Action Date |
Action |
Description |
DEC Staff |
4/7/1990 |
Site Added to Database |
Gasoline, diesel fuel, asphalt tar and lead in soil. Fuels and low level vinyl chloride, in groundwater.
(Date adjusted from 8/16/1991 for report/query consistency. (Reese))
|
Former Staff |
4/7/1990 |
Update or Other Action |
Phase II HTRW report completed. Several areas found to be contaminated with petroleum or other hazardous substances. Drums of wastes appear to be leaking. Tank Farm, drum storage area and burned quonset hut containing electrical equipment appear to be highest priorities. |
John Halverson |
7/1/1990 |
Site Ranked Using the AHRM |
Ecology and Environment site scores HRS I = 24.31, HRS II= 9.29. HRS I is below EPA score of 28.5 for potential inclusion on the NPL. No further action planned under CERCLA. |
Former Staff |
2/3/1992 |
Interim Removal Action Approved |
Corps Draft Final Report for Wildwood Air Force Station, by OHM, documents a removal conducted under FUDS program. Removed ~200 drums of wastes, ~85 five-gallon containers, approximately 75 other containers of paints, oils, pesticides, eleven transformers (non-PCB), petroleum contaminated soil from several areas and dioxin contaminated soil from the ACS Mars Quonset hut area. |
John Halverson |
11/10/1993 |
Update or Other Action |
Quest Environmental removed the fuel tanks and ~3 feet of soil from beneath them. Residual soil contamination remains. Soil placed in a long-term stockpile. |
John Halverson |
5/12/1994 |
Update or Other Action |
Received final report on dioxin and furan contaminated soil at the ACS Mars Quonset Hut. Conclusion was that remaining soil did not pose an unacceptable risk. |
John Halverson |
1/25/1995 |
Site Characterization Report Approved |
Received draft final Phase III Remedial Investigation Report - Cleanup Decision; petroleum identified as the most prevalent contaminant of concern in soil and groundwater (15 different source areas); lead in soil at three sites; vinyl chloride in groundwater beneath the landfill. Off-site migration was only found at the former tank farm, where petroleum contamination has migrated parallel to Wildwood Drive. Recommendations included no further action at 16 areas and soil removal or remedial design at nine areas. |
John Halverson |
3/25/1995 |
Update or Other Action |
Received an Engineering Evaluation/Cost Analysis (EE/CA) from E&E for soil removal and treatment or disposal from the following sites: Main Complex - drum storage area, maintenance Building 55; ACS MARS Facility - former UST locations; Quonset Hut Area - petroleum stained soil, metals contaminated ash from burned building; Operations Building - drums storage area, AST/UST areas, transformer area; High Frequency Facility - transformer location, stockpiled soil; Trench Area Burn Pit. Also included disposal of building debris, creosote poles, septic tanks. |
John Halverson |
4/7/1995 |
Interim Removal Action Approved |
Received Underground Storage Tank Closure Assessment and Pipeline Removal report, dated March 1995, by Shannon and Wilson. The report documents UST and pipeline removal work done at the main complex and the ACS Mars facility. The following USTs were addressed: ACS Mars - USTs (none met the matrix cleanup level) 253-1, 257-1, 251-1, 250-1; Main Complex - 5-1, 5-2 and 502-1, the following USTs at the main complex met matrix cleanup levels 21-1, 3-1, 4-1, 15-1 and 17-1. Remedial investigation work was being done by E&E. |
John Halverson |
8/22/1995 |
Long Term Monitoring Established |
Received final Groundwater monitoring plan documents. Established quarterly and semiannual monitoring program for various wells on- and off-site over the next five years. |
John Halverson |
8/22/1995 |
Update or Other Action |
Received final - Baseline Human Health Risk Assessment Report, by E&E, August 1995. Concluded unacceptable risk may exist under current or future land use scenarios at the following: off-site residences downgradient from the former tank farm, Operations building groundwater, Landfill area groundwater, rifle range, firing range and trench area burn pit. Proposed an alternative soil cleanup level of 3,200 mg/kg DRO. |
John Halverson |
4/1/1996 |
Risk Assessment Report Approved |
Received final - Wildwood Ecological Risk Assessment, Tier 1: report recommended further analysis under Tier 2 sampling or conducting removal/remedial actions to address hot spots. |
John Halverson |
4/18/1996 |
Proposed Plan |
The Corps finalized the proposed plan. Preferred alternatives included: Main Complex tank farm and USTs 5-1 and 5-2 - vapor extraction and air sparging; Maintenance Building ACS MARS, Quonset Hut and Disposal Trench Area Burn Pit - soil excavation and off-site treatment followed by no further action; Operations Building - excavation and off-site treatment followed by natural attenuation and institutional controls; Landfill and Disposal Trenches - capping, natural attenuation (landfill area only) and institutional controls. |
John Halverson |
6/3/1996 |
Update or Other Action |
Received a groundwater monitoring report for tank farm area from sampling in November 1995. |
John Halverson |
6/3/1996 |
Update or Other Action |
Received a groundwater monitoring report for tank farm area from sampling in August 1995. It covered the main complex area tank farm and USTs (significant fuel contamination), ACS/MARS facility (low level DRO), Operations Building (DRO and low TEX), Landfill (low level VOCs) and Trench disposal areas (DRO and benzene at burn pit area). |
