Skip to content Skip to content

Site Report: ADOC Fairbanks Correctional Center

Site Name: ADOC Fairbanks Correctional Center
Address: 1931 Eagan Avenue, Fairbanks, AK 99701
File Number: 102.26.093
Hazard ID: 24994
Status: Active
Staff: Janice Wiegers, 9074512127 janice.wiegers@alaska.gov
Latitude: 64.832900
Longitude: -147.759100
Horizontal Datum:NAD83

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

During an upgrade in 1999 to a 10,000-gallon diesel underground storage tank (UST #2), contaminated soil was reported around the fill port. Approximately 3 cy of contaminated soil (DRO up to 125,000 mg/kg) were stockpiled on site. Soil was removed from site and properly disposed of in 2000. The site was closed in 2006. In 2009, the same 10,000-gallon diesel tank (UST #2) was temporarily taken out of service while some piping was removed during the installation of a new aboveground tank south of the UST. In February, 2012 the UST Program issued a notice of non-compliance requiring the tank to be permanently closed. Based on information gathered during site assessment activities in October 2012, the site was reopened. Petroleum contamination was confirmed above DEC cleanup levels in soil and groundwater.

Action Information

Action Date Action Description DEC Staff
9/24/1992 Leaking Underground Storage Tank Release Confirmed - Petroleum LUST Site created in CSP for source area ID 77426 Former Staff
9/24/1992 Site Added to Database Former Staff
1/3/1994 Underground Storage Tank Site Characterization or Assessment Dames & Moore, 1994 Former Staff
6/4/1999 Update or Other Action Reconfiguration request submitted and 15-day waiver written for 10,000-gallon diesel tank No. 2. - Tim Stevens Former Staff
10/27/1999 Leaking Underground Storage Tank Cleanup Initiated - Petroleum According to SA, no impacts of significance. Former Staff
9/25/2000 Update or Other Action JBC Entry - I have coordinated with the RP on this site, and have indicated that they are ready for closure it they address the small contaminated stockpile onsite. They indicated that this is a very low priority with them, although I indicated it would be cost effective to deal with at this time. Former Staff
1/28/2004 Update or Other Action Transferred DEC staff lead from John Carnahan Cynthia Pring-Ham
4/3/2006 Update or Other Action Confirmed with Maintenance Supervisor Brad Miller that stockpiled soil was removed by a contractor in Anchorage in the summer of 2000 along with 5 gallons of glycol waste. Shannon Oelkers
4/6/2006 Site Closure Approved No further action letter approved. Shannon Oelkers
11/21/2012 Site Reopened In 2009, the same 10,000-gallon diesel tank (UST #2) was temporarily taken out of service while some piping was removed during the installation of a new aboveground tank south of the UST. In February, 2012 the UST Program issued a notice of non-compliance requiring the tank to be permanently closed. Based on information gathered during site assessment activities in October 2012, the site is being reopened. Petroleum contamination was confirmed above DEC cleanup levels in soil and groundwater. Mitzi Read
11/21/2012 Leaking Underground Storage Tank Release Confirmed - Petroleum LUST site created in CSP database for source area Tank #2 - 10,000-Gal Diesel UST (2012 Release), 79363 Mitzi Read
11/26/2012 Underground Storage Tank Site Characterization or Assessment Reviewed UST Site Assessment Report completed by Shannon & Wilson for DOT in October 2012. An in-place closure site assessment was completed because the tank is located in a tight location surrounded by security fencing. S&W installed three borings and found near-surface soil contamination at the north end of the UST and subsurface soil contamination south of the UST. A monitoring well (MW-1) was installed south of the UST. Groundwater samples from MW-1 contained DRO up to 14.7 mg/L. Sections of remaining piping were also pressure tested and were determined to be tight. Janice Wiegers
11/27/2012 Meeting or Teleconference Held Met with Department of Corrections, Department of Tranportation, and UST Program to discuss the 10,000-gallon UST site assessment results. DOT/DOC plans to contract with Shannon & Wilson to complete cleaning and filling of the UST, further investigate the release to by installing at least two monitoring wells northwest of MW-1, and to excavate near surface contaminated soil at the north end of the tank. Removal of the tank to expose the deeper contaminated soil observed at the south end of the tank is complicated by the security fence which cannot be undermined or comprised through excavation deeper than a couple of feet. DEC requested a workplan and explained GRO should be retained as a COC until further characterization is completed. Janice Wiegers
11/27/2012 Exposure Tracking Model Ranking Initial ranking with ETM completed for source area id: 79363 name: Tank #2 - 10,000-Gal Diesel UST (2012 Release) Mitzi Read
12/7/2012 Update or Other Action Notice of release letter sent to Department of Corrections. Janice Wiegers
6/10/2013 Update or Other Action Received notice of intent-to-close or change-in-service. Shannon & Wilson plans to inert in place the 10,000 gallon diesel tank on June 30th. Janice Wiegers
