Action Date |
Action |
Description |
DEC Staff |
8/2/1989 |
Site Visit |
Site visit during tank removal noted visual and olfactory evidence of petroleum contaminated soil. |
Ron Godden |
8/2/1990 |
Underground Storage Tank Site Characterization or Assessment |
Site assessment report for upgrade of gasoline UST system. |
Former Staff |
8/2/1990 |
Leaking Underground Storage Tank Release Confirmed - Petroleum |
LUST Site created in CSP for source area ID 78437 Gasoline contamination. |
Former Staff |
8/2/1990 |
Site Added to Database |
|
Former Staff |
8/3/1990 |
Leaking Underground Storage Tank Cleanup Initiated - Petroleum |
LCAU Date changed DB conversion. |
Former Staff |
8/10/1990 |
Update or Other Action |
ADEC letter to Texaco requesting workplans for release investigation and corrective action for the remaining contamination at the site. |
John Halverson |
9/17/1990 |
Update or Other Action |
ENSR to have AK Pollution Control remove, treat, then dispose of the contaminated soils at the Anchorage Municipality landfill. ADEC approval sent on 09/21/90. |
John Halverson |
9/21/1990 |
Update or Other Action |
ADEC approves transport and treatment of used oil contaminated soil. |
John Halverson |
10/2/1990 |
Update or Other Action |
ADEC approves thermal treatment of gasoline contaminated soil from the site. |
John Halverson |
11/8/1990 |
Document, Report, or Work plan Review - other |
ENSR Environmental assessment report for site: total petroleum hydrocarbon levels in fuel oil excavation were from 28 to 113 mg/kg, in area found to contain buried drums were 27 to 973 mg/kg. Groundwater samples collected from the 3 monitoring wells were non detectable for BETX . |
Former Staff |
12/11/1990 |
Update or Other Action |
ADEC letter sent out requesting plans for additional assessment and or cleanup by 1-25-91. ENSR documents from disposal of waste oil contaminated soil disposal at landfill after treatment at the AK Pollution Control facility in Palmer received by ADEC on 4/12/91. The letter also noted QA/QC problems with some of the samples collected. |
John Halverson |
12/14/1990 |
Document, Report, or Work plan Review - other |
12/14/90 groundwater monitoring event. The three site monitoring wells sampled were all non-detect (<1.0 ug/l) benzene in the groundwater. Corrected groundwater flow direction is to the southwest. |
Robert Weimer |
2/20/1991 |
Update or Other Action |
ADEC letter sent to Texaco conditionally approving plan (received on 2/20/91). The results of additional testing & assessment work be sent for review & approval along with final plans for the design, installation & operation of the remediation systems. |
Former Staff |
2/22/1991 |
Document, Report, or Work plan Review - other |
2/22/91 groundwater monitoring event. The three monitoring wells were sampled were all non-detect (<1.0 ug/l) benzene in the groundwater. Groundwater flowed to the southwest. |
Robert Weimer |
3/8/1991 |
Document, Report, or Work plan Review - other |
Texaco's consultant provides documentation of the disposal at the MOA landfill of soil treated at APC. |
Robert Weimer |
4/19/1991 |
Update or Other Action |
ADEC letter approving corrective action plan. The plan calls for using a vapor extraction system (VES) to treat the remaining soil contamination at the tanks and disenser islands. VES piping was installed beneath the new tanks and dispensers. |
John Halverson |
4/26/1991 |
Document, Report, or Work plan Review - other |
A fourth monitoring well (TI-4) was installed on 4/26/91. This monitoring well was installed on the east side of the former buried drum exavation (located on the northeast corner of the property). Soil samples collected during the installation of the monitoring well had up to 2,690 mg/kg DRO, and non-detect (<0.02 mg/kg) benzene. Contamination over cleanup levels was found from 2.5 to 9.5 feet below ground surface (bgs) and 15 to 24.5 feet bgs. Groundwater was encountered at 23 feet bgs. The extent of the contamination has not been defined. |
Robert Weimer |
5/22/1991 |
