| Action Date |
Action |
Description |
DEC Staff |
| 10/8/1997 |
Leaking Underground Storage Tank Release Confirmed - Petroleum |
LUST Site created in CSP for source area ID 77130 Release Investigation/Site Assessment to be conducted with UST system upgrade in Spring 1998. Approximately 15 to 20 cubic yards of soil was excavated during the investigation of loose piping connections. This soil was returned to the excavation with ADEC approval. The release investigation of the discovered release will be completed during the required UST system upgrade in Spring 1998. |
Former Staff |
| 10/8/1997 |
Site Added to Database |
|
Former Staff |
| 11/16/1998 |
Leaking Underground Storage Tank Cleanup Initiated - Petroleum |
entered by JC |
Former Staff |
| 11/16/1998 |
Underground Storage Tank Site Characterization or Assessment |
Completed more than 2 years previous. |
Former Staff |
| 12/14/1998 |
Leaking Underground Storage Tank Corrective Action Underway |
Annual meeting determined that SVE pilot test to be initiated, as well as a Well Search. |
Former Staff |
| 12/23/1998 |
Release Investigation |
Continuous RI activities as Gilfilian determines the extent of impact at this site. |
Former Staff |
| 7/7/1999 |
Update or Other Action |
Well search completed and submitted. |
Former Staff |
| 10/21/1999 |
Update or Other Action |
System start-up delayed and will not be activited this year due to low GW concentrations. |
Former Staff |
| 12/16/2003 |
Document, Report, or Work plan Review - other |
September 2003 Monitoring report review. |
Monica English |
| 1/14/2004 |
Leaking Underground Storage Tank Corrective Action Underway |
Approval of 2004 Work plan. |
Monica English |
| 10/9/2006 |
Update or Other Action |
Project manager changed from Monica English to Paul Horwath, per Paul Horwath. |
Alyce Hughey |
| 1/25/2007 |
Document, Report, or Work plan Review - other |
Reviewed MWH's October 25, 2006 Monitoring Well Decommissioning Report for this site. The decommissioning work was reported to have been completed using proper methods. |
Paul Horwath |
| 1/25/2007 |
Conditional Closure Approved |
A Conditional Closure letter was issued July 20, 2006. Conditions of closure include 1) ADEC approval must be obtained prior to removal, transport, or disposal of residual contaminated soil remaining at this site and Tesoro must provide qualified person third party oversight in order to monitor, assess, manage, treat, or dispose of any contaminated soils and, 2) Permanent closure or change in service of the existing USTs must be performed in accordance with 18 AAC 78. |
Paul Horwath |
| 1/25/2007 |
Institutional Control Record Established |
There are areas at this facility where soil contamination remains above the most stringent ADEC soil cleanup levels. Due to this residual soil contamination, the two conditions associated with this closure are: 1) In accordance with 18 AAC 78.274(b), ADEC approval must be obtained prior to removal and/or disposal of contaminated soil from this site. Tesoro shall provide the services of a qualified, impartial environmental professional as required in 18 AAC 78, in order to properly monitor, assess, manage, treat, and dispose of any contaminated soils. Future excavation activities shall be coordinated with ADEC. Tesoro shall provide for the excavation and treatment of any contaminated soils encountered in accordance with all applicable ADEC regulations at that time.
2) Permanent closure and/or change in service for the existing UST system must be conducted in accordance with 18 AAC 78.085. |
Paul Horwath |
| 11/10/2014 |
Update or Other Action |
Staff changed from Paul Horwath to IC Unit. |
Kristin Thompson |
| 8/18/2015 |
Institutional Control Compliance Review |
IC Compliance review conducted. Schedule to send an IC reminder letter to the responsible party. |
Evonne Reese |
| 8/20/2015 |
Institutional Control Update |
An IC reminder letter was issued to the responsible party on this date. |
Kristin Thompson |
| 6/2/2017 |
Institutional Control Compliance Review |
IC compliance review conducted. Closure/IC Details updated. Reminder system set to follow-up every five years, with the next review scheduled for 2020. |
Kristin Thompson |
| 8/21/2024 |
Institutional Control Compliance Review |
IC compliance review completed on this date. An IC reminder letter was e-mailed to the landowner. The next review will be in five years’ time. |
Gaige Robinson |