Action Date |
Action |
Description |
DEC Staff |
4/7/1990 |
Site Added to Database |
Multiple contaminants.
(Date adjusted from 11/10/1999 for report/query consistency. (Reese))
|
John Halverson |
4/7/1990 |
Update or Other Action |
Phase II HTRW report completed. Several areas found to be contaminated with petroleum or other hazardous substances. Several different source areas of concern were identified within the larger site. The landfill area was investigated, a well point was installed and sampled, a geophysical survey indicated about 16,000 square feet of landfill area (excluding the trenches). A pond is adjacent to the landfill. 60-80 drums, some leaking unidentified wastes was identified ~ 150' north of well point #1. |
John Halverson |
2/3/1992 |
Update or Other Action |
OHM conducted a removal action for the Corps and submitted a summary report. It indicated that ~ 26 drums of waste were removed from the general area of the disposal trenches. |
John Halverson |
1/25/1995 |
Site Characterization Report Approved |
Received the draft-final Phase III Remedial Investigation Report - Cleanup Design, prepared by E&E, for the Corps. It documented low levels of vinyl chloride in groundwater beneath the landfill and solid waste on the ground surface in the landfill and trench disposal areas. |
John Halverson |
8/22/1995 |
Long Term Monitoring Established |
Received groundwater monitoring plan documents from the Corps calling for quarterly and semi-annual monitoring from various wells throughout the Wildwood AFS site. |
John Halverson |
8/22/1995 |
Update or Other Action |
Received the final baseline human health risk assessment report for Wildwood AFS. It concluded that an unacceptable risk may exist under current or potential future land uses at the landfill area along with some other areas at the larger site. |
John Halverson |
4/1/1996 |
Risk Assessment Report Approved |
Received the final Ecological Risk Assessment Report (Tier I) for Wildwood AFS. It recommended either proceeding to a Tier II ecological risk assessment or conducting removal/remedial actions to address hot spots. |
John Halverson |
4/18/1996 |
Proposed Plan |
The Corps finalized the proposed plan. Preferred alternatives included: Main Complex tank farm and USTs 5-1 and 5-2 - vapor extraction and air sparging; Maintenance Building, ACS MARS, Quonset Hut and Disposal Trench Area Burn Pit - soil excavation and off-site treatment followed by no further action; Operations Building - excavation and off-site treatment followed by natural attenuation and institutional controls; Landfill and Disposal Trenches - capping, natural attenuation (landfill area only) and institutional controls. |
John Halverson |
6/3/1996 |
Update or Other Action |
Received a groundwater monitoring report for tank farm area from sampling in August 1995. It covered the main complex area tank farm and USTs (significant fuel contamination), ACS/MARS facility (low level DRO), Operations Building (DRO and low TEX), Landfill (low level VOCs) and Trench disposal areas (DRO and benzene at burn pit area). |
John Halverson |
7/20/1996 |
Update or Other Action |
ADEC received a draft record of decision for the Wildwood Air Force Station FUDS. It called for capping the landfill and disposal trench areas with soil, grading and revegetating the areas and monitoring groundwater. It also called for documenting the disposal site locations in the appropriate land records as an institutional control. Due to challenges over implementing institutional controls and a few other issues, the ROD has not been finalized. |
John Halverson |
8/27/1996 |
Update or Other Action |
Received the December 1995 groundwater monitoring event report. It covers the tank farm area and former USTs at the main complex (significant petroleum contamination in GW at and downgradient from tank farm), the ACS MARS facility and Quonset Hut area (low level DRO in GW), the Operation Building (DRO and TEX in GW), Landfill (low level VOCs) and Trench Disposal Areas (DRO, benzene at burn pit area). |
John Halverson |
11/22/1996 |
Interim Removal Action Approved |
Received final "Remedial Action Report Interim Removal Action, Wildwood AFS" by Harding and Lawson Associates, October 28, 1996. Conclusions, based on confirmation samples at the end of the removal document that within the Trench Area Burn Pit elevated DRO (1,200 - 18,000 mg/kg) remains in soil. |
John Halverson |
8/13/1997 |
Update or Other Action |
ADEC received the workplan for Phase II Remediation, Wildwood AFS, by HLA/Wilder, dated July 2, 1997. Plan called for capping the disposal trenches and landfill areas with a soil cover and revegetating them. ADEC reviewed and commented on the draft workplan, but the comments were not all addressed. No formal approval was given on the plan. |
John Halverson |
12/9/1997 |
Update or Other Action |
Received the groundwater monitoring report for sampling done in July 1997. Groundwater levels have dropped significantly, some MWs have gone dry. Sampling was done at the tank farm and former USTs at the main complex (sheen and noticeable fuel odor present in two MWs, free product in MW AP-365; also 1,2 DCA level increased in a downgradient, off-site MW), Landfill (low level VOCs), Operations Building (up to 6 mg/l DRO), Rifle range (260 ug/l total lead) and Firing Range (12 ug/l total lead). |
John Halverson |
5/15/1999 |
Update or Other Action |
Received groundwater monitoring report for sampling done in July 1998. Tank farm area (GW level rose slightly, free product found in 3 MWs, GRO increasing in down-gradient MW, 1,2DCA increasing in downgradient MW), Landfill area (low level VOCs, near cleanup levels), Operations building (DRO low levels, need new wells in better locations), Rifle range (total lead and antimony decreased, dissolved lead and antimony N/D), Firing range (total and dissolved lead and antimony N/D). |
John Halverson |
9/3/1999 |
Update or Other Action |