Document, Report, or Work plan Review - other |
5/22/91 groundwater monitoring event. Four monitoring wells were sampled, they were all non-detect (<1.0 ug/l) for benzene in the groundwater. Groundwater flowed to the southwest. Depth to groundwater was 21.58 to 22.48 feet below ground surface. |
Robert Weimer |
11/8/1991 |
Document, Report, or Work plan Review - other |
11/8/91 groundwater monitoring event. Four monitoring wells were sampled, they were all non-detect (<1.0 ug/l) for benzene in the groundwater. Groundwater flowed to the southwest. Depth to groundwater was 21.78 to 22.30 feet below ground surface. |
Robert Weimer |
10/20/1992 |
Document, Report, or Work plan Review - other |
10/20/92 groundwater monitoring event. Four monitoring wells were sampled. Up to 34 ug/l benzene and 0.077 mg/l GRO in the groundwater. Groundwater flowed to the southwest. Depth to groundwater was 21.5 to 22.27 feet below ground surface. |
Robert Weimer |
1/19/1993 |
Document, Report, or Work plan Review - other |
1/19/93 groundwater monitoring event. Four monitoring wells were sampled. Up to 0.6 ug/l benzene and 0.044 mg/l GRO in the groundwater. Groundwater flowed to the southwest. Depth to groundwater was 21.49 to 22.25 feet below ground surface. |
Robert Weimer |
4/27/1993 |
Document, Report, or Work plan Review - other |
4/27/93 groundwater monitoring event. Four monitoring wells were sampled. Up to 1 ug/l benzene and 0.05 mg/l GRO in the groundwater. Groundwater flowed to the southwest. Depth to groundwater was 21.28 to 22.11 feet below ground surface. |
Robert Weimer |
7/8/1993 |
Document, Report, or Work plan Review - other |
7/8/93 groundwater monitoring event. Four monitoring wells were sampled. Up to 0.4 ug/l benzene and non-detect (<0.01 mg/l) GRO in the groundwater. Groundwater flowed to the southwest. Depth to groundwater was 21.23 to 21.73 feet below ground surface. |
Robert Weimer |
8/26/1993 |
Document, Report, or Work plan Review - other |
The soil vapor extraction system (VES) began operation on August 26, 1993. Between 8/23/93 and 1/6/94 the VES system removed 513 pounds of gasoline. The VES is hooked up to piping at both pump islands, the northern portion of the tank area, and monitoring well T1-4 located at the former buried drum area. |
Robert Weimer |
10/29/1993 |
Document, Report, or Work plan Review - other |
10/29/93 groundwater monitoring event. Four monitoring wells were sampled, they were all non-detect (<0.3 ug/l) for benzene and non-detect (<0.01 mg/l) for GRO in the groundwater. Groundwater flowed to the southwest. Depth to groundwater was 21.21 to 21.63 feet below ground surface. |
Robert Weimer |
4/6/1994 |
Document, Report, or Work plan Review - other |
4/6/94 groundwater monitoring event. Two monitoring wells were sampled (two others were covered with snow). They were both non-detect (<1 ug/l) for benzene and non-detect (<0.05 mg/l) for GRO in the groundwater. Groundwater historically has flowed to the southwest. Depth to groundwater was 21.85 to 21.91 feet below ground surface. |
Robert Weimer |
7/16/1994 |
Document, Report, or Work plan Review - other |
7/16/94 groundwater monitoring event. Four monitoring wells were sampled, they were all non-detect (<0.5 ug/l) benzene and non-detect (<0.05 mg/l) GRO in the groundwater. Groundwater flowed to the southwest. Depth to groundwater was 21.71 to 22.28 feet below ground surface. |
Robert Weimer |
12/13/1994 |
Document, Report, or Work plan Review - other |
12/36/94 groundwater monitoring event. Four monitoring wells were sampled, they were all non-detect (<0.5 ug/l) benzene and non-detect (<0.05 mg/l) GRO in the groundwater. Groundwater flowed to the southwest. Depth to groundwater was 22.09 to 22.75 feet below ground surface. |
Robert Weimer |
2/10/1995 |
Update or Other Action |
ADEC letter approving suspending GRO analysis in all monitoring wells, and BTEX in monitoring wells T1-1 and T1-3. ADEC requests that all monitoring wells be sampled for TPH and monitoring well T1-4 for DRO and TPH. ADEC also requests VES system reports be submitted on a quarterly basis. |
