Action Date |
Action |
Description |
DEC Staff |
3/6/1992 |
Leaking Underground Storage Tank Release Confirmed - Petroleum |
LUST Site created in CSP for source area ID 78090 ADD; |
Former Staff |
3/6/1992 |
Site Added to Database |
|
Former Staff |
6/1/1992 |
Underground Storage Tank Site Characterization or Assessment |
Site assessment |
Former Staff |
6/2/1992 |
Update or Other Action |
Kalu denied request to discharge groundwater from BX Service Station to Sewage Treatment Plant because benzene concentration is too high (7.65, 5.66 & 3.94). |
Former Staff |
6/30/1992 |
Update or Other Action |
Kalu agrees with plans of responsible party to defer concluding detailed site assessment and implementing groundwater monitoring scheme until later this summer. Installation of new tank system will begin immediately. |
Former Staff |
1/31/1993 |
Update or Other Action |
Kalu met with Brent Koenen, John Hellen and Gibler to discuss E-S workplan for site. Slug tests must be replaced with pump tests. Pump well should have 4" casing. Nearest off-base well is Moose Creek. Analytical results on borehole samples will decide disposal method. Pump well outside plume and WWD still?? |
Former Staff |
2/23/1993 |
Update or Other Action |
Peterson: Sent PRP (potential responsible party) Notification Letter to responsible party requesting update and more environmental information concerning contaminated site. Department of the Air Force responded with update of requested site information on 3-17-93. |
Former Staff |
1/15/1994 |
Leaking Underground Storage Tank Cleanup Initiated - Petroleum |
Kalu - Corrective action is underway at this site and has been ongoing since 1992. Awaiting final corrective action plan. The three 10,000-gallon leaded and unleaded gasoline tanks were replaced in 1992. |
Former Staff |
1/28/2004 |
Update or Other Action |
Transferred DEC staff lead from John Carnahan |
Cynthia Pring-Ham |
8/5/2005 |
Update or Other Action |
Staff sent an email to Eielson requesting information about this site and the current status of monitoring. |
Emily Youcha |
8/5/2005 |
Update or Other Action |
Updated GIS coordinates from TOPOZONE, NAD 83. |
Emily Youcha |
8/23/2006 |
Update or Other Action |
Staff met with Eielson to discuss setting up a compliance monitoring program at this site to monitoring the plume stability. Ground water is contaminated at the site and has not been monitored within the past 10 years. Staff is working with Eielson to set up monitoring program for compliance and LUST sites. |
Emily Youcha |
6/25/2008 |
Exposure Tracking Model Ranking |
Intitial Ranking Complete for Source Area: 78090 (Autogenerated Action) |
|
11/9/2010 |
Document, Report, or Work plan Review - other |
Received workplan for tank removal and concrete/asphalt demolition. Workplan did not include plans for delineation of historic contamination and stated plan to return all soil, including soil known to be contaminated, to the location from which it is excavated. |
Kathleen Beutel |
12/2/2010 |
Update or Other Action |
Sent request for comment letter extention for tank removal/demolition workplan. |
Kathleen Beutel |
12/22/2010 |
Update or Other Action |
This entry contains only site-specific information. An informational site has been added to the database for actions that pertain to Eielson Air Force Base in its entirety. Please see ADEC file number 107.38.006/Hazard ID 25578/Eielson AFB Basewide Information.