6/18/2013 Document, Report, or Work plan Review - other Received workplan for completing the in-place UST closure by removing fuel, excavating to top of tank, and purging and filling the tank. Soil will be screened with a PID and contaminated material will be taken to OIT for thermal remediation. DEC approved the workplan and provided soil transport approval at the same time. Janice Wiegers
8/7/2013 Document, Report, or Work plan Review - other Shannon & Wilson (S&W) submittal of Underground Storage Tank Closure Report received and reviewed. The report summarized the in-place closure of the 10,000 gallon diesel underground storage tank (UST) a the Fairbanks Correction Center (FCC). S&W contracted with Inland Petroservice (IPS) and completed in-place closure on July 3, 2013. On July 5, 2013, the tank was filled with concrete grout using a pump truck. IPS also backfilled the excavation with the excavated soil. Conclusions and recommendations note that no contaminated soil was encountered during work. It is recommended that a release investigation is carried out to evaluate the extent of soil and groundwater contamination associated with the UST. Keri DePalma
6/29/2016 Update or Other Action Sent letter to Department of Corrections requiring additional release investigation to determine the extent of groundwater contamination. The letter requested a workplan be submitted in August 1. Janice Wiegers
7/27/2016 Update or Other Action Contacted by Dan Aicher with the Department of Corrections. Mr. Aicher indicated the Shannon & Wilson are working on a workplan. The workplan is expected to be completed by October 1, 2016. Janice Wiegers
12/2/2016 Update or Other Action Shannon & Wilson submitted workplan for additional investigation. Janice Wiegers
12/2/2016 Update or Other Action Release investigation workplan submitted by Shannon & Wilson. Two borings/monitoring wells will be installed to investigate extend of soil and groundwater contamination associated with 10,000 gallon tank that was closed in place. BTEX, DRO, GRO, and PAHs will be analyzed. Work planned for summer 2017, although DOC does not have identified funding yet. Janice Wiegers
4/24/2017 Update or Other Action Contacted Shannon & Wilson to check on the pressure testing completed on the piping runs in 2011. Piping between the UST and the Prison Industries Building initially failed the hydrotstatic pressure test, when the test was performed at the Prison Industries Buildings. However, it was determined that the piping had been cut at the UST, and once the cut piping was sealed off, the lines passed pressure testing. Janice Wiegers
4/25/2017 Document, Report, or Work plan Review - other DEC provided comments on the November 2016 workplan for release investigation in a letter to Dan Aicher at the Alaska Department of Corrections. DEC requested that the proposed monitoring wells locations be moved closer to the closed UST and that groundwater flow direction and gradient be reported. DEC will require at least two groundwater sampling events to evaluate seasonal conditions. Janice Wiegers
1/16/2018 Update or Other Action Sent letter to ADOC requesting update on project as DEC has not received a revised workplan. Janice Wiegers
1/19/2018 Update or Other Action Received call from Dan Aicher with ADOC indicating that ADOC has funding now for UST work and ADOC plans to proceed with this project. Janice Wiegers
3/15/2018 Document, Report, or Work plan Review - other Reviewed revised workplan from Shannon & Wilson. Janice Wiegers
3/23/2018 Document, Report, or Work plan Review - other Final workplan submitted for additional release investigation. DEC approved workplan on March 27. Janice Wiegers
6/19/2020 Update or Other Action Corresponded with Daniel Aicher with the Department of Corrections regarding a report for the work planned in 2018. DEC has not received a report. Janice Wiegers
6/28/2021 Update or Other Action DEC contacted the Department of Corrections to ask if the work approved in the 2018 workplan had been completed. DOC responded with some questions but did not respond after that. A new contact point may be needed. Janice Wiegers
12/15/2023 Update or Other Action DEC sent a letter to Clifton Reagle at DOC requesting follow up on the previous requests to delineate and monitor groundwater contamination. The letter requested a schedule for additional site action by 2/29/23. Janice Wiegers
4/19/2024 Update or Other Action DOC contact called to say that the previously workplan had not been completed. DOC is working on finding funding and is in contact with Shannon & Wilson about the next work. Janice Wiegers

Contaminant Information

Name Level Description Media Comments

Control Type

Type Details

Requirements

Description Details
Advance approval required to transport soil or groundwater off-site.

No associated sites were found.

Missing Location Data

Because the GIS location data for this site has not been entered, we cannot direct you to its position on the map. Click "Continue" to proceed to the Contaminated Sites Web Map or "Close" to return to the site report.
Continue     Close