Robert Weimer |
4/5/1995 |
Document, Report, or Work plan Review - other |
4/5/95 groundwater monitoring event. Three monitoring wells were sampled (monitoring well T1-4 was not sampled due to snow). They were non-detect (<0.5 ug/l) for benzene and non-detect (<0.05 mg/l) for GRO in the groundwater. Groundwater flowed to the southwest. Depth to groundwater was 22.21 to 22.80 feet below ground surface. |
Robert Weimer |
6/19/1995 |
Document, Report, or Work plan Review - other |
6/19/95 groundwater monitoring event. Four monitoring wells were sampled. Up to non-detect (<0.5 ug/l) benzene, 0.5 mg/l DRO, and non-detect (<0.25 mg/l) TPH in the groundwater. Groundwater flowed to the southwest. Depth to groundwater was 21.6 to 22.21 feet below ground surface. |
Robert Weimer |
9/19/1995 |
Document, Report, or Work plan Review - other |
9/19/95 groundwater monitoring event. Four monitoring wells were sampled. Up to non-detect (<0.5 ug/l) benzene, 1.3 mg/l DRO, and 1.6 mg/l TPH in the groundwater. Groundwater flowed to the southwest. Depth to groundwater was 22.0 to 24.58 feet below ground surface. The dilution valve has been open on the VES system since 5/25/95. |
Robert Weimer |
11/26/1996 |
Update or Other Action |
ADEC letter requests that monitoring wells T1-3 and T1-4 be sampled for DRO. ADEC also requests a confirmation soil sampling plan for the areas previously identified as having soil contamination over cleanup levels. The letter notes that the 9/23/96 sampling of the former drum area was not adequatelty assessed, it was dug in the wrong location and was only sampled at 3.5 to 4 feet below ground surface. The letter also noted that the site assessment for used oil tank that was removed on 9/19/96 was not complete. |
Robert Weimer |
1/23/1997 |
Document, Report, or Work plan Review - other |
Summary report for the removal of a 500 gallon used oil tank, 2 floor hoists, a sand trap, and a test pit near the former buried drum area on 9/23/96. The assessment of the buried drum area appears to be in the wrong location and to be too shallow (only 3.5 to 4 feet below ground surface-the previous excavation showed contamination also at the base at 8 feet bgs). Up to non-detect (<0.05 mg/kg) benzene, non-detect (<5 mg/kg) GRO, and 61.6 mg/kg at the sand trap excavation. Up to non-detect (<0.05 mg/kg) benzene, non-detect (<5 mg/kg) GRO, and 11.5 DRO mg/kg DRO at the floor hoists. Up to non-detect (<0.05 mg/kg) benzene, non-detect (<5 mg/kg) GRO, and 5.22 mg/kg DRO at the samples collected near the former buried drums, but the buried drum assessment was not complete and further assessment is required. Up to non-detect (<0.05 mg/kg) benzene, non-detect (<5 mg/kg) GRO, and 7.07 mg/kg DRO at the samples collected in the used oil tank excavation. |
Robert Weimer |
11/20/1997 |
Update or Other Action |
ADEC sends Notification of Intent to Cost Recover Letter to Current Owner: TEXACO REFINING & MARKETING INC. |
Former Staff |
7/26/2000 |
Update or Other Action |
ADEC requests a workplan for assessment at the drum area, a workplan for confirmation soil samples, and monitoring well sampling. |
Robert Weimer |
8/9/2001 |
Document, Report, or Work plan Review - other |
8/9/01 groundwater monitoring event. One monitoring well was sampled (T1-3). Up to 0.144 mg/l DRO in the groundwater. Groundwater historically flows to the southwest. Depth to groundwater was 21.92 to 22.16 feet below ground surface. |
Robert Weimer |
8/31/2004 |
Update or Other Action |
Soil contamination remains at former buried drum area and former/current UST gasoline system. There is also 0.05 mg/kg benzene on the excavation north wall of the former fuel oil tank (located on the north side of the building near the west corner). |
Robert Weimer |
10/24/2005 |
Update or Other Action |
Need soil confirmation samples to assess that remains at former buried drum area and former/current UST gasoline system. Also at the north sidewall of the former fuel oil tank (located on the north side of the building). |
