Skip to content Skip to content

Site Report: Chevron - #90932

Site Name: Chevron - #90932
Address: 2200 W. Dimond Blvd., Anchorage, AK 99507
File Number: 2100.26.064
Hazard ID: 24583
Status: Active
Staff: Rebekah Reams, 9074512144 rebekah.reams@alaska.gov
Latitude: 61.136921
Longitude: -149.921101
Horizontal Datum:NAD83

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

In 1996 Gasoline contamination found during the removal of three 12,000 gallon gasoline tanks and their associated and piping at the tanks, piping, and dispensers. The new piping was placed back in the same location except for the potions that ran to the new replacement tanks location on the western portion of the property. 80 cubic yards of contaminated soil was removed and thermally treated at ASR. In 1996 there was contamination left in place at the tank excavation (up to 3.93 mg/kg benzene and 52.8 mg/kg GRO at 16 feet bgs), at the northwest, northeast, and southeast dispensers (up to 10.2 mg/kg benzene and 4,380 mg/kg GRO at 2 to 4 feet bgs at the SE dispenser). Also contamination at the SW product piping (1.48 mg/kg benzene and 7.68 mg/kg GRO at 4 feet bgs). In 1998 five soil borings were sampled and soil contamination of 0.1 mg/kg benzene and non-detect GRO was identified at a depth of 5 feet at soil boring B-1 (located about 10 feet south and upgradient of the southeast dispenser island). Three of the soil borings were completed as monitoring wells (MW-1, MW-2, and MW-3). Three soil samples (MW-3 at the soil/water interface and the 1 cy drill cutting samples SP-1 and SP-2) were analyzed for VOCs and PAHs and they were non-detect. In 2002 an additional monitoring well (MW-4) was installed to help define the extent of the groundwater contamination. In 2006 four soil borings were sampled (the soil samples collected were non-detect for GRO and MTBE, and had 0.035 mg/kg benzene on the upgradient side of the NE dispenser island) and two of the soil borings were completed as monitoring wells (MW-5 and MW-6). In 2010 three replacement monitoring wells (MW-3R, MW-5R, and MW-6R) were installed, but no soil samples were collected. An additional downgradient monitoring well (MW-7) was installed in 2011. In 2011 monitoring well MW-7 was installed, soil samples collected from this boring were analyzed for GRO, DRO, and benzene. All results were below cleanup levels or non-detect. In 2019 all site monitoring wells were decommissioned, groundwater samples indicate no analytes have exceeded cleanup levels since 2012 second semi-annual sampling event. Contamination remains near the existing active UST system dispensers and piping, and the former tanks location. Additional soil investigation was attempted to assess contaminant attenuation at the site; however, could not be completed due to the presence of piping and utilities. Depth to groundwater is 2 to 4 feet below ground surface and flows to the northwest.

