teleconference Held |
Teleconference with Shell with Shells consultant (GES) to discuss future site work for site closure. We discussed that they will continue to attempt to get off property access to define the extent of the soil and groundwater contamination at the site, if they are not able to get access then DEC could contact the property owner to see if it can help get access. Full VOC and PAH groundwater sampling to continue, may need vapor intrusion assessment of on-property building depending on the VOC results. |
Robert Weimer |
4/6/2018 |
Document, Report, or Work plan Review - other |
DEC review and approval of April 6, 2018 revised well installation work plan. Work is to be conducted around April 18, 2018. The work plan proposes to install five additional downgradient monitoring wells and collect soil and groundwater samples to help define the extent of the remaining contamination. Three of the monitoring wells are to be installed on the property to the west. |
Robert Weimer |
4/18/2018 |
Site Visit |
Site visit to observe the soil sampling and installation of the additional down gradient monitoring wells. Work was going slow due to cobbles. |
Robert Weimer |
4/18/2018 |
Meeting or Teleconference Held |
Teleconference with Shell with Shells consultant (GES) to discuss future site work for site closure. We discussed that they have access to down gradient property and are to install monitoring wells soon and that if contamination remains off-property there would need to be a separate IC signed by that property owner for closure. |
Robert Weimer |
8/15/2018 |
Meeting or Teleconference Held |
Meeting with Shell with Shells consultant (GES) to discuss future site work for site closure. We discussed that they need a minimum of four quarterly monitoring events of the newly installed monitoring wells along with the semi-annual sampling of the other site monitoring wells. They were not able to install one of the proposed monitoring wells due to utilities in that area so they will need a monitoring well across Dimond Boulevard or wait until the on-property monitoring wells in that direction are demonstrated below Table C cleanup levels to consider the site for IC closure. On all sites GES will provide a diagram showing the remaining soil contamination above migration to groundwater, human health, and maximum allowable cleanup levels. |
Robert Weimer |
11/1/2018 |
Document, Report, or Work plan Review - other |
On April 18-20, 2018 four additional monitoring wells (MW-9, MW-10, MW-12, and MW-13) were installed. These monitoring wells were installed off-property just to the west of the gas station property. Two soil samples were collected from each monitoring well during installation. The soil samples were analyzed for VOCs, GRO, DRO, RRO, and PAHs. Up to 7.14 mg/kg GRO. 12.8 mg/kg DRO, 75.6 mg/kg RRO, 0.00474 mg/kg naphthalene, and 0.0102 mg/kg benzene. The rest of the compounds were non-detect or below current site cleanup levels. Groundwater was encountered between 4.5 to 7.5 feet below ground surface (bgs). The well screen intervals in all of the monitoring wells is 4 to 14 feet bgs. |
Robert Weimer |
11/5/2018 |
Offsite Soil or Groundwater Disposal Approved |
DEC approved request for off-site treatment and disposal of 6 drums of soil cuttings and 1 drum of development water. The soil and water were generated during the April 2018 monitoring well installations. |
Robert Weimer |
12/12/2018 |
Document, Report, or Work plan Review - other |
April 25, 2018 groundwater monitoring event. Up to 6.24 ug/l benzene, 0.0328 mg/l GRO, 0.487 mg/l DRO, 1.32 mg/l RRO, 0.143 ug/l Naphthalene, 28.3 ug/l MTBE, and 0.619 ug/l 1-Methylnapthalene in the groundwater. The other VOCs and PAHs were either non-detect or below current cleanup levels. Contaminant concentrations increased in 3 of the 7 monitoring wells sampled. Groundwater flow was to the west during this monitoring event. Depth to groundwater was 4.52 to 13.64 feet below ground surface (bgs). Groundwater samples were collected with a bladder pump after purging. The samples are potentially biased low because the depth of the sampling was not documented and the samples may not have been collected within the top foot of the water column as required. |
Robert Weimer |
1/17/2019 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 77716 UST contamination. |
Robert Weimer |
2/20/2019 |