Robert Weimer |
3/1/2007 |
Exposure Tracking Model Ranking |
Site ranked on the new Exposure Tracking Model (ETM). The ETM is a new site ranking system that looks at, based on available data, the potential exposure pathways for the contamination remaining at the site. (Gasoline tanks and drum areas) |
Robert Weimer |
10/24/2008 |
Document, Report, or Work plan Review - other |
Review of Phase II Report dated February 28, 2008 for the 901 East 15th Avenue property. The report documents the sampling of 6 soil borings and the collection of one groundwater sample at the site on January 21, 2008. While the sampling found no detectable petroleum contamination at the locations and depths sampled, the soil benzene detection limits (0.05 mg/kg and 0.06 mg/kg) did not meet our laboratory requirements so we it does not demonstrate that the benzene contamination remaining is below site cleanup levels (0.025 mg/kg). In addition the areas sampled were not close enough to assess the areas previously identified as having contamination above site cleanup levels. Additional confirmation sampling will be required the evaluate this site for closure. |
Robert Weimer |
12/2/2008 |
Update or Other Action |
File review to determine where confirmation sampling is needed for site closure. At minimum need: 1. Gasoline tank (TI-3) 20ft and soil/water interface for BTEX/GRO. 2. South dispenser island (TI-32) 6ft for BTEX/GRO. 3. South dispenser island (boring TI-B1) 21ft, soil/water interface, and the highest field screening depth shallower than 21ft all for BTEX/GRO. This boring to be completed as a monitoring well with a water sample collected for BTEX/GRO. 4. Fuel oil tank (TI-20) highest field screening within 8 feet for BTEX. 5. Drum area (TI-34) 8ft for BTEX/GRO/DRO/RRO/Total Arsenic/Total Chromium. 6. Drum area (TI-38) 4ft for BTEX/GRO/DRO/RRO/Total Arsenic/Total Chromium. 7. Drum area (Boring TI-4) 21, the highest field screening depth shallower than 21ft, and the soil water interface for BTEX/GRO/DRO/RRO/Total Arsenic/Total Chromium. This boring needs to be completed as a monitoring well, with a groundwater sample collected for BTEX/GRO/DRO/RRO. Monitoring wells need to be completed so that additional future groundwater monitoring events can be conducted if necessary. |
Robert Weimer |
2/12/2009 |
Update or Other Action |
Discussed with Texaco's consultant that they need to do further assessment and groundwater monitoring at the site. |
Robert Weimer |
4/1/2009 |
Meeting or Teleconference Held |
Discussed with Texaco's consultant (Delta) that they are stilling waiting direction from Texaco as to which consultant will take the lead on this site. |
Robert Weimer |
4/22/2010 |
Leaking Underground Storage Tank Release Confirmed - Petroleum |
LUST site created in CSP database for source area gasoline tank system, 78438 |
Robert Weimer |
8/25/2011 |
Meeting or Teleconference Held |
Meeting with Shell and CRA to discuss proposed site investigation work plan. The plan proposes to install two additional monitoring wells and sample 3 other soil borings to assess current soil contamination concentrations in those areas. The hope is that the sampling will demonstrate that the site has remediated to site cleanup levels. CRA is to provide a revised work plan to include additional soil boring locations. DEC also requested missing groundwater monitoring reports. |
Robert Weimer |
8/25/2011 |
Site Visit |
Site visit to observe current site conditions. |
Robert Weimer |
10/7/2011 |
Site Characterization Workplan Approved |
DEC approves work plan for the collection of soil and groundwater samples from 6 soil boring of which 1 or 2 will be completed as long term monitoring wells. The samples will help to assess the current levels of contamination at the site. |
Robert Weimer |
9/19/2012 |
Document, Report, or Work plan Review - other |
November 8, 2011 groundwater monitoring event. One monitoring well was sampled (MW-5) it was non-detect (<1.0 ug/l) benzene, non-detect (<100 ug/l) GRO, non-detect (<755 ug/l) DRO, and non-detect (<975 ug/l) RRO in the groundwater. Groundwater historically flows to the southwest. Depth to groundwater was 22 feet below ground surface. |
