Action Date |
Action |
Description |
DEC Staff |
7/1/1993 |
Underground Storage Tank Site Characterization or Assessment |
SA1; Plan to remove contaminated soil to landfill for remediation. CAP to be submitted in coming months. |
Former Staff |
7/23/1993 |
Leaking Underground Storage Tank Release Confirmed - Petroleum |
LUST Site created in CSP for source area ID 78426 ADD; Diesel contaminated soil around site of two 1000 gal USTs. |
Former Staff |
7/23/1993 |
Site Added to Database |
|
Former Staff |
11/20/1997 |
Update or Other Action |
ADEC sends Notification of Intent to Cost Recover Letter to Current Owner: CITY & BOROUGH OF SITKA |
Former Staff |
10/11/1999 |
Leaking Underground Storage Tank Cleanup Initiated - Petroleum |
|
Former Staff |
10/2/2001 |
Update or Other Action |
Changed Project Manager from Paul Horwath to Bill Janes |
Cynthia Pring-Ham |
1/29/2002 |
Update or Other Action |
Project tickler update - email sent to Hugh Bevan requesting project status update |
Bill Janes |
1/30/2002 |
Update or Other Action |
Reply from Bevan: CBS removed the tanks, sampled under Smith Bayliss observation, but left contamination in place. The VCP (C-site named Former Sitka Public Works) will take care of the contamination and close
the USTs. |
Bill Janes |
4/9/2004 |
Update or Other Action |
Email from Rich Riggs, CBS, discussing possibility of CBS selling property "as is where is." |
Bruce Wanstall |
10/22/2004 |
Document, Report, or Work plan Review - other |
Cleanup Action Plan received from Carson Dorn. Several cleanup alternatives are presented but none specifically selected. A supplementary is required for approval once an option is selected. If CBS sells the property the new buyer will need to do this. |
Bruce Wanstall |
7/5/2006 |
Update or Other Action |
Project management change from Janes to Wanstall; meeting held with CDI to examine data gaps in site investigation and remedial options for Tracts I & II, UST releases at the vehicle shop, power plant, and electrical buildings need soil removal; the shop sump and transformer sites may need more assessment. |
Bruce Wanstall |
7/5/2006 |
Update or Other Action |
Project management change from Janes to Wanstall; meeting held with CDI to examine data gaps in site investigation and remedial options for Tracts I & II, the former ADOT and City Shop USTs. |
Bruce Wanstall |
11/3/2006 |
Leaking Underground Storage Tank Corrective Action Underway |
Approved this date and stored in electronic site file. Petroleum contaminated soil to be excavated and biotreated at the Granite Creek quarry. A method 3 cleanup level may be requested later. |
Bill Janes |
11/20/2006 |
Update or Other Action |
Conceptual Site Model received from consultant. Saved in pdf format in email this date in Outlook public folders. |
Bill Janes |
1/9/2007 |
Exposure Tracking Model Ranking |
ETM: Baseline Ranking |
Jill Taylor |
3/9/2007 |
Update or Other Action |
Amended cleanup plan received for second phase of cleanup. |
Bill Janes |
3/9/2007 |
Cleanup Level(s) Approved |
Method 3 cleanup levels approved as follows:
GRO - 1,400 ppm
DRO - 3,800 ppm
RRO - 12,500 ppm |
Bill Janes |
7/11/2007 |
Update or Other Action |
Final cleanup report received. On file in the associated 38 file for the property called Sitka Former Public Works |
Bill Janes |
7/12/2007 |
Cleanup Level(s) Approved |
Correction made to RRO cleanup level - from 12,500 ppm to 8,300 ppm based on July 2007 final cleanup report |
Bill Janes |
7/19/2007 |
Exposure Tracking Model Ranking |
Updated ranking - all exposure pathways deminimis exposure or incomplete. |
Bill Janes |
8/1/2007 |
Site Visit |
Site Visit - All structures have been removed and the site has been leveled. Runoff water from the hillside is diverted around the property in a ditch where it eventually enters the storm drain system. It discharges through a nearby small wetland and then into marine waters.
The biocell has been constructed at the Granite Creek Quarry. No leachate was observed; the soil was last tilled at the end of June. No odors or visible signs of contamination present. |
Bill Janes |
1/14/2008 |
Update or Other Action |
Cleanup complete determination issued this date with site-specific method 3 migration to groundwater cleanup levels for DRO. Site will remain in "open" status until the Granite Creek quarry bioremedation stockpile soil reaches applicable cleanup levels. Pre-approval issued to use the soil for cover material at the nearby waste water sludge disposal area once cleanup levels have been met. |
Bill Janes |
5/8/2008 |
Update or Other Action |
DRO/RRO sampling results for the Granite Creek stockpile received. FIve of the ten samples exceed method 2 but all samples are below the approved method 3 cleanup level. City given the option of further treatment and re-sampling or using the material as cover for the nearby biosolids disposal site. |
Bill Janes |
10/15/2008 |
Cleanup Complete Determination Issued |
Granite Creek soil stockpile concentrations now meet method 2 migration to groundwater cleanup levels. |
Bill Janes |