Document, Report, or Work plan Review - other |
October 4-5, 2018 groundwater monitoring event. Up to 42.9 ug/l benzene, 0.0752 mg/l GRO, 1.31 mg/l DRO, 6.04 mg/l RRO, 0.229 ug/l Naphthalene, 30.3 ug/l MTBE, and 3.53 ug/l 1-Methylnapthalene in the groundwater. The other VOCs and PAHs were either non-detect or below current cleanup levels. A sheen was noted on the surface of the water in monitoring well MW-4A which was not sampled during this monitoring event. Contaminant concentrations increased in 4 of the 6 monitoring wells sampled. Groundwater flow was to the west during this monitoring event. Depth to groundwater was 4.89 to 7.45 feet below ground surface (bgs). Groundwater samples were collected with a bladder pump after purging in monitoring wells DMW-2 and MW-9 but the depth of the pump intake was not documented as being in the top foot of the water column as required, so the results in those monitoring wells may be biased low. Since monitoring well DMW-1, MW-10, MW-12, MW-13 samples were collected after purging using a bailer the volatile results from these monitoring wells may be biased low. A sheen was noted on the surface of the water in monitoring well MW-4A which was not sampled during this monitoring event, need to add this monitoring well to the groundwater sampling schedule. |
Robert Weimer |
8/27/2019 |
Document, Report, or Work plan Review - other |
January 23, 2019 groundwater monitoring event. Up to 0.931 ug/l benzene, 0.025 mg/l GRO, 0.705 mg/l DRO, 1.01 mg/l RRO, 0.0385 ug/l Naphthalene, and 17.2 ug/l MTBE in the groundwater. The other VOCs and PAHs were either non-detect or below current cleanup levels. Contaminant concentrations increased in 3 of the 3 monitoring wells sampled. Monitoring well MW-9 was not sampled this monitoring event because it could not be located. Groundwater flow was not determined this monitoring event. Depth to groundwater was 6.55 to 6.70 feet below ground surface (bgs). Groundwater samples were collected with a bladder pump after purging from the top foot of the water column as required. |
Robert Weimer |
8/27/2019 |
Document, Report, or Work plan Review - other |
April 3, 2019 groundwater monitoring event. Up to 31.7 ug/l benzene, 0.0422 mg/l GRO, 0.417 mg/l DRO, 1.05 mg/l RRO, 5.16 ug/l Naphthalene, 43.6 ug/l MTBE, and 16.3 ug/l Ethylbenzene in the groundwater. The other VOCs and PAHs were either non-detect or below current cleanup levels. Monitoring well MW-9 was not sampled this monitoring event because of ice in the monitoring well. The only time monitoring well MW-9 was sampled (10/04/2018) it had 36.7 ug/l benzene. No sheens were noted in any of the monitoring wells. Contaminant concentrations increased in 4 of the 8 monitoring wells sampled. Groundwater flow was to the west during this monitoring event. Depth to groundwater was 5.55 to 8.23 feet below ground surface (bgs). Groundwater samples were collected with a bladder pump after purging from the top foot of the water column as required in the shallow monitoring wells. The deep monitoring well MW-4A that is screened between 25-30 feet below ground surface (bgs) had its sample collected at 8.5 bgs instead of within the top foot of the screened interval as required. |
Robert Weimer |
8/28/2019 |
Meeting or Teleconference Held |
Meeting with Shell with Shells consultant (GES) to discuss future site work for site closure. We discussed that they need a summer monitoring event in 2020 of the newly installed monitoring wells along with the semi-annual sampling of the other site monitoring wells. They will submit a work plan for the installation of a downgradient monitoring well across Dimond Boulevard (sampled for a minimum of 4 quarters) or wait until the on-property monitoring wells in that direction are demonstrated below Table C cleanup levels to consider the site for IC closure. GES will provide a diagram showing the remaining soil contamination above migration to groundwater, human health, and maximum allowable cleanup levels. We discussed that the deeper monitoring well MW-4A need to have the pump intake between 25 to 26' bgs so it is purging and collecting water from the top foot of the screened interval. |
Robert Weimer |
8/4/2020 |
Document, Report, or Work plan Review - other |
The ADEC sent a comment letter regarding the submitted groundwater monitoring report dated November 27, 2019. |
Randy Guintu |