|
Kathleen Beutel |
4/22/2011 |
Document, Report, or Work plan Review - other |
Staff reviewed the Revised Work Plan to Demolish Base Service Station Fuel Tanks and Underground Utilities, Phase 2, Building 2375 Eielson Air Force Base, received on April 11, 2011. Soil and groundwater contamination were detected when the Service Station tanks and piping were replaced with new tanks and piping in 1992. One of the previous tanks had held leaded gasoline. Soil will be screened and segregated into clean and contaminated and stockpiles which will be sampled prior to disposal. The revised work plan incorporated analysis of soil samples for PAHs, EDB, DCA, MTBE and lead in addition to the analysis for BTEX, and AK methods listed in the Draft Work Plan. The contractor had planned to sample a floor sump in the service station for AK methods, VOCs and RCRA metals; PAHs and PCBs were added to the list of analytes. The funding programmed for this UST removal is limited, and a release investigation and corrective action plan will be necessary but may be delayed until funding for Compliance Restoration sites is available in 2012. |
Kim DeRuyter |
6/21/2011 |
Site Visit |
Contaminated sites staff conducted two site visits to observe the AAFES Service Station tank removal. The tanks that are being removed replaced three tanks that were removed in 1992. Smear zone contamination from the previous tanks was anticipated and encountered. Additional soil contamination was discovered as the result of an improperly installed vent pipe. The contract for the tank pull did not include removal of contaminated soil. Staff sent a letter response to the workplan asking that a release investigation (RI) workplan be provided prior to the tank pull so that the RI would follow directly on the tails of the tank pull, but funding for this activity has not yet been released. The site will be fenced until the release investigation and corrective action are completed. |
Kim DeRuyter |
7/7/2011 |
Underground Storage Tank Site Characterization or Assessment |
Staff issued a letter reminding Air Force personel of the UST regulations which require that a release investigation report be submitted within 45 days of confirmation of a release. During discussions with the Air Force environmental staff and their contractor it became clear that FY12 funds for the release investigation and corrective action had not yet been released. |
Kim DeRuyter |
8/4/2011 |
Update or Other Action |
Staff received a call from the contractor and a call and letter from the Air Force in response to the July 7, 2011 letter requesting a release investigation report be submitted within 45 days of the discovery of contamination at the AAFES Service Station. The contractor requested an extension, and explained the the contract did not cover an RI, but he would submit a report of his findings during the next two weeks. Eielson environmental staff stated that contracting money had not been allocated for the RI and corrective action, but they would try to find funding from other sources to complete the work; however, money may not be available until next summer. The letter stated that the Air Force understood that RI/CA were required under the UST regulations and requested an extension in order to obtain funding for the work. |
Kim DeRuyter |
9/9/2011 |
Update or Other Action |
CS staff sent a letter to USAF that acknowledged receipt of the report titled "Site Assessment and Phase 1 Release Investigation Report for UST System Closure - Former Eielson AFB AAFES Station" and noted that, as previously discussed, this report does not meet the requirements of a release investigation (RI)/corrective action per 18 AAC 78.235. As stated in a letter from the USAF dated August 04, 2011, it is anticipated that Eielson will conduct an RI as soon as funding is secured. |
Kathleen Beutel |
9/9/2011 |
Interim Removal Action Approved |
CS staff approved a work plan to remove additional blacktop and contaminated soil from the location where the tanks were excavated. Soil will be held at Eielson's containment cell until it can be evaluated and disposed of in 2012. |
Kathleen Beutel |
12/30/2011 |
Update or Other Action |
Staff sent a letter to Eielson requesting the report for the interim removal action that occurred in September/October and a schedule for the overdue release investigation. |
Kathleen Beutel |
6/13/2012 |
Site Visit |
Contaminated Sites staff conducted a site visit. Field work under the Preliminary Assessment/Site Inspection QAPP was about to begin. CS staff discussed sampling procedures with contractors and drillers. |
Kathleen Beutel |
4/10/2014 |
Document, Report, or Work plan Review - other |
