Action Date |
Action |
Description |
DEC Staff |
4/20/1989 |
Release Investigation |
SI; Four soil borings drilled and two monitoring wells installed by Shannon & Wilson. Hydrocarbon contamination indicated in 3 of 4 borings. Up to 3200 ppm TPH, 4.8 ppm benzene and sum of 1035 ppm BTEX in soil. Floating hydrocarbon product in well B-10 and sheen in well B-9. Product identified as leaded gasoline. |
Former Staff |
5/18/1989 |
Leaking Underground Storage Tank Release Confirmed - Petroleum |
LUST Site created in CSP for source area ID 76777 ADD; |
Former Staff |
5/18/1989 |
Site Added to Database |
|
Former Staff |
2/8/1990 |
Leaking Underground Storage Tank Corrective Action Underway |
RAPR; Recommendation Plan for Follow-up Investigation prepared by Shannon & Wilson. |
Former Staff |
3/6/1990 |
Underground Storage Tank Site Characterization or Assessment |
SA1; Recommended plan for full investigation considering neighboring sites and establishing "clean" perimeter. |
Former Staff |
12/1/1990 |
Release Investigation |
SI; Final Report, Illinois Street and Minnie Street Connector, Hazardous Waste Field Investigation, Phase II, Fairbanks, Alaska, by Shannon & Wilson. Two soil borings drilled and one monitoring well installed. Analytical results indicated soil contamination by hydrocarbons at the water table and groundwater contamination by BTEX compounds (8200 ppb benzene) and 1,2-dichloroethane (27 ppb). |
Former Staff |
10/14/1991 |
Underground Storage Tank Site Characterization or Assessment |
SA1; Site Characterization work plan. |
Former Staff |
10/29/1991 |
Leaking Underground Storage Tank Corrective Action Underway |
CAPR; Basketfield - rejected work plan. |
Former Staff |
1/24/1992 |
Leaking Underground Storage Tank Corrective Action Underway |
CAPR; Revised Site characterization work plan. |
Former Staff |
1/27/1992 |
Underground Storage Tank Site Characterization or Assessment |
SA1R; Reviewed final, revised site assessment workplan. |
Former Staff |
1/31/1992 |
Underground Storage Tank Site Characterization or Assessment |
SA1R; Sent review & approval letter to consultant. |
Former Staff |
2/5/1992 |
Leaking Underground Storage Tank Corrective Action Underway |
CAPR; Basketfield - approved revised site characterization work plan. |
Former Staff |
3/28/1992 |
Release Investigation |
SA2; |
Former Staff |
5/15/1992 |
Leaking Underground Storage Tank Corrective Action Underway |
LCAR; Basketfield reviewed. |
Former Staff |
5/15/1992 |
Release Investigation |
RELR; Reviewed by Basketfield. |
Former Staff |
5/21/1992 |
Leaking Underground Storage Tank Corrective Action Underway |
LCAR; Revised corrective action plan submitted. |
Former Staff |
6/17/1992 |
Leaking Underground Storage Tank Corrective Action Underway |
LCAR; 2nd Revised CAP submitted |
Former Staff |
6/17/1992 |
Underground Storage Tank Site Characterization or Assessment |
SA1; Basketfield reviewed. |
Former Staff |
6/18/1992 |
Update or Other Action |
CORR; Gibler - Requestinf Standard QAPp and list of approved labs used for AR LUST soil and H2O analysis. |
Former Staff |
7/22/1992 |
Leaking Underground Storage Tank Corrective Action Underway |
LCAR; Final revision of CAP submitted and letter from Basketfield considers CAP inadequate re-details. |
Former Staff |
7/22/1992 |
Leaking Underground Storage Tank Corrective Action Underway |
LCAR; Basketfield reviews final revision submitted and sends letter stating inadequate. |
Former Staff |
8/6/1992 |
Update or Other Action |
SLC; (SLSW) State Lead Clenaup. Thomas: Final request completed and sent to Juneau for approval included 10 points for Site Assessment: Site History, Monitor Wells, Well Surveys, Water Elevations, Pieziometric Surface, Aquifer Test, Groundwater Analysis and Final Report. Starting date Feb.1993. |
Former Staff |
8/12/1992 |
Update or Other Action |
UPD; Reviewed by Hung. |
Former Staff |
12/18/1992 |
Update or Other Action |
RPL2; Thomas: PRP notified by letter, party of ADEC's intent to use Response Fund monies to initiate a comprensive area-wide Phase I site Assessment of the Illinois-Minnie Site. Asks to submit questions and comments. |
Former Staff |
12/28/1992 |
Update or Other Action |
SLC; (OSLP) Thomas: Corr. returned to ARRC thanking for comments. Will incorporate into ADEC final version. will keep ARRC and all parties updated on future actions. |
Former Staff |
12/28/1992 |
Update or Other Action |
SLC; (OSLP) Thomas: ARRC submitted comments and preferred Site Assessment plan for Illinois-Minnie Site. This Project was first proposed in 1990. |
Former Staff |
2/3/1993 |
Update or Other Action |