Action Information

Action Date Action Description DEC Staff
8/2/1996 Leaking Underground Storage Tank Release Confirmed - Petroleum LUST Site created in CSP for source area ID 78027 Former Staff
8/2/1996 Site Added to Database Former Staff
8/3/1996 Underground Storage Tank Site Characterization or Assessment Gasoline contamination found during tank and piping removal in 1996. The new piping was placed back in the same locations. The replacement tanks were placed at a new location on the west side of the property. 80 cubic yards of contaminated soil was removed and thermally treated at ASR. Contamination was left in place at the tank excavation (up to 3.93 mg/kg benzene and 52.8 mg/kg GRO at 16 feet bgs), at the northwest, northeast, and southeast dispensers (up to 10.2 mg/kg benzene and 4,380 mg/kg GRO at 2 to 4 feet bgs at the SE dispenser), and at the SW product piping (1.48 mg/kg benzene and 7.68 mg/kg GRO at 4 feet bgs). Robert Weimer
11/20/1997 Update or Other Action ADEC sends Notification of Intent to Cost Recover Letter to Current Owner: CHEVRON PRODUCTS COMPANY, INC/PERMITS DESK Former Staff
3/25/1998 Leaking Underground Storage Tank Cleanup Initiated - Petroleum Former Staff
9/25/1998 Document, Report, or Work plan Review - other Monitoring wells installed to help define the extent of the groundwater contamination at the site. Soil contamination of 0.1 mg/kg benzene and non-detect GRO was identified at a depth of 5 feet at soil boring B-1 (located about 10 feet south and upgradient of the southeast dispenser island). Monitoring wells were installed in 1998 and 2002 to help define the extent of the groundwater contamination. Two soil samples (MW-3 at the soil/water interface and stockpile SP-1) were analyzed for VOCs and PAHs and they were non-detect. Robert Weimer
12/22/2000 Update or Other Action SECOR (R. Hoffmore) going to request NFA. I sent an email that site characterization incomplete requested downgradient monitoring wells be installed. Linda Nuechterlein
1/30/2001 Meeting or Teleconference Held Annual meeting with Chevron reps to review Alaska sites and set goals for 2001. Linda Nuechterlein
5/25/2001 Document, Report, or Work plan Review - other ADEC letter approving the installation of 2 additional monitoring wells to help define the lateral extent of the groundwater contamination at the site. The letter notes that as discussed in the January 2001 meeting, prior to closure of the site additional (beyond what is proposed in this workplan) soil and groundwater samples would be required close to the release points. Robert Weimer
9/18/2002 Document, Report, or Work plan Review - other Only one additional monitoring well was installed (instead of two in the workplan) about 50 feet downgradient from the northwest dispenser island and sampled. A monitoring well was not placed near the former tank location because of the proximity of the active fuel piping. The level and extent of the groundwater contamination near the former tanks and the eastern dispenser islands is still not known. The groundwater downgradient of the east dispenser islands may not be captured by the single additional monitoring well. Robert Weimer
8/25/2004 Document, Report, or Work plan Review - other June 1, 2004 groundwater sampling report. Up to 0.71 mg/l GRO, 31 ug/l benzene, and 63 ug/l MTBE in the groundwater. 3 of the 4 monitoring wells are showing an increase in contaminant concentrations. Robert Weimer
12/2/2004 Document, Report, or Work plan Review - other September 24, 2004 groundwater sampling report. Up to 0.16 mg/l GRO, 3 ug/l benzene, and 46 ug/l MTBE in the groundwater. 3 of the 4 monitoring wells are showing a decrease in contaminant concentrations. Robert Weimer
7/6/2005 Document, Report, or Work plan Review - other May 9, 2005 groundwater sampling report. Up to 0.26 mg/l GRO, 1 ug/l benzene, and 20 ug/l MTBE in the groundwater. 3 of the 4 monitoring wells are showing a decrease in contaminant concentrations. Groundwater flows to the northwest. Robert Weimer
11/22/2005 Document, Report, or Work plan Review - other September 22, 2005 groundwater sampling report. Up to ND mg/l GRO, ND ug/l benzene, and 49 ug/l MTBE in the groundwater. MTBE contaminant concentrations are increasing. Groundwater flows to the northwest. Depth to groundwater is 1.8 to 4.1 feet below ground surface. Robert Weimer
6/28/2006 Update or Other Action ADEC requests confirmation soil samples at the northwest corner of the former tank excavation, the northwest dispenser island, the north east dispenser island and the southeast dispenser island. Also requested a monitoring well near the northeast dispenser island and the former tank excavation. Robert Weimer
7/14/2006 Document, Report, or Work plan Review - other ADEC approves work plan to install 2 additional monitoring wells and 2 other soil borings to assess the site. Robert Weimer