ADEC received the Remedial Action Report, Phase II Remediation, by HLA/Wilder, dated August 25, 1999. It documents work done between June 1997 and November 1998. The landfill and trench areas were capped as specified in the workplan. Trench area burn pit still has residual soil contamination that needs to be addressed, either through institutional controls or further cleanup. |
John Halverson |
9/12/2002 |
Site Number Identifier Changed |
Workplan changed from X5 to x9. Sequence Number changed to 03 from 01 to accommodate changing the Workplan. The DBA pointed out to the project manager that despite this site being listed as a military landfill, vinyl chloride appears to be the biggest chemical of concern. |
John Halverson |
9/12/2002 |
Site Ranked Using the AHRM |
Checked the Multiple Sources box. |
Former Staff |
2/3/2005 |
Update or Other Action |
File number issued 2320.38.051 |
Aggie Blandford |
6/2/2005 |
Site Characterization Workplan Approved |
A work plan for Site Characterization and Attenuation Monitoring was approved with minor comments. The work plan describes the planned investigation to delineate further the locations of remaining NAPL at the various source areas within the former Wildwood AFS using the Rapid Optical Screening Tool (ROST), Laser-Induced Fluorescence (LIF). It includes sampling and analysis to calibrate the results of the ROST LIF work and to further characterize contaminant nature and obtain data with which to evaluate the status of each source area using current Method II and III tools, and possibly a 4-phase partitioning model. Sampling and analysis will also obtain data with which to evaluate natural attenuation occurrence at each source area. |
Debra Caillouet |
6/21/2005 |
Meeting or Teleconference Held |
Staff visited all of the Wildwood sites with the new project manager and the environmental engineer for the site. Staff also observed the ROST/LIF in operation. |
Debra Caillouet |
6/15/2007 |
Update or Other Action |
The Declaration of Project Closure Decison for the CON/HTRW project at Wildwood was signed. |
Debra Caillouet |
9/5/2007 |
Site Characterization Report Approved |
The ROST/LIF Investigation, Former Wildwood Air Force Station, Revision 1, April 2007 Report was reviewed and approved. The report presents the results of the investigation at multiple areas within the former Wildwood AFS during the summer of 2005. The logs from the ROST/LIF are presented along with laboratory analysis results. The report provides valuable site characterization data to support future decisions and generally meets the requirements of 18 AAC 75.335 Site Characterization.
|
Debra Caillouet |
9/22/2008 |
Site Added to Database |
A new site has been added to the database |
Mitzi Read |
9/26/2008 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed for source area id: 78511 name: Trench Area Burn Pit |
Debra Caillouet |
11/9/2018 |
Update or Other Action |
Drafted closure evaluation letter, dated November 9, 2018 and sent to the Corps of Engineers. Requested historical groundwater table be developed for several wells. Table is due February 19, 2019. |
Joshua Barsis |
1/23/2019 |
Update or Other Action |
Reviewed letter from USCOE, dated January 14, 2019 sent in response to DECs letter dated November 9, 2018. Letter documents sampling completed in 1996 at Well AP-375. ADEC requested additional files from achieve in response to letter and as part of the closure evaluation for this site. |
Joshua Barsis |
2/7/2019 |
Update or Other Action |
Letter sent to ACOE on this day (February 7, 2019) with a full site summary and recommended action. |
Joshua Barsis |
9/2/2021 |
Site Characterization Workplan Approved |
Approved Kenaitze Indian Tribe NALEMP work plan to remove 20 cy of contaminated soil from the Trench Area Burn Pit. Soil will be sampled for lead and DRO. If appropriate soil waste will be transported to ASR. |
Lisa Krebs-Barsis |
8/3/2022 |
Document, Report, or Work plan Review - other |
A NALEMP Draft Report for the Removal of Contaminated Soil at the Trench Area Burn Pit was reviewed. The report included work at other hazard ids. Comments were sent. The consultant removed approximately 40 cubic yards of contaminated soil in the area believed to be where 2009 soil boring BP-4 was located. The excavation was 7 ft deep and extended into the saturated zone. Five sidewall samples were collected from the excavation and analyzed for DRO and lead. The maximum concentration of DRO was 437 mg/Kg. Lead did not exceed soil cleanup levels. Waste generated by the excavation was analyzed for VOC, PCB, RCRA metals, and dioxins in addition to DRO and lead. DRO was detected in the stockpile at up to 1,080 mg/Kg. Dioxins below the cleanup level were also detected. The waste will be transported to MCF for thermal treatment. |
Lisa Krebs-Barsis |
8/3/2022 |
Offsite Soil or Groundwater Disposal Approved |
Approval to transport 40 cy of soil to MCF. Soil is contaminated with diesel. Dioxins below cleanup levels are present. |
Lisa Krebs-Barsis |
5/10/2024 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 78511 Trench Area Burn Pit. |
Erica Blake |
7/9/2024 |
Site Visit |
DEC staff conducted a site visit to the Wildwood AFS area in Kenai, Alaska. The purpose of the site visit was to inspect multiple sites within the Wildwood Air Force Station and observe groundwater monitoring fieldwork. Sites inspected were; 12-acre Landfill, disposal trench area, Underground Storage Tank (UST) area near the Correctional Facility, and the Operations Maintenance Building. U.S. Army Corp of Engineers staff accompanied DEC staff around the facility for the inspection. |
Peter Campbell |
7/29/2024 |
Update or Other Action |
DEC provided the U.S. Army Corp of Engineers with a letter summarizing site inspection notes from a July 9, 2024 site visit at various Wildwood AFS sites. The letter described several deviations from the approved work plans (dated 2016 and 2023), and requested USACE discuss impacts of the deviations and issues in the reporting. |
Erica Blake |