2014- Draft Multiple Compliance Restoration Program Sites RI Work Plan received March 1, 2014. In 2012, 12 soil and 3 groundwater samples were collected and analyzed for DRO, RRO, GRO, VOC, SVOCs, PCBs and metals. 3 COPCs (Contaminant of potential concern) Benzene, Chromium (total), and Arsenic had levels that exceeded current MCL (Maximum contaminant level) or ADEC soil levels. GRO, DRO, Benzene, Ethylbenzene, Toluene, Xylenes (total), bis (2-Ethylhexyl) phthalate, Arsenic, Lead, and Thallium all exceed cleanup levels in groundwater. Additional field work is expected in the 2014 field season. |
Anna Iverson |
6/13/2014 |
Update or Other Action |
On April 23, 2014, the Alaska Department of Environmental Conservation and the United States Air Force reached agreement on the State-Eielson Air Force Base Petroleum Site Restoration Agreement (Two-party Agreement). This agreement was established to perform any necessary assessment, monitoring, remediation and cleanup determinations for petroleum contaminated sites at Eielson Air Force Base. This site was identified as a petroleum contaminated site requiring a response action and its cleanup will continue under Alaska regulations, following the procedures established in the agreement. |
Monte Garroutte |
8/7/2015 |
Document, Report, or Work plan Review - other |
DEC provided comments to the USAF on the draft "2014 Site Characterization Report, Various Sites, Eielson Air Force Base, Alaska dated June 2015 (the 2014 CRP SCR). The 2014 CRP SCR describes sampling activities completed at PL001(M), CS082, SS530, SS068, SS083, TU531, CS074, CG517, SS533, TU077, SS519, SS079, CS525 at Eielson Air Force Base in July, August and September of 2014. Sampling of soil and groundwater was conducted to evaluate data gaps from previous investigations; delineate the nature and extent of soil and groundwater contamination; determine the potential for co-mingling of plumes from separate sites; and to determine the need, or lack thereof, for further investigation at each site. |
Melinda Brunner |
8/24/2015 |
Site Characterization Workplan Approved |
DEC approved the "Multiple Compliance Restoration Program Sites Phase II Remedial Investigation/Feasibility Study Work Plan, Eielson Air Force Base, Alaska" dated August 2015. The work plan describes soil and groundwater sampling that will occur at CG517; fieldwork is scheduled to begin in August 2015. |
Melinda Brunner |
10/28/2016 |
Update or Other Action |
DEC acknowledged receipt of the Draft Multiple Compliance Restoration Program Sites Interim Activities Report, Eielson Air Force Base, Alaska (July, 2016). DEC did not provide comments on the Interim Report and is reserving review and comments for the completed characterization reports. |
John O'Brien |
11/14/2016 |
Document, Report, or Work plan Review - other |
DEC reviewed and provided comments on the Draft 2014 Site Characterization Report for Various Sites, Appendix F - Data Quality Assessment, Eielson Air Force Base, Alaska (June, 2015). |
John O'Brien |
12/14/2016 |
Meeting or Teleconference Held |
DEC and the Air Force discussed plans for site characterization in 2017 and reviewed data from the 2016 field effort. |
Monte Garroutte |
12/16/2016 |
Document, Report, or Work plan Review - other |
DEC completed review of the 2014 "Site Characterization Report, Various Sites - Data Quality Assessment" and resolved all comments. |
Monte Garroutte |
11/1/2017 |
Document, Report, or Work plan Review - other |
DEC reviewed and provided comments on the Draft 2016 CG517 Site Characterization Report, Eielson Air Force Base, Alaska (September, 2017). |
John O'Brien |
11/30/2017 |
Document, Report, or Work plan Review - other |
DEC completed review of the CG517 SC report |
Monte Garroutte |
8/14/2018 |
Update or Other Action |
DEC reviewed and approved "Final Decision Document, Source Area CG517, Eielson Air Force Base, Alaska," dated July 2018. The selected remedy to address contaminants of concern at CG517 is the excavation of affected soil and monitored natural attenuation for affected groundwater. |
Bri Clark |
9/18/2018 |
CERCLA Remedial Design/Remedial Action Plan Approved |
DEC approved the Final Work Plan for Removal Action and Monitoring at Source Areas CG517 and CS081, Eielson Air Force Base, Alaska, dated August 2018. |
Bri Clark |
4/26/2019 |
Cleanup Level(s) Approved |
The Alaska Department of Environmental Conservation (DEC) completed a review of the Final Decision Document Source Area CG517 Eielson Air Force Base, Alaska, dated March 2019. The document provides cleanup level changes made to the decision document (dated July 2018). All cleanup levels have been accurately revised to match the 2018 DEC cleanup levels and the document is approved. |
Dennis Shepard |
5/9/2019 |
Document, Report, or Work plan Review - other |
DEC provided comments on the Draft Remedial Action Report, Removal Action and Monitoring at Source Areas CG517 and CS081, Eielson Air Force Base, Alaska dated April 2019. The report describes the site activities that were performed to complete Remedial Action for sites CG517 and CS081. |
Bri Clark |
7/1/2019 |
Document, Report, or Work plan Review - other |