7/20/2006 Document, Report, or Work plan Review - other May 8, 2006 groundwater sampling event. Up to 3 ug/l MTBE and non-detect (<0.10 mg/l) GRO and (<0.5 ug/l) benzene in the groundwater. MTBE contaminant concentrations have decreased from the pervious monitoring event, the levels appear to be lower in the spring and higher in the fall when the groundwater drops slightly. Groundwater flows to the northwest. Depth to groundwater is 1.8 to 4.3 feet below ground surface. Two additional monitoring wells are to be installed in July 2006 to help determine groundwater contaminant concentrations closer to the release points. Robert Weimer
11/2/2006 Meeting or Teleconference Held Met with RP's consultant to discuss Conditional Closure request. Need to sample the two new monitoring wells a minimum of 4 quarters to establish trends. Other monitoring wells may be reduced. Robert Weimer
1/19/2007 Meeting or Teleconference Held Discussed site with RP's consultant. They will be submitting the results of the fall 2006 groundwater monitoring event soon. After two more groundwater events in the new monitoring wells we can evaluated the site. We discussed that some of the confirmation soil sampling locations may have to wait for such time that the UST system is removed. Robert Weimer
4/6/2007 Document, Report, or Work plan Review - other August 22, 2006 groundwater sampling event. Up to 0.13 mg/l GRO, 0.6 ug/l benzene, and 31 ug/l MTBE in the groundwater. MTBE contamination levels have increased from the pervious monitoring event, the levels appear to be lower in the spring and higher in the fall when the groundwater drops slightly. Groundwater flows to the northwest. Depth to groundwater is 1.45 to 4.10 feet below ground surface. Two additional monitoring wells were installed in August 2006 to help determine groundwater contaminant concentrations closer to the release points. Results in monitoring wells MW-1, MW-3, and MW-4 may be biased low due to top of screened interval being submerged. Robert Weimer
3/3/2008 Document, Report, or Work plan Review - other May 16, 2007 groundwater sampling event. Up to 0.20 mg/l GRO, 4 ug/l benzene, and 21 ug/l MTBE in the groundwater. Benzene contaminant concentrations have increased from the pervious monitoring event. Groundwater flows to the northwest. Depth to groundwater is 1.50 to 4.38 feet below ground surface. Results in monitoring wells MW-1, MW-3, MW-4, MW-5, and MW-6 may be biased low due to top of screened interval being submerged. Robert Weimer
3/4/2008 Document, Report, or Work plan Review - other September 25, 2007 groundwater sampling event. Up to 92 ug/l MTBE and non-detect GRO and benzene in the groundwater. MTBE contaminant concentrations have increased from the pervious monitoring event. Groundwater flows to the northwest. Depth to groundwater is 1.45 to 4.39 feet below ground surface. Results in monitoring wells MW-1, MW-3, MW-4, MW-5, and MW-6 may be biased low due to top of screened interval being submerged. Robert Weimer
5/12/2008 Exposure Tracking Model Ranking Site ranked on the new Exposure Tracking Model (ETM). The ETM is a new site ranking system that looks at, based on available data, the potential exposure pathways for the contamination remaining at the site. Robert Weimer
9/17/2008 Document, Report, or Work plan Review - other May 16, 2008 groundwater sampling event. Up to 0.50 mg/l GRO, 1 ug/l benzene, and 56 ug/l MTBE in the groundwater. GRO contaminant concentrations have increased from the pervious monitoring event. Groundwater flows to the northwest. Depth to groundwater is 1.32 to 4.23 feet below ground surface. Results in monitoring wells MW-1, MW-3, MW-4, MW-5, and MW-6 may be biased low due to top of screened interval being submerged. Robert Weimer
2/25/2009 Meeting or Teleconference Held Meeting with Chevron and their consultants. They are to conduct an evaluation of indoor air at this site. Site monitoring is to continue. Chevron's current consultant (CRA) is to evaluate data gaps and submerged well screen data. They are to provide a plan to conduct confirmation soil sampling. Robert Weimer
2/26/2009 Document, Report, or Work plan Review - other September 12, 2008 groundwater sampling event. Up to 1 ug/l benzene, 52 ug/l MTBE and non-detect GRO in the groundwater. contaminant concentrations have decreased from the pervious monitoring event. Groundwater flows to the northwest. Depth to groundwater is 1.54 to 3.66 feet below ground surface. Missing QA/QC data. Results in monitoring wells MW-1, MW-3, MW-4, MW-5, and MW-6 may be biased low due to top of screened interval being submerged. Robert Weimer
4/28/2009 Update or Other Action ADEC approves request for suspending MTBE analysis in monitoring wells MW-1, MW-2, MW-3, and MW-4. MTBE analysis is to continue in monitoring wells MW-5 and MW-6. Robert Weimer
6/4/2009 Meeting or Teleconference Held Teleconference with RPs consultant (CRA). They will subit a request for thermal treatment of old drums of drill cuttings currently stored at the site. Robert Weimer
6/8/2009 Offsite Soil or Groundwater Disposal Approved Approve request for thermal treatment of 4 drums of contaminated drill cuttings from 2006 site assessment. Robert Weimer