8/24/2020 |
Meeting or Teleconference Held |
Meeting with Shell and their consultant, GES to discuss site conditions, pending actions and future work at multiple sites. It was discussed that sites must be characterized both vertically and horizontally in all contaminated media to move forward with site closure with institutional controls (ICs). To move forward with site closure with ICs would also require landowner and stakeholder concurrence and the required documentation under the Uniform Environmental Covenants Act. Other discussions involved what steps needed to be taken to continue monitoring and sampling where necessary. |
Randy Guintu |
3/5/2021 |
Site Characterization Report Approved |
The ADEC issued a report approval letter for the revised Second Semiannual 2019 Groundwater Monitoring Report on March 5, 2021. |
Randy Guintu |
9/7/2021 |
Document, Report, or Work plan Review - other |
ADEC received a work plan from Shell's consultant, GES. The work plan proposes installing a new monitoring well, MW-14, to the southwest of the site across Dimond Boulevard, pending approval from the business owner. |
Flannery Ballard |
9/24/2021 |
Update or Other Action |
The ADEC issued a comment letter in response to the Work Plan for Well Installation, requesting additional information concerning the contaminants to be tested, methodology, soil sampling intervals, and waste disposal plan. The ADEC also asked for clarification on whether all wells will be sampled if proposed well, MW-14, is installed to the southwest of the site. Lastly, the ADEC noted that the location of the proposed well is at such as distance from the site, that it it may not provide sufficient data to adequately delineate the contaminant plume. The ADEC recommended the RP and consultant consider coordinating with the Alaska Department of Transportation to inquire whether a sampling event might be possible in the right-of-way or in E. Dimond Blvd. |
Flannery Ballard |
10/4/2021 |
Document, Report, or Work plan Review - other |
GES consultants submitted a letter addressing ADEC's comments in regards to the Work Plan for Well Installation for MW-14. The ADEC is reviewing the response letter. |
Flannery Ballard |
10/20/2021 |
Update or Other Action |
ADEC issued a letter of approval for the installation of monitoring well (MW-14) to the south of the site. The consultant, GES, is still waiting for property owner approval. |
Flannery Ballard |
3/23/2022 |
Site Characterization Report Approved |
The ADEC approved the "Second Semiannual 2021 Groundwater Monitoring Report". Groundwater samples were collected from nine monitoring wells, DMW-1, DMW-2, DMW-4A, DMW-4C, DMW-5, MW-9, MW-10, MW-12, and MW-13.
Benzene was detected in MW-9 at a concentration of 20.2 micrograms per liter (ug/L), which is greater than the ADEC groundwater cleanup level of 4.6 ug/L. The ADEC agrees with the recommendation to continue semiannual groundwater monitoring at the site until the constituents of potential concern (COPCs) are at concentrations less than the ADEC groundwater cleanup levels or show a stable or decreasing trend that may be acceptable for closure with institutional controls. |
Flannery Ballard |
1/13/2023 |
Site Characterization Report Approved |
The ADEC approved the "First Semiannual 2022 Groundwater Monitoring Report". Groundwater samples were collected from nine monitoring wells, DMW-1, DMW-2, DMW-4A, DMW-4C, DMW-5, MW-9, MW-10, MW-12, and MW-13. Benzene was detected in MW-9 at a concentration of 17.2 micrograms per liter (ug/L), which is greater than the ADEC groundwater cleanup level of 4.6 ug/L. The ADEC agrees with the recommendation to continue semiannual groundwater monitoring at the site until the constituents of potential concern (COPCs) are at concentrations less than the ADEC groundwater cleanup levels or show a stable or decreasing trend that may be acceptable for closure with institutional controls. In addition, the ADEC agrees with the recommendation to remove PAHs from the analytical sampling list. PAHs have not been detected at the site above the ADEC cleanup levels with the exception of one detection of naphthalene in DMW-4C in April 2019 |
Alena Voigt |
5/5/2023 |
Site Characterization Report Approved |
The ADEC CSP reviewed the “Second Semiannual 2022 Groundwater Monitoring Report”, dated January 12, 2023, from Groundwater & Environmental Services, Inc. (GES).
