Action Date |
Action |
Description |
DEC Staff |
9/24/1992 |
Leaking Underground Storage Tank Release Confirmed - Petroleum |
LUST Site created in CSP for source area ID 77426 |
Former Staff |
9/24/1992 |
Site Added to Database |
|
Former Staff |
1/3/1994 |
Underground Storage Tank Site Characterization or Assessment |
Dames & Moore, 1994 |
Former Staff |
6/4/1999 |
Update or Other Action |
Reconfiguration request submitted and 15-day waiver written for 10,000-gallon diesel tank No. 2. - Tim Stevens |
Former Staff |
10/27/1999 |
Leaking Underground Storage Tank Cleanup Initiated - Petroleum |
According to SA, no impacts of significance. |
Former Staff |
9/25/2000 |
Update or Other Action |
JBC Entry - I have coordinated with the RP on this site, and have indicated that they are ready for closure it they address the small contaminated stockpile onsite. They indicated that this is a very low priority with them, although I indicated it would be cost effective to deal with at this time. |
Former Staff |
1/28/2004 |
Update or Other Action |
Transferred DEC staff lead from John Carnahan |
Cynthia Pring-Ham |
4/3/2006 |
Update or Other Action |
Confirmed with Maintenance Supervisor Brad Miller that stockpiled soil was removed by a contractor in Anchorage in the summer of 2000 along with 5 gallons of glycol waste. |
Shannon Oelkers |
4/6/2006 |
Site Closure Approved |
No further action letter approved. |
Shannon Oelkers |
11/21/2012 |
Site Reopened |
In 2009, the same 10,000-gallon diesel tank (UST #2) was temporarily taken out of service while some piping was removed during the installation of a new aboveground tank south of the UST. In February, 2012 the UST Program issued a notice of non-compliance requiring the tank to be permanently closed. Based on information gathered during site assessment activities in October 2012, the site is being reopened. Petroleum contamination was confirmed above DEC cleanup levels in soil and groundwater. |
Mitzi Read |
11/21/2012 |
Leaking Underground Storage Tank Release Confirmed - Petroleum |
LUST site created in CSP database for source area Tank #2 - 10,000-Gal Diesel UST (2012 Release), 79363 |
Mitzi Read |
11/26/2012 |
Underground Storage Tank Site Characterization or Assessment |
Reviewed UST Site Assessment Report completed by Shannon & Wilson for DOT in October 2012. An in-place closure site assessment was completed because the tank is located in a tight location surrounded by security fencing. S&W installed three borings and found near-surface soil contamination at the north end of the UST and subsurface soil contamination south of the UST. A monitoring well (MW-1) was installed south of the UST. Groundwater samples from MW-1 contained DRO up to 14.7 mg/L. Sections of remaining piping were also pressure tested and were determined to be tight. |
Janice Wiegers |
11/27/2012 |
Meeting or Teleconference Held |
Met with Department of Corrections, Department of Tranportation, and UST Program to discuss the 10,000-gallon UST site assessment results. DOT/DOC plans to contract with Shannon & Wilson to complete cleaning and filling of the UST, further investigate the release to by installing at least two monitoring wells northwest of MW-1, and to excavate near surface contaminated soil at the north end of the tank. Removal of the tank to expose the deeper contaminated soil observed at the south end of the tank is complicated by the security fence which cannot be undermined or comprised through excavation deeper than a couple of feet. DEC requested a workplan and explained GRO should be retained as a COC until further characterization is completed. |
Janice Wiegers |
11/27/2012 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed for source area id: 79363 name: Tank #2 - 10,000-Gal Diesel UST (2012 Release) |
Mitzi Read |
12/7/2012 |
Update or Other Action |
Notice of release letter sent to Department of Corrections. |
Janice Wiegers |
6/10/2013 |
Update or Other Action |
Received notice of intent-to-close or change-in-service. Shannon & Wilson plans to inert in place the 10,000 gallon diesel tank on June 30th. |
Janice Wiegers |
6/18/2013 |
Document, Report, or Work plan Review - other |
Received workplan for completing the in-place UST closure by removing fuel, excavating to top of tank, and purging and filling the tank. Soil will be screened with a PID and contaminated material will be taken to OIT for thermal remediation. DEC approved the workplan and provided soil transport approval at the same time. |