6/22/2009 Site Visit At the request of the project manager, Robert Weimer, the quality assurance officer conducted a site visit on June 19, 2009 to oversee sampling activities by CRA consultants. While onsite six monitoring wells were sampled for GRO/BTEX. Additionally, two wells were also sampled for MTBE and GRO/BTEX. No major deviations from standard sampling practices were noted. A copy of the QA field report has been placed in the field file and in the QA file. Brenton Porter
8/20/2009 Document, Report, or Work plan Review - other Approve request to suspend groundwater monitoring in monitoring wells MW-1 and MW-2. Robert Weimer
10/15/2009 Document, Report, or Work plan Review - other June 19, 2009 groundwater sampling event. Up to 1.1 ug/l benzene, 55 ug/l MTBE, and non-detect GRO in the groundwater. Contamination concentrations are simular to the pervious monitoring event. Groundwater flows to the northwest. Depth to groundwater is 2.03 to 4.54 feet below ground surface. Missing QA/QC data. Results in monitoring wells MW-1, MW-3, MW-4, MW-5, and MW-6 may be biased low due to top of screened interval being submerged. Robert Weimer
10/26/2009 Document, Report, or Work plan Review - other ADEC approves request for treatment of contaminated purge water. Robert Weimer
2/18/2010 Document, Report, or Work plan Review - other September 7, 2009 groundwater sampling event. Up to 1.1 ug/l benzene, 78 ug/l MTBE , and non-detect GRO in the groundwater. Contamination concentrations increased in 2 of the 4 monitoring wells sampled. Groundwater flows to the northwest. Depth to groundwater is 1.49 to 4.36 feet below ground surface. Results in monitoring wells MW-3, MW-4, MW-5, and MW-6 may be biased low due to top of screened interval being submerged. Robert Weimer
3/11/2010 Meeting or Teleconference Held Meeting with Chevron and their consultants on 3/10/10. Chevron to submit a workplan to install replacement monitoring wells for MW5 and MW6, with PAH soil sampling. Monitoring wells MW3 & MW4 may need to be replaced if contamination found at the replacement MW5 or MW6. We discussed that groundwater samples for volatiles should not be collected with bailers or peristaltic pumps due to the loss of volatiles, Chevron is to provide a workplan specifying how groundwater samples will be collected in the future. Robert Weimer
4/6/2010 Document, Report, or Work plan Review - other DEC review of Site Vapor Intrusion Evaluation report for this site. The report concluded that this site does not have a potential for vapor intrusion based on the remaining concentrations in the soil and groundwater at this site. The vapor intrusion evaluation will be revised as necessary when new site data is aquired. Robert Weimer
5/28/2010 Document, Report, or Work plan Review - other Approve request to suspend MTBE sampling in monitoring wells MW-5 and MW-6. Robert Weimer
6/3/2010 Document, Report, or Work plan Review - other Review of June 2, 2010 Monitoring Well Installation Workplan. Provided comments to Chevron's consultant. They will submit a revised work plan soon. DEC requested that the replacement monitoring well MW6 be sampled for PAH in addition to GRO and BTEX during its first groundwater monitoring event. Robert Weimer
6/3/2010 Document, Report, or Work plan Review - other Reviewed June 3, 2010 Monitoring Well Installation Workplan. The workplan was updated based on the comments provided to Chevron's consultant. The workplan calls for decommissioning and replacing 3 monitoring wells (MW-3, MW-5, and MW-6) which had submerged well screens. These monitoring wells will sampled in the summer and fall of 2010, then abandoned prior to winter. Robert Weimer
10/5/2010 Offsite Soil or Groundwater Disposal Approved ADEC approves request for treatment of one drum of monitoring well purge water. Robert Weimer
11/1/2010 Offsite Soil or Groundwater Disposal Approved ADEC approves request for thermal treatment of three drums of contaminated dril cuttings. Robert Weimer
3/9/2011 Document, Report, or Work plan Review - other June 22, 2010 groundwater sampling event. Up to 16 mg/l GRO, and 4,400 ug/l benzene in the groundwater. Contamination concentrations increased in 2 of the 4 monitoring wells sampled. Monitoring well MW-6R (near the former tanks) also had PAH analysis with 15 PAH compounds detected including 0.014 ug/l Benzo(a)pyrene, 0.014 ug/l Dibenz(a,h)anthracene, 0.061 ug/l Fluoranthene, 0.18 ug/l Naphthalene, 0.28 ug/l Phenanthene, and 0.11 ug/l Pyrene. Groundwater flows to the northwest. Depth to groundwater is 2.19 to 4.43 feet below ground surface. Replacement monitoring wells MW-3R, MW-5R, and MW-6R have been installed to get better groundwater quality data. The replacement monitoring well MW-3R has much higher contamination concentrations than the previous monitoring well that had a submerged well screen. Robert Weimer
3/10/2011 Document, Report, or Work plan Review - other August 4, 2010 groundwater sampling event. Up to 6.4 mg/l GRO, and 680 ug/l benzene in the groundwater. Contamination concentrations increased in 0 of the 4 monitoring wells sampled. Groundwater flows to the northwest. Depth to groundwater is 1.42 to 4.20 feet below ground surface. Replacement monitoring wells MW-3R, MW-5R, and MW-6R have been installed to get better groundwater quality data. Robert Weimer
