Site Report: City Electric Incorporated
Site Name: | City Electric Incorporated |
---|---|
Address: | 3540 Holt Road, Fairbanks, AK 99706 |
File Number: | 102.26.111 |
Hazard ID: | 24465 |
Status: | Cleanup Complete - Institutional Controls |
Staff: | IC Unit, 9074655229 dec.icunit@alaska.gov |
Latitude: | 64.814177 |
Longitude: | -147.731958 |
Horizontal Datum: | WGS84 |
We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.
Problems/Comments
This site involves residual contamination from a leaking used-oil underground storage tank. The extent of soil and groundwater contamination from this UST is unknown and the consultant recommends a release investigation be conducted at the site.
Action Information
Action Date | Action | Description | DEC Staff |
---|---|---|---|
12/7/1995 | Leaking Underground Storage Tank Release Confirmed - Petroleum | LUST Site created in CSP for source area ID 77741 | Former Staff |
12/7/1995 | Site Added to Database | Former Staff | |
12/30/1996 | Underground Storage Tank Site Characterization or Assessment | ADEC received City Electric, Inc. Underground Storage Tank Site Assessment Report. According to the report, four UST's were removed from the ground. UST #1 had contained used oil and it was removed in 1996. EMI, the consultant, stated that samples from the excavation had DRO up to 9,300 mg/Kg, 8,600 mg/Kg RRO and PCE of 1.6 mg/Kg. The consultant recommends that a release investigation be completed for that site. For UST's #2, #3, and #4, a test pit was dug in the former location. The tanks were supposibly removed in 1992. The highest benzene level fromthat excavation was 0.21 ppm. GRO and DRO were below ADEC cleanup levels. | Deborah Williams |
12/31/1996 | Leaking Underground Storage Tank Cleanup Initiated - Petroleum | 10/11/06 LUST Cleanup Initiated (petroleum) added to action history | Evonne Reese |
11/20/1997 | Update or Other Action | ADEC sends Notification of Intent to Cost Recover Letter to Current Owner: CITY ELECTRIC INC. | Former Staff |
3/1/2006 | Update or Other Action | Sent letter to City Electric requesting a release investigation and update for the site. | Deborah Williams |
5/9/2006 | Update or Other Action | Received a work plan for a release investigation for the soil and groundwater at the former Tank #1 location. | Deborah Williams |
7/20/2006 | Update or Other Action | ADEC received a report - Limited Phase II Site Investigation / Soil Sampling for the City Electric Property. Three soil borings were installed with two being developed as monitoring wells. The soil boring were drilled to a depth of 12' bgs with groundwater being encountered at 9' bgs. Soil boring #1 (MW-1) had DRO levels in the soil at 1,350 mg/kg, TCE was non-detect and PCE was 23 ppb. The groundwater sample (below ADEC cleanup levels) had DRO at 1.18 ppm, TCE at 1.47 ppb and PCE at 3.33 ppb. Soil boring #2 was non-detect for DRO and PCE, but had TCE at 40.4 ppb (above ADEC cleanup levels). Soil boring #3 (MW-2) was downgradient of the source area and had detection of DRO, but below ADEC cleanup levels and was non-detect for TCE and PCE. MW-2 had some detection of DRO and benzene but below ADEC cleanup levels. The on-site water well was sampled for VOCs in order to check the TCE/PCE results from a source deeper in the water table. The results were non-detect for all VOC constituents. | Deborah Williams |
3/13/2007 | Exposure Tracking Model Ranking | Initial ranking completed. | Deborah Williams |
4/25/2007 | Institutional Control Record Established | The conditions of the closure are the following: 1. A Notice of Environmental Contamination will be established on the ADEC Database identifying the nature and extent of contamination remaining on site. 2. In accordance with 18 AAC 78.274(b), the transport of soil or groundwater from this site requires ADEC review and approval prior to any transport. 3. If the contaminated soil remaining on site becomes accessible and/or is determined to pose a risk in the future, a plan to address the contamination shall be submitted to ADEC for review and approval. 4. The monitor wells shall be decommissioned in accordance with ADEC’s April 1992 guidance on Recommended Practices for Monitoring Well Design, Installation and Decommissioning. | Deborah Williams |
4/25/2007 | Conditional Closure Approved | ADEC issued a conditional closure determination for this site. | Deborah Williams |
4/20/2011 | Institutional Control Compliance Review | IC review conducted, staff changed to IC Unit, periodic review added as an IC Requirement, and tickler reminder system activated. | Evonne Reese |
5/27/2014 | Institutional Control Update | An IC reminder letter was issued to the responsible party on this date. | Kristin Thompson |
6/19/2014 | Institutional Control Periodic Reporting | Received a letter from the responsible party (RP) which confirms that land use has not changed for this site and that the monitoring wells have been decommissioned. Also the former contact person for the RP has passed away so the contact info will be updated in the Affiliates record. The reminder system has been updated to check back with the RP in two years’ time to verify that conditions remain protective. | Evonne Reese |
6/30/2016 | Institutional Control Update | An IC reminder letter was issued to the responsible party on this date. | Nathan Maxwell |
2/23/2023 | Institutional Control Compliance Review | IC compliance review conducted on this date and a reminder letter was issued. The next compliance review will be in 5 yrs. A new owner bought the property in 2021; they were sent the IC letter and informed that we are aware of the change. | Jennifer McGrath |
Contaminant Information
Name | Level Description | Media | Comments |
---|---|---|---|
DRO | Between Method 2 Migration to Groundwater and Human Health/Ingestion/Inhalation | Soil | |
Trichloroethene | Between Method 2 Migration to Groundwater and Human Health/Ingestion/Inhalation | Soil |
Control Type
Type | Details |
---|---|
CS Database Notation And Letter To Landowner/RP |
Requirements
Description | Details |
---|---|
Advance approval required to transport soil or groundwater off-site. | |
When Contaminated Soil is Accessible, Remediation Should Occur | |
Periodic Review | 4/20/11 - this requirement was added during an IC review in order to meet the 2009 closure policy. Every two years (starting July 2011) the RP shall be contacted to verify that the site conditions and uses have remained consistent. |