The report discusses the latest groundwater monitoring and sampling event at the Texaco - #91 Oehrlis site on October 10 - 11, 2022. Groundwater samples were collected from nine monitoring wells, DMW-1, DMW-2, DMW-4A, DMW-4C, DMW-5, MW-9, MW-10, MW-12, and MW-13. Samples were analyzed for GRO, DRO, RRO, VOCS, and PAHs.
Benzene was detected in MW-9 at a concentration of 8.06 micrograms per liter (ug/L), which is greater than the ADEC Table C cleanup level of 4.6 ug/L. In addition, RRO was detected in MW-13 at a concentration of 1,730 ug/L, greater than the ADEC Table C cleanup level of 1,100 ug/L. The remaining tested analytes were either not detected or were detected at concentrations less than the applicable cleanup levels. Groundwater flow direction is to the west.
The ADEC agrees with the recommendation to continue semiannual groundwater monitoring at the site. In addition, the ADEC agrees with the recommendation to remove PAHs from the analytical sampling list. PAHs have not been detected at the site above the ADEC cleanup levels with the exception of one detection in DMW-4C in April 2019. The ADEC requests an updated work plan to reflect the recommendation above and be submitted for review to the CSP.
|
Alena Voigt |
9/15/2023 |
Update or Other Action |
The ADEC CSP reviewed the “First Semiannual 2023 Groundwater Monitoring Report”, dated June 14, 2023, received on July 14, 2023, via electronic mail, from Groundwater & Environmental Services, Inc. (GES). The ADEC provided comments to the responsible party and environmental consultant and requested a revised report be submitted to the CSP for review. |
Alena Voigt |
9/29/2023 |
Meeting or Teleconference Held |
Teleconference held with GES, Shell, ADEC PM and Supervisor regarding site and path towards closure. |
Alena Voigt |
12/28/2023 |
Site Characterization Workplan Approved |
The ADEC CSP reviewed the "2023 Updated Groundwater Monitoring Workplan" received by GES. The work plan recommends removing polycyclic aromatic hydrocarbons (PAHs) from the analytical sampling list. PAHs have not been detected at the site above the ADEC cleanup levels with the exception of one detection in DMW-4C in April 2019.Groundwater monitoring wells identified as DMW-1, DMW-2, DMW-4A, DMW-4C, DMW-5, MW-9, MW-10, MW-12, and MW-13 will be sampled on a semi-annual schedule and analyzed for gasoline range organics (GRO), diesel range organics (DRO), residual range organics (RRO), and volatile organic compounds (VOCs). |
Alena Voigt |
12/28/2023 |
Site Characterization Report Approved |
The ADEC CSP received the revised report from GES on December 4, 2023. Groundwater samples were collected from nine monitoring wells, DMW-1, DMW-2, DMW-4A, DMW-4C, DMW-5, MW-9, MW-10, MW-12, and MW-13. Samples were analyzed for GRO, DRO, RRO, and VOCs. Benzene was detected in MW-5 and MW-9 at concentrations of 10.3 micrograms per liter (ug/L) and 12.1 ug/L, respectively, greater than the ADEC Table C cleanup level of 4.6 ug/L. In addition, naphthalene was detected in DMW-1 (2.20 ug/L) greater than the ADEC Table C cleanup level of 1.7 ug/L. The remaining tested analytes were either not detected or were detected at concentrations less than the applicable cleanup levels. Groundwater flow direction is to the west. |
Alena Voigt |
5/29/2024 |
Site Characterization Report Approved |
CSP reviewed "Second Semiannual 2023 Groundwater Monitoring Report". Groundwater samples were collected from nine monitoring wells, DMW-1, DMW-2, DMW-4A, DMW-4C, DMW-5, MW-9, MW-10, MW-12, and MW-13. Samples were analyzed for GRO, DRO, RRO, and VOCs. Benzene was detected in MW-9 at a concentration of 8.71 micrograms per liter (ug/L), greater than the ADEC Table C cleanup level of 4.6 ug/L. The remaining tested analytes were either not detected or were detected at concentrations less than the applicable cleanup levels. Groundwater flow direction is to the west. |
Alena Voigt |