4/19/2011 Update or Other Action Call from DOWL regarding the potential impact of this site on the property on the northwest corner of the intersection. They may recommend that a monitoring well be installed on that property near the intersection. They plan to forward any results to ADEC. Robert Weimer
7/19/2011 Document, Report, or Work plan Review - other ADEC conditionally approves the work plan to install and sample one monitoring well down gradient of monitoring well MW-3R. The work plan is approved on the condition that the monitoring well be placed, as utilities allow, to the northwest of monitoring well MW-3R and that at least one analytical soil sample be collected at the soil/water interface. Robert Weimer
7/19/2011 Document, Report, or Work plan Review - other On June 15, 2010 monitoring wells MW-3, MW-5, and MW-6 were decommissioned and replacement monitoring wells MW-3R, MW-5R, and MW-6R were installed to get better groundwater quality data with well screens from 1 to 14 feet below ground surface. Robert Weimer
7/21/2011 Conceptual Site Model Submitted Conceptual site model identified completed direct contact, ingestion, and inhalation pathways from the shallow benzene and GRO contaminated soil and groundwater. Robert Weimer
8/16/2011 Offsite Soil or Groundwater Disposal Approved ADEC approves request to purge monitoring wells prior to sampling. Purging and sampling will be conducted using a bladder pump. Robert Weimer
10/24/2011 Offsite Soil or Groundwater Disposal Approved ADEC approves treatment of contaminated purge water. Robert Weimer
10/26/2011 Offsite Soil or Groundwater Disposal Approved ADEC approves request for treatment of one drum of monitoring well purge water. Robert Weimer
11/4/2011 Offsite Soil or Groundwater Disposal Approved ADEC approves request for thermal treatment of 1 drum of contaminated soil. The soil was generated during the August 2011 subsurface investigation. Robert Weimer
2/27/2012 Document, Report, or Work plan Review - other May 21, 2011 groundwater sampling event. Up to 26.0 mg/l GRO, and 1,700 ug/l benzene in the groundwater. These are the highest concentrations ever found in the groundwater at this site. Contamination concentrations increased in 3 of the 4 monitoring wells sampled. Groundwater flows to the northwest. Depth to groundwater is 1.47 to 4.41 feet below ground surface. Replacement monitoring wells MW-3R, MW-5R, and MW-6R have been installed to get better groundwater quality data. Robert Weimer
3/7/2012 Meeting or Teleconference Held Meeting with Chevron and their consultants on 2/28/12. Chevron is to decommission damaged monitoring well MW-2. They are to continue semi-annual groundwater monitoring. If monitoring well MW-7 remains over cleanup levels they may need to install additional monitoring wells to define the extent of the groundwater contamination. Robert Weimer
5/17/2012 Document, Report, or Work plan Review - other ADEC approved work plan for decommissioning damaged monitoring well MW-2. Robert Weimer
8/17/2012 Offsite Soil or Groundwater Disposal Approved ADEC approves request for offsite treatment of two drums of monitoring well purge water. Robert Weimer
9/25/2012 Update or Other Action Call from DOT. When working on the northern most driveway into the Chevron property on the east side of Victor Road they encountered a seep of shallow groundwater about 30 feet west of monitoring well MW-3R. They suspect that it is from a leaking water line and they are having the water tested for chlorine and floride. Robert Weimer
10/30/2012 Document, Report, or Work plan Review - other On August 22, 2011 an additional monitoring well (MW-7) was installed and sampled to help assess the extent of the contamination downgradient of monitoring well MW-3R. Monitoring well MW-7 was screened from 1 to 11 feet below ground surface (bgs). A silt/clay layer was encountered at 5 feet bgs and it extended to the base of the monitoring well. A soil sample was collected at 1 foot bgs at the soil/water interface, it had 5.8 mg/kg DRO, <0.6 mg/kg GRO, and <0.0064 mg/kg benzene. Robert Weimer
1/8/2013 Document, Report, or Work plan Review - other August 23, 2011 groundwater sampling event. Up to 5.0 mg/l GRO, and 890 ug/l benzene in the groundwater. Contamination concentrations increased in 1 of the 4 monitoring wells sampled. Groundwater flows to the northwest. Depth to groundwater is 0.60 to 4.32 feet below ground surface. Replacement monitoring wells MW-3R, MW-5R, and MW-6R have been installed to get better groundwater quality data. Robert Weimer
1/8/2013 Document, Report, or Work plan Review - other May 24, 2012 groundwater sampling event. Up to 0.2 mg/l GRO, and 30 ug/l benzene in the groundwater. Contamination concentrations increased in 1 of the 3 monitoring wells sampled. Groundwater flows to the northwest. Depth to groundwater is 0.90 to 4.38 feet below ground surface. Replacement monitoring wells MW-3R, MW-5R, and MW-6R have been installed to get better groundwater quality data. Samples were collected using a bladder pump after the monitoring wells were purged. Robert Weimer