MEET; Thomas reports: Teleconference with NADO, FAP, Miller, and Gilfilian regarding proposed CAP for FY95, and ADEC's non-approval of the CAP. At meeting, all tasks were deleted from CAP except O&M and GW sampling. Deleted tasks will be funded under last years grant. Gilfilain will submit detailed design and operation plan of SVE system. |
Former Staff |
3/19/1993 |
Leaking Underground Storage Tank Corrective Action Underway |
CAPR; Basketfield reviewed Alaska Petroleum Engineering's cost estimate for 3 alternate work plans at the sites. |
Former Staff |
3/23/1993 |
Update or Other Action |
CORR; Basketfield reviewed comments on outline of proposed activities at the site as related to air sparging/vapor extraction systems. |
Former Staff |
4/5/1993 |
Leaking Underground Storage Tank Corrective Action Underway |
CAPR; Basketfield approved Alaska Petroleum Environmental Engineering air sparging/vapor extration system work plan of 4-5-93 entitled "Alaska Chevron, Inc. Corrective Action Plan, Air Sparging/Vapor Extration System." |
Former Staff |
9/13/1993 |
Site Visit |
FI; Thomas met with Owner on site to discuss proposed actions to removed LUST system during upgrade. New tank system recently installed. Also a series of AS/VES test wells were installed to determine radius of influence for upcoming treatment system. Tank removal is slated fir the next 5-10 working days. |
Former Staff |
9/13/1993 |
Leaking Underground Storage Tank Cleanup Initiated - Petroleum |
LCAU; Thomas reports: 68 yards of heavily contaminated materials were removed from the UST during closure, and theramlly remediated. A VES/Air Sparging system has been installed and should be on-line by spring 1994. |
Former Staff |
12/1/1993 |
Leaking Underground Storage Tank Corrective Action Underway |
CAPR; Thomas received and reviewed CAP for FY95. Plan lacked any meaningful detail, or tasks were in appropriate or redundent. ADEC asks for new plan. Included 7 tasks, Comments included: Use existing down gradient wells on Illinois St. rather than install new ones; Include vapor treatment in the AS/SVE; Explain what $$ to be used for in "Construction of AS/SVE"; Explain rationel for why certain MW's were selected for Monitoring; Removal of Waste oil tank not appropriate under cleanup grant; Clear up funding accounts on O&M before additional O&M $$ released. Plan denied. |
Former Staff |
2/25/1994 |
Leaking Underground Storage Tank Corrective Action Underway |
LCAR; Thomas reviewed and approved modified CAP. CAP is reduced to contain only elements necessary to install new mws and sample them quarterly. Money from existing fund will be used to complete installation and operation of SVE/AS. |
Former Staff |
3/14/1994 |
Leaking Underground Storage Tank Corrective Action Underway |
LCAR; Thomas completed review of Design Plan for Soil and Ground Water Treatment by Gilifilian. CAP approved contingent upon submitting schedule of acvtivities and noting some design suggestions regarding trenching depth, pilot testing, and off-gas. Plan should be implemented soon. |
Former Staff |
6/6/1994 |
Update or Other Action |
CORR; Wingerter sent letter informing RP of their financial liability under new ADEC cost recovery policy. State is authorized, under Section 9003(h) of the Resource Conservation and Recovery Act to take action on this LUST facility. |
Former Staff |
6/9/1994 |
Site Visit |
FI; Kalu field visit for site inspection. |
Former Staff |
8/24/1994 |
Underground Storage Tank Site Characterization or Assessment |
SA1R; Thomas reviewed SA/tank closure for the waste oil tank. Thomas determined NFA for this tank. Cleanup ongoing for other tanks. |
Former Staff |
1/13/1995 |
Update or Other Action |
UPD; SITE SUMMARY: Tanks & contam soil removed. Investigation complete. Plume does not extend much past Illinois St. AS/SVE on line and treating GW. Gilfil will provide quarterly GW sampling reports. Staff should monitor BTEX concentrations. |
Former Staff |
11/1/1995 |
Leaking Underground Storage Tank Corrective Action Underway |
LCAR; AS/SVE system being modified to enhance recovery of system |
Former Staff |
11/20/1997 |
Update or Other Action |
ADEC sends Notification of Intent to Cost Recover Letter to Current Owner: DALE MILLER |
Former Staff |
6/1/1999 |
Risk Assessment |
Gilfillian Engineering & Environmental Testing, Inc. submits Risk Assessment Report |
Former Staff |
8/11/1999 |
Conditional Closure Approved |
No Further Remedial Action Planned letter issued. Annual monitoring for BTEX required to confirm decreasing concentrations. |
Former Staff |
8/11/1999 |
Cleanup Level(s) Approved |
|