DEC provided approval for the Remedial Action Report, Removal Action and Monitoring at Source Areas CG517 and CS081, Eielson Air Force Base, Alaska, June 2019. |
Dennis Shepard |
3/14/2022 |
Document, Report, or Work plan Review - other |
DEC provided review comments for the Draft Uniform Federal Policy – Quality Assurance Project Plan (UFP-QAPP), Environmental Construction and Services, Remedial Action – Construction at Multiple sites: TU077, SS079, CG517 and ZZ088, Eielson Air Force Base, Alaska (February 2022). The UFP-QAPP details the remedial excavation services to be performed at Eielson Air Force Base (AFB) sites TU077, SS079, CG517, and ZZ088. Remedial excavation is proposed at sites TU077, SS079, and CG517 to remove up to 6,500 cubic yards (cy) of POL-contaminated soil in the vadose zone in order to eliminate the potential exposure concerns to human health and the environment. Remedial excavation is proposed at site ZZ088 to remove up to 350 cy of lead contaminated soil, as well as encapsulate the former communications building frame with a concrete cap. |
Dennis Shepard |
5/16/2022 |
Document, Report, or Work plan Review - other |
DEC provided backcheck review comments for the Draft Final Uniform Federal Policy – Quality Assurance Project Plan, Environmental Construction and Services, Remedial Action – Construction at Multiple sites: TU077, SS079, CG517 and ZZ088, Eielson Air Force Base, Alaska (April 2022). Some remaining clarification is needed for the Air Force responses. |
Dennis Shepard |
6/3/2022 |
Document, Report, or Work plan Review - other |
DEC provided approval for the Final Uniform Federal Policy – Quality Assurance Project Plan, Environmental Construction and Services, Remedial Action – Construction at Multiple sites: TU077, SS079, CG517 and ZZ088, Eielson Air Force Base, Alaska (May 2022).Remedial excavation is proposed at sites TU077, SS079, and CG517 to remove up to 6,500 cubic yards (cy) of POL-contaminated soil in the vadose zone in order to eliminate the potential exposure concerns to human health and the environment. Remedial excavation is proposed at site ZZ088 to remove up to 350 cy of lead contaminated soil, as well as encapsulate the former communications building frame with a concrete cap. |
Dennis Shepard |
5/10/2023 |
Offsite Soil or Groundwater Disposal Approved |
DEC reviewed and signed a Contaminated Soil Transport and Treatment Approval Form for disposal of 195 cubic yards of PFAS contaminated soil from the TU077 and CG517 removal actions to a RCRA facility. |
Axl LeVan |
9/18/2023 |
Document, Report, or Work plan Review - other |
DEC reviewed and provided comments on the "Eielson AFB Two-Party Sites, Periodic Review - Draft, August 2023". The document reviewed and recorded the current status of two party sites (managed by USAF and DEC) at Eielson Air Force Base. |
Axl LeVan |
12/21/2023 |
Document, Report, or Work plan Review - other |
DEC reviewed and approved "Draft-Final Periodic Review Report for Two-Party Sites at Eielson Air Force Base, Alaska, November 2023". This report documents the evaluation of the Interim Land Use Controls (Interim LUCs) for 23 two-party sites at EAFB. |
Axl LeVan |
4/16/2024 |
Document, Report, or Work plan Review - other |
DEC reviewed the "Draft 2024 Remedial Action Report for Remedial Action – Construction at Multiple Sites: CG517, SS079, TU077 and ZZ088, Eielson Air Force Base, Alaska, March 2024". The report outlines the excavation and removals performed at the four sites and the installation of monitoring wells. |
Axl LeVan |
6/21/2024 |
Document, Report, or Work plan Review - other |
DEC reviewed and provided comments on the "Periodic Review Report for Two-Party Sites, Eielson Air Force Base, Alaska, April 2024." DEC had previously approved the document, but is reviewing an updated version after substantial changes to the document. This report documents the evaluation of the Interim Land Use Controls (Interim LUCs) and remedy implementation for 17 sites at EAFB. |
Axl LeVan |
7/9/2024 |
CERCLA ROD Periodic Review |
DEC reviewed and approved the "Final Periodic Review Report for Two-Party Sites, Eielson Air Force Base, Alaska, July 2024". This report documents the evaluation of the Interim Land Use Controls (Interim LUCs) for 17 sites at EAFB. DEC approved a previous version of periodic review before substantial changes based on USAF legal review. Based on this DEC provided a new comment matrix addressing the updated version. |
Axl LeVan |
7/11/2024 |
CERCLA Removal Action Report |
DEC reviewed and approved the "Final 2024 Remedial Action Report for Remedial Action – Construction at Multiple Sites: CG517, SS079, TU077 and ZZ088, Eielson Air Force Base, Alaska, May 2024" based on response to DEC comments on the draft document. The report outlines the excavation of contaminated material at the four sites and the installation of groundwater monitoring wells for continued monitoring at the three of the sites. |
Axl LeVan |