Robert Weimer |
10/30/2012 |
Offsite Soil or Groundwater Disposal Approved |
DEC approves request for transport and treatment of 1 drum of contaminated monitoring well purge water. |
Robert Weimer |
3/22/2013 |
Update or Other Action |
DEC request that all sites where there has been no purge groundwater sampling conducted during the last year, that for the next sampling event that they do both no purge then purge sampling from each monitoring well within the top foot of the water column, so we evaluate on a site specific basis whether no purge sampling has provided comparable data. The post purge well sampling for VOCs would need to be conducted via hydrasleeve, bladder pump, or in well pump. Non VOC sampling can be collected with a bailer or peristaltic pump (in addition to the VOC methods) if desired. The specific sampling methods will need to be documented in the report and included field notes.
If there is not enough time to do this adjustment for the planned sample event of March 26-April 4, then DEC requests that it be done on the following event. |
Robert Weimer |
3/27/2013 |
Document, Report, or Work plan Review - other |
March 30, 2012 groundwater monitoring event. One monitoring well was sampled (MW-5) it was non-detect (<1.0 ug/l) benzene, non-detect (<100 ug/l) GRO, non-detect (<769 ug/l) DRO, and non-detect (<952 ug/l) RRO in the groundwater. Groundwater historically flows to the southwest. Depth to groundwater was 22 feet below ground surface. Monitoring well was purged before sampling with low flow in well pump. |
Robert Weimer |
5/8/2013 |
Update or Other Action |
DEC confirmed that since the previous groundwater samples were collected after purging, that the DEC is not requesting a purge/no purge comparison sampling event for this site. |
Robert Weimer |
5/17/2013 |
Document, Report, or Work plan Review - other |
October 29, 2012 groundwater monitoring event. One monitoring well was sampled (MW-5) it was non-detect (<1.0 ug/l) benzene, non-detect (<100 ug/l) GRO, non-detect (<762 ug/l) DRO, and non-detect (<952 ug/l) RRO in the groundwater. Groundwater historically flows to the southwest. Depth to groundwater was 21 feet below ground surface. Monitoring well was purged before sampling with low flow in well pump. |
Robert Weimer |
6/28/2013 |
Site Visit |
Site visit to observe current site conditions. |
Robert Weimer |
8/29/2013 |
Document, Report, or Work plan Review - other |
June 13, 2012 groundwater monitoring event. One monitoring well was sampled (MW-5) it was non-detect (<1.0 ug/l) benzene, non-detect (<100 ug/l) GRO, non-detect (<769 ug/l) DRO, and non-detect (<952 ug/l) RRO in the groundwater. Groundwater historically flows to the southwest. Depth to groundwater was 21 feet below ground surface. Monitoring well was purged before sampling with low flow in well pump. |
Robert Weimer |
9/2/2013 |
Site Characterization Report Approved |
On October 2011 four soil borings were sampled and one monitoring well (MW-5) was installed and sampled. The sampling was conducted to help assess the current concentrations of contaminants in some of the areas of the site that had previously shown contamination over site cleanup levels. In the areas sampled there was up to non-detect (<23.7 mg/kg) GRO, non-detect (<20.7 mg/kg) DRO, non-detect (<101 mg/kg) RRO, 5.99 mg/kg arsenic, 35.7 mg/kg chromium, and 0.00448 mg/kg benzene in the soil. In the groundwater (MW-5) had non-detect (<0.1 mg/l) GRO, non-detect (<0.755 mg/l) DRO, non-detect (<0.971 mg/l) RRO, and non-detect (<1.0 ug/l) benzene. Depth to groundwater was 22.05 feet below ground surface. Two of the areas planned to be sampled (TI-29) and (TI-4/MW-4) were not sampled because of nearby active fuel line and nearby utilites. |
Robert Weimer |
9/3/2013 |
Site Characterization Workplan Approved |
The July 2, 2013 work plan is approved under the following conditions:
1. No vac truck or air-knife within 4 feet horizontally or vertically of a sample location.
2. Where the soil samples are to be collected they were excavated previously and filled with clean backfill. In those areas the samples need to be collected from non backfill soils unless there are higher field readings at shallower depths in the boring.
3. If the highest field reading depth is a different depth than proposed sampling depth then an additional sample needs to be collected at the highest field screening depth.
4. Need to report the full results of the 8260B analysis not just the BTEX and PCE proposed.
The work plan proposes to collect soil samples at two locations at waste oil WO-2 and and dispenser/piping location TI-29.
As have been discussed in the past, there are two other areas at the site that had identified contamination over cleanup levels that have not had confirmation samples collected and will need further assessment in the future: T1-4/MW-4 (former buried drum area) and T1-3 (former UST excavation). We can discuss in the future how best to address those areas.
Based on the results of site sampling additional assessment, monitoring, and or corrective action may be required. |
Robert Weimer |
10/10/2013 |
Document, Report, or Work plan Review - other |
August 17, 2012 groundwater monitoring event. One monitoring well was sampled (MW-5) it had non-detect (<100 ug/l) GRO, non-detect (<800 ug/l) DRO, and non-detect (<1,000 ug/l) RRO in the groundwater. Groundwater historically flows to the southwest. Depth to groundwater was 21 feet below ground surface. The monitoring well was purged before sampling with low flow in well pump. |
Robert Weimer |
10/22/2013 |
Update or Other Action |
Approved reduction in groundwater sampling in monitoring well MW-5 from quarterly to annual. |
Robert Weimer |
12/12/2013 |
Document, Report, or Work plan Review - other |
March 29, 2013 groundwater monitoring event. One monitoring well was sampled (MW-5) it had non-detect (<1 ug/l) benzene, non-detect (<100 ug/l) GRO, non-detect (<777 ug/l) DRO, non-detect (<1,010 ug/l) RRO, non-detect (<2 ug/l) arsenic, and non-detect (<2 ug/l) chromium in the groundwater. Groundwater historically flows to the southwest. Depth to groundwater was 21.45 feet below ground surface. The monitoring well was purged before sampling with a bladder pump. |
Robert Weimer |
3/5/2014 |
Document, Report, or Work plan Review - other |
June 14, 2013 groundwater monitoring event. One monitoring well was sampled (MW-5) it was non-detect (<1 ug/l) benzene, non-detect (<100 ug/l) GRO, non-detect (<800 ug/l) DRO, non-detect (<1,000 ug/l) RRO, non-detect (<2 ug/l) arsenic, and non-detect (<2 ug/l) chromium in the groundwater. Groundwater historically flows to the southwest. Depth to groundwater was 22.07 feet below ground surface. The monitoring well was purged before sampling with a bladder pump, but the results may be biased low because the sample interval was not documented in the report or in the field notes. |
Robert Weimer |
3/10/2014 |
Document, Report, or Work plan Review - other |
