Site Report: FNSB - Old Main School
Site Name: | FNSB - Old Main School |
---|---|
Address: | 804 Cushman Street; , Fairbanks, AK 99701 |
File Number: | 102.26.089 |
Hazard ID: | 24400 |
Status: | Cleanup Complete |
Staff: | No Longer Assigned, 9074655229 dec.icunit@alaska.gov |
Latitude: | 64.840130 |
Longitude: | -147.718350 |
Horizontal Datum: |
We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.
Problems/Comments
A 300-gallon gasoline underground storage tank (UST) was removed in 1993. FNSB (previous owner) will be responsible for UST cleanup according to agreement. City of Fairbanks currently owns property. Soil and groundwater impacted. Ten cubic yards contaminated soil thermally treated in 1994. Samples in 1997 show high levels of benzene (361 micrograms per liter (ug/L)) in the groundwater. Shannon & Wilson suggest that contamination may be part of Goldpanner Chevron plume (File No. 102.26.063). File review and site visit by ADEC staff conclude that the contamination detected is most likely from the former UST. Monitoring requested for summer 2007.
Action Information
Action Date | Action | Description | DEC Staff |
---|---|---|---|
9/23/1993 | Site Added to Database | Former Staff | |
9/23/1993 | Leaking Underground Storage Tank Release Confirmed - Petroleum | LUST Site created in CSP for source area ID 77827 ADD; Hung: FNSB Old Main School. File# 102.26.089. | Former Staff |
9/12/1994 | Update or Other Action | UPD; Dupee reviewed file. | Former Staff |
9/13/1994 | Update or Other Action | CORR; DUPEE: Wrote ltr. to George Feree, FNSB, regarding submittal of site assessment for Old Main School site. | Former Staff |
3/22/1996 | Leaking Underground Storage Tank Cleanup Initiated - Petroleum | LCAU; 300-gal gasoline emergency generator removed 9/22/93. Approx. 10 cubic yards contaminated soil thermally treated 10/13/94. | Former Staff |
1/28/2004 | Update or Other Action | Transferred DEC staff lead from John Carnahan | Cynthia Pring-Ham |
5/3/2006 | Update or Other Action | Updated to reflect file. | Shannon Oelkers |
5/3/2006 | Release Investigation | 1997 S&W drilled soil boring, monitoring well, and collected soil and groundwater samples as part of release investigation. FNSB submitted request for NFA. Added to DB 05/06. | Shannon Oelkers |
6/27/2006 | Site Visit | DEC staff Uzzell and Williams visited Old Main site. Inspected location of MW-1, and monitoring wells associated with Goldpanner Chevron located on Old Main site. Determined that MW-1 is in good condition and could be sampled. MW-1 is also in good position for downgradient GW sample. | Shannon Oelkers |
6/29/2006 | Update or Other Action | Meeting with Randy Johnson (FNSB) and Peter Beardsley with NORTECH. Discussed Big Dipper and Old Main sites (File no: 102.26.070 and 102.26.089). ADEC required groundwater monitoring event at MW-1 at Old Main School, testing for GRO and BTEX. Sampling will occur in summer, 2007. | Shannon Oelkers |
4/23/2007 | Exposure Tracking Model Ranking | Intitial Ranking Complete for Source Area: 77827 (Autogenerated Action) | |
10/3/2007 | Update or Other Action | Meeting with Randy Johnson- public works. Needs right of access from the City of Fairbanks to sample GW-1. Wrote letter to Borough and CC'd to City to request sampling. | Neal Everson |
6/4/2010 | Update or Other Action | Talked to Phil Streeter with the Borough. Discussed the status of this site and DEC's request to sample for sulfolane. Phil plans to conduct groundwater monitoring this summer. | Janice Wiegers |
8/25/2010 | Update or Other Action | Well monitoring report submitted. At the request of ADEC, MW-01 was sampled and tested for sulfolane. No sulfolane was detected in the sample. | Janice Wiegers |
12/1/2010 | Update or Other Action | Site management transferred to ADEC PM Will Boger. | Janice Wiegers |
5/18/2012 | Update or Other Action | Janice Wiegers and Will Boger reviwed file after request on status of monitoring needs and possible closure of site from FNSB Engineeing. Shann Jones of FNSB is preparing plan for BTEX and GRO samples from monitoring well. | Willett Boger |
6/28/2012 | Site Visit | Monitoring Well was sampled by Shannon and Wilson personnel for BTEX, GRO and Napthlene. The well is to be decommisssioned to put in a cement slab for a new AST at this location. Monitoring Well results will determine if and where a new well will be placed. | Willett Boger |
7/7/2015 | Document, Report, or Work plan Review - other | Work plan for decommissioning the monitoring well received and reviewed. | Willett Boger |
1/31/2017 | Potentially Responsible Party/State Interest Letter | A PRP letter addressing several FNSB sites was mailed and the FNSB was notified. | Michael Hooper |
2/22/2017 | Meeting or Teleconference Held | Met with Borough Division of Public Works and briefly discussed the active FNSB CSP and LUST Sites. Preparing information request letter including 22 sites. | Michael Hooper |
4/25/2017 | Update or Other Action | Sent the FNSB a letter addressing 22 active CSP/UST sites. For The Old Main School the letter notified them that the site file is being reviewed for possible closure. | Michael Hooper |
5/31/2017 | Cleanup Complete Determination Issued | After a review of the administrative file a cleanup complete determination has been issued for this site. Remaining soil and groundwater contamination is below the most stringent method 2 cleanup levels with the exception of trichloroethylene, which exceeds the groundwater cleanup level due to effects of the Gaffney Areawide Plume (ADEC File No. 102.38.084). | Michael Hooper |
Contaminant Information
Name | Level Description | Media | Comments |
---|---|---|---|
Benzene | < Table C | Groundwater | 0.740 ug/L in groundwater in 2012 |
GRO | < Table C | Groundwater | Non-detect in groundwater in 2012. |
Control Type
Type | Details |
---|---|
No ICs Required |
Requirements
Description | Details |
---|---|
Advance approval required to transport soil or groundwater off-site. | |
Movement or use of contaminated material (including on site) in a manner that results in a violation of the water quality standards is prohibited (18 AAC 70) |
No associated sites were found.