Former Staff |
9/10/1999 |
Long Term Monitoring Established |
Reduction in annual monitoring requirements from 5 wells to 1. (Adler) |
John Carnahan |
1/11/2002 |
Update or Other Action |
JBC: Reduction of monitoring of one well from annual to every two years. |
John Carnahan |
9/23/2002 |
Institutional Control Record Established |
Impacted soil and groundwater remain on-site. ADEC must be consulted prior to removal of impacted soil or groundwater. |
Janice Wiegers |
3/5/2003 |
Update or Other Action |
Per Janice Wiegers, this site is NFRAP, not closed. (Uzzell) |
Wendy Uzzell |
1/28/2004 |
Update or Other Action |
Transferred DEC staff lead from John Carnahan |
Cynthia Pring-Ham |
10/25/2007 |
Document, Report, or Work plan Review - other |
Reviewed 2007 annual GW monitoring report and request to decommission wells AKC-1, AKC-2, AKC-3 and AKC-4. The request was granted. Also approved that sampling frequency would change from every other year to once every five years. Next sampling event is scheduled for 2009. |
Former Staff |
9/22/2009 |
Document, Report, or Work plan Review - other |
Entered in 2014 as part of a file review effort. Reviewed the groundwater monitoring results for sampling performed on August 31, 2009. Monitoring well AS-5 was sampled and analyzed for GRO, BTEX, and DRO. This sample exceeded the cleanup level for GRO, but was below the cleanup levels for DRO and BTEX compounds. |
IC Unit |
12/16/2009 |
Update or Other Action |
Note: NFRAP dated 1999 requires monitoring of well GW-128. This well was replaced with AS-5 at some point. |
Tamara Cardona-Marek |
7/3/2013 |
Institutional Control Update |
Staff changed from Tamara Cardona-Marek to IC Unit. |
Kristin Thompson |
9/28/2013 |
Institutional Control Update |
DEC received and reviewed the August 2013 Well Decommissioning and Well Installation Report from Alaska Resources and Environmental Services, LLC for Kellys Firestone which is adjacent to this site and includes monitoring well GW-128. On June 8 and June 22, 2012, all wells associated with the sites were decommissioned, including 14 total wells within the construction corridor plus three additional wells that were encountered during construction. Three permanent groundwater monitoring wells (GW-128R, K-9R, and K-4R) were installed on June 27, 2013 and then later sampled on July 23, 2013. Results were non-detect in GW-128R. The next groundwater monitoring event should be summer 2014. |
Evonne Reese |
12/5/2013 |
Institutional Control Compliance Review |
IC review conducted. |
Evonne Reese |
10/8/2014 |
Document, Report, or Work plan Review - other |
DEC received and reviewed the September 2014 Groundwater Sampling report from Travis/Peterson Environmental Consulting, Inc. Monitoring well AS-5 was sampled on September 10, 2014 and analyzed for GRO, DRO, and BTEX compounds. This well was sampled the same day as the wells located nearby for the Kelly's Firestone site. Concentrations of GRO (3.63 mg/L) and benzene (6.10 ug/L) were above ADEC cleanup levels. The GRO concentration has decreased since the 2009 sampling event (from 7.92 mg/L); however, the benzene concentration has increased since 2009 (from 4.4 ug/l). Sampling should occur again in September, 2015. |
Kristin Thompson |
11/14/2014 |
Institutional Control Update |
After further review of the groundwater monitoring frequency at this site, the next monitoring event should be in September 2019. A 10/25/2007 action entered by CS staff changed the frequency from every other year to every five years. |
Evonne Reese |
5/18/2018 |
Institutional Control Compliance Review |
IC compliance review conducted. Closure/IC Details updated to more accurately reflect the conditions listed in the No Further Remedial Action Planned. Reminder system set for periodic reviews to occur every three years. |
Kristin Thompson |
10/1/2019 |
Update or Other Action |
Received the 2019 groundwater sampling report on this date. The report will be reviewed in the near future. |
Evonne Reese |
11/1/2019 |
Document, Report, or Work plan Review - other |
DEC received and reviewed the September 2019 Groundwater Sampling report from Travis/Peterson Environmental Consulting, Inc. Monitoring well AS-5 was sampled on August 28, 2019 and analyzed for GRO, DRO, and BTEX compounds. Analytical sampling results documented that concentrations for all contaminants were below the Table C cleanup values. Sampling will be performed again in five year’s time. If the 2024 results show concentrations remain below cleanup values, removal of future groundwater monitoring requirements may be considered. |
Evonne Reese |