2/15/2013 Document, Report, or Work plan Review - other August 1, 2012 groundwater sampling event. Up to 0.61 mg/l GRO, and 48 ug/l benzene in the groundwater. Contamination concentrations increased in 2 of the 5 monitoring wells sampled. Groundwater flows to the northwest. Depth to groundwater is 0.63 to 4.2 feet below ground surface. Replacement monitoring wells MW-3R, MW-5R, and MW-6R have been installed to get better groundwater quality data. Samples were collected using a bladder pump after the monitoring wells were purged. Robert Weimer
2/15/2013 Document, Report, or Work plan Review - other On May 23, 2012 monitoring well MW-2 was decommissioned due to a damaged well casing. Robert Weimer
2/27/2013 Meeting or Teleconference Held Meeting with Chevron and their consultants on 2/26/13. Chevron proposes to continue to conduct semi-annual groundwater monitoring to monitor for natural attenuation and trends. We discussed that all semi-annual monitoring events need to be at least 120 days apart. Robert Weimer
3/26/2013 Document, Report, or Work plan Review - other DEC conditionally approves the use of a portable activated carbon (gac) filter system for this site to treat water generated during groundwater monitoring. The storage of water at the site or the secure storage area at 1441 C Street is also approved. Robert Weimer
4/24/2013 Update or Other Action DEC approved request to suspend until further notice the sampling of monitoring wells MW-5R and MW-6R. Robert Weimer
1/23/2014 Document, Report, or Work plan Review - other May 1, 2013 groundwater sampling event. Up to 0.045 mg/l GRO, and 0.18 ug/l benzene in the groundwater. The previous most contaminated monitoring well (MW-3R) was not sampled this monitoring event because it was plugged with ice. Contamination concentrations increased in 1 of the 2 monitoring wells sampled. Groundwater flows to the northwest. Depth to groundwater is 1.55 to 6.89 feet below ground surface. Replacement monitoring wells MW-3R, MW-5R, and MW-6R have been installed to get better groundwater quality data. Samples were collected by both using no purge with hydrasleeves, and using a bladder pump after the monitoring wells were purged. The sample interval for the bladder pump was not document in field notes. The hydrasleeve samples were collected from the interval 1 to 4 feet below groundwater surface. Robert Weimer
2/18/2014 Document, Report, or Work plan Review - other September 17, 2013 groundwater sampling event. Up to 0.072 mg/l GRO, and 3.6 ug/l benzene in the groundwater. Contamination concentrations increased in 2 of the 3 monitoring wells sampled. Groundwater flows to the northwest. Depth to groundwater was 1.41 to 4.09 feet below ground surface. Replacement monitoring wells MW-3R, MW-5R, and MW-6R have been installed to get better groundwater quality data. Samples were collected from the top 3 feet of the water column in each monitoring by no purge using hydrasleeves. Robert Weimer
2/27/2014 Meeting or Teleconference Held Meeting with Chevron and their consultants on 2/27/2014. Because of problems with last year’s purge/no-purge sampling the next groundwater sampling event they will sample both using no purge and purge help evaluate that the past no purge results were providing comparable data or they will switch to no purge for future sampling events. We discussed that the groundwater samples needs to be collected as close as possible to the soil/water interface, with the pump intake within a foot of the soil/water interface at the time of the sampling. After reviewing the results of the May 2014 groundwater sampling event the consultant may be requesting a reduction in ground water monitoring or closure with IC's. The consultant will make sure that their site reports are complete in accordance with DEC’s 9/23/2009 Site Characterization Work Plan and Reporting Guidance for Investigation of Contaminated Sites. Robert Weimer
7/29/2014 Update or Other Action Based on the results of the 6/6/2014 purge/no purge sampling the DEC has no objection to doing no purge sampling at this site. They plan to continue to conduct purge sampling to demonstrate trends for site closure. Robert Weimer
10/2/2014 Document, Report, or Work plan Review - other DEC provides review comments on the September 2014 confirmation soil boring work plan. The work plan proposes to collect soil samples at only two locations (near the northeast dispenser and the southeast dispenser). The September 2014 work plan is not approved. There are other areas of soil contamination at the site that need confirmation samples. The work plan needs to include copies of tables for all site soil and groundwater sampling results. Because BTEX, GRO, and MTBE contamination has been identified at the site confirmation soil samples need to be analyzed for those contaminants. Confirmation soil samples need to be collected from non-backfill soil at the same depth that they were had identified previously and the soil/water interface. A third sample depth will need an analytical sample if another depth in that boring appears to be more contaminated based on field readings/observations. Complete copies of field notes need to be included in the report. More detail needs to be provide on how the soil samples are to be collected (hand driven split spoon ahead of the auger bit?) and field readings are to be taken. Robert Weimer
