Action Date |
Action |
Description |
DEC Staff |
7/8/1997 |
Leaking Underground Storage Tank Release Confirmed - Petroleum |
LUST Site created in CSP for source area ID 78078 |
Former Staff |
9/24/1997 |
Document, Report, or Work plan Review - other |
On this date, ADEC received Final Report UST Removal Site Assement Anchorage Cold Storage Facilities For the Odom Corp., dated September 10, 1997 submitted by Dames and Moore. A combined total of 25 cubic tons of impacted soil were excavated from both tank 1 and tank 2 excavations and transported to Alaska Soil Recycling (ASR) for thermal remediation. At the tank 1 excavation, a petroleum fuel odor was noted along the north side of the excavation. While excavating this soil, perched groundwater was encountered at 4 feet below ground surface (bgs). Removal of impacted soil was limited due to: a sewer pipe located north of the excavation; and the presence of the beverage plant building located east and south of the excavation. Confirmation soil samples collected from 3 to 5 feet bgs, contained benzene up to 0.584 mg/kg. At the tank 2 excavation olfactory and visually petroleum impacted soil was noted along the fill pipe. Groundwater was not encountered. Removal of impacted soil was limited due to: a storm drain pipe located north of the excavation; a power line located west of the excavation; and the beverage plant building located south of the excavation. Confirmation soil samples collected at 6 feet bgs, contained benzene up to 0.0585 mg/kg. Both tank 1 and 2 excavations were backfilled with clean fill. |
Grant Lidren |
3/29/2001 |
Document, Report, or Work plan Review - other |
On this date, ADEC Draft Release Investigation Report Anchorage Cold Storage Facilities, dated March 22, 2000, submitted URS. Monitoring well MW-1 was installed at the tank 1 location. Two soil samples collected 5.5 feet bgs at the perched groundwater interface, during the advancement of MW-1, contained detectable levels of contaminants, but below ADEC cleanup levels. Groundwater samples collected at 11 feet bgs, contained benzene up to 0.013 mg/L. |
Grant Lidren |
12/10/2001 |
Update or Other Action |
Letter to Koslosky requesting final of RI report and additional RI into extent of soil and GW contamination sent. |
Lynne Bush |
12/10/2001 |
Update or Other Action |
CH2MHill doing MOA storm water rehabilitation project in area, needs file data to determine if pcs or pcgw will impact their work. |
Lynne Bush |
4/22/2004 |
Update or Other Action |
Letter requesting site update mailed to owner of record. |
Lynne Bush |
5/3/2004 |
Update or Other Action |
Letter returned "Addressee Unknown". Sent letter again but this time to Odom Corporate HQ in both Anchorage and Seattle. |
Lynne Bush |
5/7/2004 |
Update or Other Action |
Returned letter resent to new address. |
Lynne Bush |
6/17/2004 |
Update or Other Action |
Approved cost recovery invoice. |
Lynne Bush |
6/17/2004 |
Update or Other Action |
Received bi-annual report. |
Lynne Bush |
2/24/2005 |
Update or Other Action |
No response from Responsible Party, as of this date. |
Lynne Bush |
7/13/2006 |
Update or Other Action |
Used Figures 2 and 3 from the Dames & Moore "Final Report, UST Removal Site Assessment, Anchorage Cold Storage Facilities, for the Odom Corporation" dated 9/10/97 in conjunction with the Anchorage Area Atlas and TopoZone Pro to update the erroneous coordinates in both decimal degrees, and degrees, minutes and seconds. Plotted with No Topo Base Map on a Large Size Map at 1:3,333 Scale using High-Resolution Urban Aerial Photography. High degree of confidence in accuracy of coordinates. The map crosshairs represents the site of UST 1. Coordinates could only be improved using a GPS on site. Used MOA web resources to update landowner information. |
Bill Petrik |
6/13/2008 |
Exposure Tracking Model Ranking |
Intitial Ranking Complete for Source Area: 78078 (Autogenerated Action) |
|
6/15/2008 |
Update or Other Action |
From 2002 to 2008, MW-1 was sampled periodically four times. The water sampling events indicated a stable or decreasing trend of benzene in the groundwater. The 2008 groundwater sampling event contained benzene up to 0.00940 mg/l. |
Grant Lidren |
8/5/2008 |
Release Investigation |
Rec'd Supplemental Release Investigation work plan dated Aug 5, 2008. |
Eileen Olson |
8/12/2008 |
Site Characterization Workplan Approved |
ADEC issued a letter approving the Supplemental Release Investigation Work Plan dated August 5, 2008 with appended Sampling and Analysis Plan. The plan proposes to conduct additional investigation of soil and groundwater contamination associated with an unleaded-gasoline
LUST and the associated piping and dispenser that were removed in 1997. A groundwater monitoring well (MW-1) installed at the tank location in 2000 has been sampled a total of four times. Samples were analyzed for GRO, DRO, RRO and BTEX. The only contaminant
exceeding cleanup levels was benzene, with benzene levels exceeding MCLs found in Table C of 18 AAC 75.345 for all events. The plan proposes drilling five borings near the former UST area, with two soil samples to be collected from each boring, and two of the borings to be
completed as monitoring wells. Groundwater is expected to be present at a depth of 8 to 10
feet below the ground surface. ADEC approved the plan with the condition that for each boring
a sample be collected at and just above the soil/groundwater interface regardless of field
screening results. |