August 5, 2013 groundwater monitoring event. One monitoring well was sampled (MW-5) it had non-detect (<1 ug/l) benzene, non-detect (<100 ug/l) GRO, non-detect (<762 ug/l) DRO, non-detect (<943 ug/l) RRO, 11.5 ug/l arsenic, and 35.4 ug/l chromium in the groundwater. Groundwater historically flows to the southwest. Depth to groundwater was 21.11 feet below ground surface. The monitoring well was purged before sampling with a bladder pump, but the results may be biased low because the sample interval was not documented in the report or in the field notes. |
Robert Weimer |
5/27/2014 |
Document, Report, or Work plan Review - other |
On September 2013 two soil borings SB-A (near TI-29 at 6.5 feet below ground surface) and SB-B (near WO-2 at 7 feet below ground surface) were sampled. The borings were hand cleared within 4 feet of volatile samples. The samples were analyzed only for VOCs (full method 8260). Only 0.0207 mg/kg toluene was detected in the samples collected. This information was summarized in the May 2014 conceptual site model report. Still need copy of the full report for the September 2013 sampling. |
Robert Weimer |
5/27/2014 |
Conceptual Site Model Submitted |
Updated conceptual site model submitted. |
Robert Weimer |
8/8/2014 |
Offsite Soil or Groundwater Disposal Approved |
ADEC approves request for transport and treatment of 1 drum of contaminated monitoring well purge water. |
Robert Weimer |
9/25/2014 |
Offsite Soil or Groundwater Disposal Approved |
ADEC approves request for transport and treatment of 1 drum of contaminated monitoring well purge water. |
Robert Weimer |
4/23/2015 |
Document, Report, or Work plan Review - other |
June 16, 2014 groundwater monitoring event. One monitoring well was sampled (MW-5) that had non-detect (<1 ug/l) benzene, 286 ug/l DRO, 79.5 ug/l RRO, non-detect (<100 ug/l) GRO, non-detect (<2.0 ug/l) arsenic, and 0.532 ug/l chromium in the groundwater. Groundwater historically flows to the southwest. Depth to groundwater was 20.94 feet below ground surface. The monitoring well was purged before sampling with a bladder pump and the intake of the pump was 0.56 feet below the groundwater surface. |
Robert Weimer |
1/25/2016 |
Document, Report, or Work plan Review - other |
September 11, 2015 groundwater monitoring event. One monitoring well was sampled (MW-5) that had non-detect (<1 ug/l) benzene (5 ug/l cleanup level), 0.142 mg/l DRO (1.5 mg/l cleanup level, 0.0943 mg/l RRO (1.1 mg/l cleanup level), non-detect (<0.1 mg/l) GRO (2.2 mg/l cleanup level), non-detect (<2.67 ug/l) chromium (100 ug/l cleanup level), and 0.598 ug/l arsenic (10 ug/l cleanup level) in the groundwater. Groundwater historically flows to the southwest. Depth to groundwater was 21.62 feet below ground surface. The monitoring well was purged before sampling with a bladder pump and the intake of the pump was 0.45 feet below the groundwater surface. An additional monitoring well at the former drum are (TI-4) has been requested to assess the concentrations of groundwater contamination in that area of the site. |
Robert Weimer |
3/18/2016 |
Update or Other Action |
File review and provide the following information to the RPs (Shell Oil) consultant (GHD). Need further site characterization to consider it for closure:
1. Drum area (Boring TI-4), soil samples collected at the highest field screening depth shallower than 21ft, and the soil water interface analyzed for BTEX/GRO/DRO/RRO/PAH/VOC/Total Arsenic/Total Chromium. This boring needs to be completed as a long-term monitoring well, with quarterly groundwater samples collected for BTEX/GRO/DRO/RRO/PAH/VOC for a minimum of 1 year.