10/22/2014 Document, Report, or Work plan Review - other DEC provides review comments on the October 2014 revised confirmation soil boring work plan. The work plan proposes to collect soil samples at six locations. Because it is currently an active gas station they may need to wait and collect the dispenser confirmation soil samples (five locations) when the current UST system is updated or removed. They will provide an updated work plan for review and approval to cover the collection of confirmation samples at four locations (MW3R/MW7, P4, T5, and sidewall near T7/8) outside of the current UST system. We discussed that collecting volatile samples from a hand auger is not approved due to the loss of volatiles. This confirmation soil sampling work was not conducted. Robert Weimer
10/28/2014 Update or Other Action DEC has no objection to suspending groundwater sampling in the 1st quarter, but there needs groundwater monitoring for the other 3 quarters to establish trends. Based on the results of the soil sampling DEC can evaluate what long term groundwater monitoring would be required for this site. Robert Weimer
4/6/2015 Document, Report, or Work plan Review - other June 6, 2014 groundwater sampling event. Up to 0.051 mg/l GRO, and 2.4 ug/l benzene in the groundwater. Contamination concentrations increased in 1 of the 3 monitoring wells sampled. Groundwater flows to the northwest. Depth to groundwater was 1.75 to 4.31 feet below ground surface. Sampling was conducted by both no-purge with Hydrasleeves and purge with a bladder pump. The bladder pump results from two of the monitoring wells (MW-7 and MW-3R) are considered biased low because the pump intake was not at the top of the water column as required. The pump intake was at 2.4 to 2.51 below the soil/water interface during sampling of those wells. Robert Weimer
4/15/2015 Document, Report, or Work plan Review - other July 31, 2014 groundwater sampling event. Up to 0.05 mg/l GRO, and 1.1 ug/l benzene in the groundwater. Contamination concentrations increased in 0 of the 3 monitoring wells sampled. Groundwater flows to the northwest. Depth to groundwater was 1.57 to 4.04 feet below ground surface. Samples were collected from the top 1 foot of the water column in each monitoring by purge sampling using a bladder pump. Robert Weimer
4/20/2015 Document, Report, or Work plan Review - other November 10, 2014 groundwater sampling event. Up to 0.05 mg/l GRO, and 0.32 ug/l benzene in the groundwater. Contamination concentrations increased in 0 of the 3 monitoring wells sampled. Groundwater flows to the northwest. Depth to groundwater was 1.85 to 4.45 feet below ground surface. Replacement monitoring wells MW-3R, MW-5R, and MW-6R have been installed to get better groundwater quality data. Samples were collected from the top 1 foot of the water column in each monitoring by purge sampling using a bladder pump. Robert Weimer
4/21/2015 Update or Other Action DEC approves reducing monitoring to an annual basis for GRO and BTEX of monitoring wells MW-3R, MW-4, and MW-7 to be conducted in the May/June/July of each year. DEC has no objection to decommissioning monitoring wells MW-1, MW-5R, and MW-6R in accordance with the DEC September 2013 Monitoring Well Guidance. Robert Weimer
2/1/2016 Document, Report, or Work plan Review - other May 30, 2015 groundwater sampling event. Up to 0.059 mg/l GRO and 1.0 ug/l benzene in the groundwater. Contamination concentrations increased in 2 of the 3 monitoring wells sampled. Groundwater flows to the northwest. Depth to groundwater was 1.94 to 4.32 feet below ground surface. Samples were collected by purge sampling using a bladder pump. The results for monitoring wells MW-4 and MW-7 are considered biased low because they did not document in the field notes that the pump intake depth was within the top foot of the water column at the time of sampling as specified in the sampling plan. Robert Weimer
9/28/2016 Document, Report, or Work plan Review - other DEC approves work plan for decommissioning monitoring wells MW-1, MW-5R, and MW-6R. Robert Weimer
2/15/2017 Document, Report, or Work plan Review - other July 5, 2016 groundwater sampling event. Up to 0.026 mg/l GRO and non-detect benzene in the groundwater. Contamination concentrations increased in 0 of the 3 monitoring wells sampled. Groundwater flows to the northwest. Depth to groundwater was 1.20 to 4.31 feet below ground surface. Samples were collected by purge sampling using a bladder pump. The pump intake depth was within the top foot of the water column at the time of sampling as specified in the sampling plan. Robert Weimer
11/27/2017 Document, Report, or Work plan Review - other July 11, 2017 groundwater sampling event. Up to 0.015 mg/l GRO and non-detect benzene in the groundwater. Contamination concentrations increased in 0 of the 3 monitoring wells sampled. Groundwater flows to the northwest. Depth to groundwater was 1.75 to 3.88 feet below ground surface. Samples were collected by purge sampling using a bladder pump. The pump intake depth was within the top foot of the water column at the time of sampling as specified in the sampling plan. Robert Weimer
