| Action Date |
Action |
Description |
DEC Staff |
| 5/2/1990 |
Site Visit |
LFI; RPCON submitted 5/29/90 "Report On Studies Of Potential Hydrocarbon Contamination, Fuel Facility And Tractor Shed, Former Sea-Land Property, Aurora Drive Fairbanks, Alaska" by Shannon & Wilson, Inc. for Sourdough Express, Inc. |
Former Staff |
| 7/19/1992 |
Underground Storage Tank Site Characterization or Assessment |
SA1; Gibler rec'd rpt by Nortech. DRPH contamination present |
Former Staff |
| 8/24/1992 |
Update or Other Action |
NOR; Gibler sent NORL. |
Former Staff |
| 8/26/1992 |
Underground Storage Tank Site Characterization or Assessment |
SA1R; Basketfield reviewed. |
Former Staff |
| 8/26/1992 |
Update or Other Action |
CORR; Basketfield sent ltr requesting corrective action plan. |
Former Staff |
| 8/29/1992 |
Leaking Underground Storage Tank Release Confirmed - Petroleum |
LUST Site created in CSP for source area ID 76928 ADD; File# 102.26.056. |
Former Staff |
| 8/29/1992 |
Site Added to Database |
|
Former Staff |
| 9/22/1992 |
Update or Other Action |
UPD; Hung reviewed. |
Former Staff |
| 12/15/1992 |
Update or Other Action |
UPD; The 7/31/92 "Underground Storage Tank Assessment" contains error in date of field soil borings & sampling. Field work & sampling for in-place closure conducted 6/19/92 NOT 7/19/92. Diesel detected @ 12.5'bgs-410 & 390 ppm. At 2.5'bgs 970 ppm diesel detected. Rept. confirms soil & grd. water contam. by diesel above ADEC cleanup levels. Recommends RI in order to define extent soil & grd. water contam. Three USTs excavated 9/25/92. No SA1 conducted. Same RPCON removed USTs & remediated soil. DEC gave verbal approval only for design of CCBC. No prior approval given for sampling of CCBC and final disposal of treated soils. |
Former Staff |
| 12/25/1993 |
Leaking Underground Storage Tank Cleanup Initiated - Petroleum |
LCAU; RPCON submitted "Closure Report For Closed Cycle Bioremediation Cells" (CCBC) |
Former Staff |
| 1/14/1994 |
Update or Other Action |
RPL2; Peterson sent PRP-CS Database Noitification Letter to RP requesting update and more environmental information concerning the contaminated site. As of this "complete date" no response has been received. |
Former Staff |
| 3/13/1994 |
Update or Other Action |
CORR; HUNG: review for requested NFA letter indicated lack of approved CAP. Wrote letter with list of questions and request of documents in order to complete review. |
Former Staff |
| 3/23/1994 |
Leaking Underground Storage Tank Corrective Action Underway |
CAPR; RPCON submitted "Clarification Of Closure Report, ADEC Letter 3/13/94" in response to CP request. |
Former Staff |
| 3/25/1994 |
Update or Other Action |
MEET; HUNG: RPCON met w/Kalu and Hung in response to DEC 3/13/94 letter. RPCON indicated bioremediation CAP was verbally approved by Basketfield and Kalu. However, DEC was unaware nor approved of final disposal of soil by spreading around the site. |
Former Staff |
| 4/11/1994 |
Update or Other Action |
MEET; HUNG: RPCON meets request by submitting more documents for review. |
Former Staff |
| 6/6/1994 |
Update or Other Action |
CORR; Wingerter sent letter informing RP of their financial liability under new ADEC cost recovery policy. State is authorized, under Section 9003(h) of the Resource Conservation and Recovery Act to take action on this LUST facility. |
Former Staff |
| 7/6/1994 |
Underground Storage Tank Site Characterization or Assessment |
SA1R; Reviewed 5/29/90 S&W, Inc. rept. 5/2/90 findings indicated SB 2 west of pumps detected presence of soil contam. slightly above detection limits @ water table. SB 1 east of pumps detected no hydrocarbons, however, headspace gas conc. suggest some level of volatile compds. |
Former Staff |
| 7/13/1994 |
Update or Other Action |
CORR; HUNG: Informed RPCON that NFA denied as grd water quality unknown. NFA only for soils remediated. No record of MW installation(s),sampling/analyses of grd. water. Letter to follow. |
Former Staff |
| 10/17/1994 |
Update or Other Action |
CP; RPCON submits "Closure Report" an after action summary with historical attachments. |
Former Staff |
| 12/15/1994 |
Update or Other Action |
TBIO; 1,066 cu. yds. contam. soils from Carlile & Sea-Land sites were mixed and remediated ex-situ in CCBC together. Process operated 9/92-12/12/93. TPH levels 34-170 ppm from 12 sampling points. Soils spread over site(s) without prior DEC approval. |
Former Staff |
| 12/19/1994 |
Update or Other Action |
UPD; Reviewed entire file for NFA request by RPCON. NFA denied based on not addressing grd. water contam. RPCON only addressed soil contam. RP given 30 days to respond upon receipt of ltr. |
Former Staff |
| 1/6/1995 |
Leaking Underground Storage Tank Corrective Action Underway |
CAPR; RPCON submits one page written plan and schematic of where Hydropunches will be made. DEC requests more information and better schematic showing Hydropunch locations. |
Former Staff |
| 1/10/1995 |
Leaking Underground Storage Tank Corrective Action Underway |
CAPR; RPCON submits another schematic of where three Hydropunches will be made. DEC awaiting information on Hydropunch drilling depth prior to final approval. |
Former Staff |
| 2/1/1995 |
Leaking Underground Storage Tank Corrective Action Underway |
CAPR; Reviewed HydroPunch sampling plans submitted 1/6 & 1/10/95. Made requests to stagger and conduct multi-level sampling of ground water at various depths. RP agrees w/DEC revisions. DEC to be notified when HydroPunch sampling begins. DEC plans to be on-site to monitor activities. |
Former Staff |
| 7/18/1995 |
Site Visit |
FI; RP notifies DEC that RPCON plans to drill 3 well pts. 7/21/95. DEC on-site w/RPCON to monitor correct placement of well points. |
Former Staff |
| 7/26/1995 |
Site Visit |
FI; Oversee & assist RPCON in purging/sampling/field QC for BTEX method 602 from three well points drilled 7/21/95. Took photos. |
Former Staff |
| 11/20/1997 |
Update or Other Action |
ADEC sends Notification of Intent to Cost Recover Letter to Current Owner: CARLILE ENTERPRISES INC. |
Former Staff |
| 11/25/1998 |
Site Closure Approved |
|
Former Staff |
| 11/9/2000 |
Update or Other Action |
Receive letter of this date confirming the closure of monioring wells as requested by the DEC. |
John Carnahan |