Janice Wiegers |
8/7/2013 |
Document, Report, or Work plan Review - other |
Shannon & Wilson (S&W) submittal of Underground Storage Tank Closure Report received and reviewed. The report summarized the in-place closure of the 10,000 gallon diesel underground storage tank (UST) a the Fairbanks Correction Center (FCC). S&W contracted with Inland Petroservice (IPS) and completed in-place closure on July 3, 2013. On July 5, 2013, the tank was filled with concrete grout using a pump truck. IPS also backfilled the excavation with the excavated soil. Conclusions and recommendations note that no contaminated soil was encountered during work. It is recommended that a release investigation is carried out to evaluate the extent of soil and groundwater contamination associated with the UST. |
Keri DePalma |
6/29/2016 |
Update or Other Action |
Sent letter to Department of Corrections requiring additional release investigation to determine the extent of groundwater contamination. The letter requested a workplan be submitted in August 1. |
Janice Wiegers |
7/27/2016 |
Update or Other Action |
Contacted by Dan Aicher with the Department of Corrections. Mr. Aicher indicated the Shannon & Wilson are working on a workplan. The workplan is expected to be completed by October 1, 2016. |
Janice Wiegers |
12/2/2016 |
Update or Other Action |
Shannon & Wilson submitted workplan for additional investigation. |
Janice Wiegers |
12/2/2016 |
Update or Other Action |
Release investigation workplan submitted by Shannon & Wilson. Two borings/monitoring wells will be installed to investigate extend of soil and groundwater contamination associated with 10,000 gallon tank that was closed in place. BTEX, DRO, GRO, and PAHs will be analyzed. Work planned for summer 2017, although DOC does not have identified funding yet. |
Janice Wiegers |
4/24/2017 |
Update or Other Action |
Contacted Shannon & Wilson to check on the pressure testing completed on the piping runs in 2011. Piping between the UST and the Prison Industries Building initially failed the hydrotstatic pressure test, when the test was performed at the Prison Industries Buildings. However, it was determined that the piping had been cut at the UST, and once the cut piping was sealed off, the lines passed pressure testing. |
Janice Wiegers |
4/25/2017 |
Document, Report, or Work plan Review - other |
DEC provided comments on the November 2016 workplan for release investigation in a letter to Dan Aicher at the Alaska Department of Corrections. DEC requested that the proposed monitoring wells locations be moved closer to the closed UST and that groundwater flow direction and gradient be reported. DEC will require at least two groundwater sampling events to evaluate seasonal conditions. |
Janice Wiegers |
1/16/2018 |
Update or Other Action |
Sent letter to ADOC requesting update on project as DEC has not received a revised workplan. |
Janice Wiegers |
1/19/2018 |
Update or Other Action |
Received call from Dan Aicher with ADOC indicating that ADOC has funding now for UST work and ADOC plans to proceed with this project. |
Janice Wiegers |
3/15/2018 |
Document, Report, or Work plan Review - other |
Reviewed revised workplan from Shannon & Wilson. |
Janice Wiegers |
3/23/2018 |
Document, Report, or Work plan Review - other |
Final workplan submitted for additional release investigation. DEC approved workplan on March 27. |
Janice Wiegers |
6/19/2020 |
Update or Other Action |
Corresponded with Daniel Aicher with the Department of Corrections regarding a report for the work planned in 2018. DEC has not received a report. |
Janice Wiegers |
6/28/2021 |
Update or Other Action |
DEC contacted the Department of Corrections to ask if the work approved in the 2018 workplan had been completed. DOC responded with some questions but did not respond after that. A new contact point may be needed. |
Janice Wiegers |
12/15/2023 |
Update or Other Action |
DEC sent a letter to Clifton Reagle at DOC requesting follow up on the previous requests to delineate and monitor groundwater contamination. The letter requested a schedule for additional site action by 2/29/23. |
Janice Wiegers |
4/19/2024 |
Update or Other Action |
DOC contact called to say that the previously workplan had not been completed. DOC is working on finding funding and is in contact with Shannon & Wilson about the next work. |
Janice Wiegers |