Eileen Olson |
11/3/2008 |
Update or Other Action |
ADEC received and approved a request for transport and disposal of Investigation Derived Waste
for all three open Odom sites (240 West 1st,244 Nelchina Street and 135 South Post Road). Emerald Alaska was contracted to transport and dispose the waste, consisting of four 55-gallon drums of groundwater generated during groundwater sampling activities at the sites in July and October 2008. |
Eileen Olson |
3/13/2009 |
Update or Other Action |
The ADEC sent an email, on this date, for information on the site status. URS indicates that Supplemental RI work will continue in the spring of 2009. The ADEC will be notified 48 hrs before the work commences. |
Grant Lidren |
10/26/2009 |
Document, Report, or Work plan Review - other |
The Alaska Department of Environmental Conservation (ADEC), Contaminated Sites Program, has no objection to the proposed transportation of two 55-gallon drums of water; and one 55-gallon drum and two 5-gallon buckets of soil; from petroleum contaminated soil and groundwater encountered during site evaluation activities during May and June 2009. An approval letter for transport was sent on this date. |
Grant Lidren |
11/2/2009 |
Document, Report, or Work plan Review - other |
On May 28, 2009, further evaluation at the area of former UST 1 was conducted. Five soil borings(B3-B7) and two monitoring wells (MW2 & MW3) were advanced. GW was encountered at 13.5 to 14.5 ft. bgs. A perched GW layer was also encountered at 2.5 ft. bgs. GW was found to flow to the west and slightly to the northwest. GW analyzed from the historic well MW 1 and the new wells MW 2 & 3 contained benzene up to 0.0261 mg/L. Soil samples collected from the borings and advancement of MW2 and MW3 contained benzene up to 0.862 mg/kg. |
Grant Lidren |
7/21/2010 |
Document, Report, or Work plan Review - other |
On this date, ADEC received Groundwater Monitoring Plan Anchorage Beverage Plant The Odom Corporation, submitted by URS. The groundwater from the monitoring wells: MW1, MW2, and MW3; will be analyzed for GRO and BTEX. |
Grant Lidren |
9/30/2010 |
Document, Report, or Work plan Review - other |
On this date, ADEC receive the 2010 Groundwater Monitoring Report Anchorage Beverage Plant, submitted by URS and dated September 28, 2010. Four groundwater samples were collected from monitoring wells MW-1, MW-2, and MW-3; and were sampled for GRO and BTEX on August 12, 2010. Only one monitoring well, MW-1(which is located at the former UST area), contained benzene above ADEC cleanup levels with benzene up to 0.00608 mg/L. The groundwater gradient was to the north-northwest and the mean depth to GW for the three wells was approximately 6.6 feet below the top of the well casings. |
Grant Lidren |
10/11/2010 |
Site Visit |
On this date, the area of former Tank 2 was located. T2 is located adjacent to the bridge support, doorway, and the Odom building |
Grant Lidren |
10/22/2010 |
Document, Report, or Work plan Review - other |
ADEC reviewed and approved Monitoring Well Decommissioning Work Plan, submitted by URS, dated October 21, 2010 |
Grant Lidren |
11/17/2010 |
Offsite Soil or Groundwater Disposal Approved |
On this date, ADEC approved Emerald’s transport and disposal of a 30-gallon drum of petroleum impacted water from the site. |
Grant Lidren |
12/10/2010 |
Document, Report, or Work plan Review - other |
On this date, ADEC received Well Closure Report Anchorage Beverage Plant, submitted by URS dated December 10, 2010. Monitoring wells MW-1, MW-2, and MW-3 were decommissioned in accordance w/ ADEC’s February 2009 Monitoring Well Guidance. |
Grant Lidren |
1/20/2011 |
Cleanup Complete Determination Issued |
The Alaska Department of Environmental Conservation (ADEC), Contaminated Sites Program, has completed a review of the environmental records associated with the Odom Corporation - 240 West 1st Avenue. Based on the information provided to date, the ADEC has determined that the contaminant concentrations remaining on site do not pose an unacceptable risk to human health or the environment, and no further remedial action will be required as long as the site is in compliance with established institutional controls. |
Grant Lidren |
1/20/2011 |
Institutional Control Record Established |
Institutional Controls established and entered into the database. |
Grant Lidren |
1/20/2011 |
Leaking Underground Storage Tank Cleanup Initiated - Petroleum |
3/14/11- Administrative action addition for reporting purposes.
|
Bianca Reece |
2/15/2011 |
Update or Other Action |
On this date, ADEC recieved signed Cleanup Complete-ICs Agreement and Signature Page. |
Grant Lidren |
6/13/2012 |
Update or Other Action |
Staff changed from Grant Lidren to IC Unit. |
Kristin Thompson |
6/13/2012 |
Institutional Control Compliance Review |
IC review conducted and reminder system set-up for 2016 follow-up with responsible party. |
Kristin Thompson |
1/11/2016 |
Institutional Control Compliance Review |
IC compliance review conducted and IC reminder letter issued to the responsible party on this date. Reminder system set to follow-up in 2021. |
Kristin Thompson |
5/25/2017 |
Institutional Control Compliance Review |
IC compliance review conducted. Closure/IC Details updated. |
Kristin Thompson |
8/13/2024 |
Institutional Control Compliance Review |
IC compliance review completed on this date. An IC reminder letter was e-mailed to the landowner. The next review will be in five years’ time. |
Gaige Robinson |