2. Gasoline tank (TI-3) soil samples collected at 20ft and soil/water interface analyzed for BTEX/GRO/Naphthalene.
3. Dispenser/piping location (TI-29) soil samples collected at 6.5ft and soil/water interface analyzed for BTEX/GRO/ Naphthalene.
|
Robert Weimer |
4/14/2016 |
Update or Other Action |
DEC requests from Shells consultant (GHD) a copy of the site investigation report for the sampling conducted on September 2013. |
Robert Weimer |
4/18/2017 |
Update or Other Action |
DEC requested work plan to complete site characterization at the dispenser, tank, and buried drum area. |
Robert Weimer |
4/19/2017 |
Update or Other Action |
Email from Shell's consultant GHD, they have not been able to locate the site investigation report for the sampling conducted on September 2013. They said they will continue to look for the report. |
Robert Weimer |
2/5/2018 |
Update or Other Action |
DEC again requests from Shells consultant (GHD) a copy of the site investigation report for the sampling conducted on September 2013. |
Robert Weimer |
4/12/2019 |
Update or Other Action |
DEC talked with Shells consultant and it appears that the 2013 report was never completed by the previous consultant and that the 2013 samples were not properly preserved in the field. They will submit a work plan to conduct the assessment of areas of TI-4 (former drum area), TI-3 (former UST excavation), and TI-29 (southern dispenser). This would include a monitoring well and a minimum of 4 quarterly groundwater event at the drum area. |
Robert Weimer |
8/26/2019 |
Update or Other Action |
DEC contacted Shells consultant for an update on the requested work plan and site work. |
Robert Weimer |
3/30/2021 |
Site Characterization Workplan Approved |
The ADEC approved a site characterization work plan submitted by Shell, and prepared by AECOM on February 24, 2021. |
Randy Guintu |
7/29/2021 |
Offsite Soil or Groundwater Disposal Approved |
Approval for investigative derived waste consisting of soil borings and purge water approved to be disposed of via US Ecology. |
Kara Kusche |
12/16/2021 |
Offsite Soil or Groundwater Disposal Approved |
Approval for 55 gallons of investigative derived purge water to be disposed of via US Ecology. |
Flannery Ballard |
4/7/2022 |
Document, Report, or Work plan Review - other |
The ADEC provided comments in response to "Site Investigation Draft Report", and requested the report should be revised and re-submitted for approval. |
Flannery Ballard |
9/6/2022 |
Site Characterization Workplan Approved |
ADEC Approval Letter sent to Shell and consultant (AECOM) for Modification to Work Plan for additional site characterization. |
Alena Voigt |
12/16/2022 |
Document, Report, or Work plan Review - other |
The ADEC provided additional comments in response to "Site Investigation Draft Report", and requested the report should be revised and re-submitted for approval. |
Alena Voigt |
1/4/2023 |
Site Characterization Report Approved |
The revised “Site Investigation Final Report” was received on December 28, 2022. The revised final report is approved. |
Alena Voigt |
9/18/2023 |
Update or Other Action |
The Alaska Department of Environmental Conservation’s (ADEC) Contaminated Sites Program (CSP) reviewed the “Groundwater Monitoring Work Plan”, dated September 12, 2023, from AECOM Technical Services, Inc. (AECOM). The ADEC provided comments to the responsible party and environmental consultant that should be addressed and re-submitted. |
Alena Voigt |
10/12/2023 |
Site Characterization Workplan Approved |
The ADEC CSP reviewed the “Groundwater Monitoring Work Plan”, dated September 13, 2023, received from AECOM Technical Services, Inc. The CSP provided comments on September 18, 2023, and a revised work plan, dated September 19, 2023, was received on October 4, 2023. The work plan details include a land survey to confirm groundwater flow direction and gradient, an environmental database report (EDR), collecting groundwater monitoring samples, and preparing a letter report.
|
Alena Voigt |
6/21/2024 |
Site Visit |
Site visit to observe groundwater monitoring sampling. |
Alena Voigt |