12/1/2017 Update or Other Action Based on the information provided DEC is recommending the remaining site monitoring wells be decommissioned in preparation for closure with IC status. DEC requests a work plan for the decommissioning of the remaining site monitoring wells. Robert Weimer
12/1/2017 Exposure Tracking Model Ranking A new updated ranking with ETM has been completed for source area 78027 1996 UST contamination. Robert Weimer
11/28/2018 Document, Report, or Work plan Review - other DEC approval of the 2018 Well Decommissioning Work Plan and Amendment. The work plan proposes to decommission the remaining three monitoring wells at the site. DEC requests documentation once the decommissioning has been completed. Robert Weimer
11/5/2019 Meeting or Teleconference Held Meeting with Chevron's consultant. They will provide an updated site figure showing estimated extent of soil contamination for each of the following: over maximum allowable, over human health, and over migration to groundwater. After reviewing the figure, DEC will evaluate the site for closure with ICs. They confirmed that the site monitoring wells have not been decommissioned yet. We discussed that we are now using environmental covenant IC (UECA) instead of notice of environmental contamination IC (NEC). May need confirmation soil sampling to document current concentrations to demonstrate levels for closure. Robert Weimer
12/16/2019 Document, Report, or Work plan Review - other ADEC request that for all future monitoring events for all of the Chevron sites that the field notes document the measurement of the pump intake is within the top foot of the water column at the time of the sampling. Robert Weimer
1/15/2021 Meeting or Teleconference Held DEC staff met with Chevron Environmental Management Company (CEMC) and Arcadis to discuss Chevron sites located in Alaska during the Annual Portfolio Meeting on January 14th and 15th, 2021. Rebekah Reams
2/5/2021 Document, Report, or Work plan Review - other DEC provided comments on the Site Closure Request submitted by Arcadis on November 20, 2020. This report summarizes the site history and provides cumulative risk calculations, activity and use limitations, and an updated Conceptual Site Model (CSM) to support the request for site closure with institutional controls. DEC does not consider this site to be ready for closure under current policy. Sample locations determined to be above human health cleanup levels have not been evaluated since initial sampling was completed in 1996. Additionally, historic analytical results have not characterized the presence of volatile organic compounds (VOCs) or polynuclear aromatic hydrocarbons (PAHs) in areas determined to have elevated concentrations of contaminants. Rebekah Reams
8/13/2021 Site Characterization Workplan Approved DEC provided conditional approval for the Soil Investigation Work plan. This work plan proposes to advance two soil borings to evaluate contaminant concentrations that have exceeded human health and maximum allowable contaminant concentrations observed in 1996 at sample locations D-5, D-5A and D-6A. Analytical soil samples will be analyzed for the full suite of VOCs and PAHs in addition to GRO at these locations in order to determine whether these COPCs are present within the source area. Rebekah Reams
9/8/2022 Meeting or Teleconference Held DEC met with Chevron and their consultant to discuss challenges presented during the soil investigation field work. Due to the presence of utilities in the area, soil borings could not be advanced to confirm contaminant concentrations at the former boring locations where human health cleanup level exceedances were observed in 1996. Chevron will provide a revised closure request that addresses DEC's report comments dated February 5, 2021. Rebekah Reams
12/21/2023 Exposure Tracking Model Ranking A new updated ranking with ETM has been completed for source area 78027 1996 UST contamination. Rebekah Reams
3/20/2024 Document, Report, or Work plan Review - other ADEC sent the draft environmental covenant with tracked changes to the responsible party for review and revision. Rebekah Reams
5/13/2024 Update or Other Action Environmental covenant revisions are complete, final version of the covenant will be sent to the landowner for signature. Rebekah Reams
9/25/2024 Meeting or Teleconference Held ADEC staff met with Chevron and their consultant for an annual portfolio meeting to discuss site status, upcoming document submittals, pending reviews, and general updates for Chevron's contaminated sites throughout the state. Rebekah Reams

Contaminant Information

Name Level Description Media Comments

Control Type

Type Details

Requirements

Description Details

No associated sites were found.

Missing Location Data

Because the GIS location data for this site has not been entered, we cannot direct you to its position on the map. Click "Continue" to proceed to the Contaminated Sites Web Map or "Close" to return to the site report.
Continue     Close