John Halverson |
8/27/1996 |
Update or Other Action |
Received the December 1995 groundwater monitoring event report. It covers the tank farm area and former USTs at the main complex (significant petroleum contamination in GW at and downgradient from tank farm), the ACS MARS facility and Quonset Hut area (low level DRO in GW), the Operation Building (DRO and TEX in GW), Landfill (low level VOCs) and Trench Disposal Areas (DRO, benzene at burn pit area). |
John Halverson |
8/27/1996 |
Update or Other Action |
Received the groundwater monitoring results from sampling in March 1996. It only included the tank farm area and USTs at the main complex area. |
John Halverson |
11/22/1996 |
Interim Removal Action Approved |
Received final "Remedial Action Report Interim Removal Action, Wildwood AFS" by Harding and Lawson Associates, October 28, 1996. Conclusions, based on confirmation samples at the end of the removal, include: ACS Mars - UST 250 and 253 meet cleanup levels, UST 251 did not (DRO 500 -3,400 mg/kg in soil); Quonset Hut Area - DRO 2,800 - 5,900 in soil; Trench Area Burn Pit - DRO 12,00 - 18,000 mg/kg; Main Complex - Building 55 and Drum Storage Area met cleanup levels; High Frequency Facility - up to 4,500 mg/kg DRO remains. |
John Halverson |
8/13/1997 |
Update or Other Action |
ADEC received the Work Plan for Phase II Remediation, Wildwood AFS, by HLA Wilder, dated July 2, 1997. Plan called for capping the disposal trenches and landfill areas with a soil cover and revegetating them, excavation and treatment of lead contaminated soil from the firing and rifle range, excavating and treating petroleum contaminated soil from the operations building transformer, UST and AST areas and installing an air sparing/vapor extraction system at the former tank farm. ADEC comments on the draft workplan were not all adequately addressed (i.e. it calls for excavating to pre-determined limits rather than to achieve cleanup levels) and no formal approval was given on the workplan. |
John Halverson |
12/9/1997 |
Update or Other Action |
Received the groundwater monitoring report for sampling done in July 1997. Groundwater levels have dropped significantly, some MWs have gone dry. Sampling was done at the tank farm and former USTs at the main complex (sheen and noticeable fuel odor present in two MWs, free product in MW AP-365; also 1,2 DCA level increased in a downgradient, off-site MW), Landfill (low level VOCs), Operations Building (up to 6 mg/l DRO), Rifle range (260 ug/l total lead) and Firing Range (12 ug/l total lead). |
John Halverson |
10/7/1998 |
Update or Other Action |
ADEC sent a letter to the Corps approving operation of the vapor extraction system without running the thermal oxidizer. The approval is based on the condition that a startup report be provided within 30 days after the 5 day startup period, the monthly and annual monitoring report be provided to DEC, if the VOC concentration in the stack monitor exceed 2,000 ppm - ADEC be notified immediately. This was based on air dispersion modeling done in the remedial design, the low levels of VOCs encountered thus far and challenges operating the thermal oxidizer. |
John Halverson |
12/15/1998 |
Update or Other Action |
Received groundwater monitoring report for sampling in February 1998. It covered sampling at the former tank farm area (water level continued to drop, has fallen from 3.5 to 6.5 feet since 12/95; four MWs contained measurable free product, 1,2DCA continued to increase in downgradient MW) and the Rifle Range (resampled for total and dissolved lead, dissolved lead was <1 ug/l, total lead was 95 ug/l). |
John Halverson |
5/5/1999 |
Update or Other Action |
Received groundwater monitoring report for sampling done in May 1998. Tank farm area (water level still low, free product in four MWs). |
John Halverson |
5/5/1999 |
Update or Other Action |
Received groundwater monitoring report for sampling done in February 1999. Tank farm area (free product in 3 MWs, several new MWs installed due to drop in water levels, new wells have longer well screens, samples from these wells had significantly lower contaminant levels that the samples from the original MWs), other areas not sampled. |
John Halverson |
5/5/1999 |
Update or Other Action |
Received groundwater monitoring report for sampling done in July 1998. Tank farm area (GW level rose slightly, free product found in 3 MWs, GRO increasing in down-gradient MW, 1,2DCA increasing in downgradient MW), Landfill area (low level VOCs, near cleanup levels), Operations building (DRO low levels, need new wells in better locations), Rifle range (total lead and antimony decreased, dissolved lead and antimony N/D), Firing range (total and dissolved lead and antimony N/D). |
John Halverson |
5/11/1999 |
Update or Other Action |
ADEC received the groundwater monitoring report for sampling done in February 1999 at the former tank farm area. Several new MWs were installed in late 1998 to replace wells that had gone dry due to falling water levels. The new wells have longer well screens. Sample results from these wells were generally much lower than from the original wells and may be due to a dilution effect from having a larger screened interval. Free product is present in three wells (two along the southern boundary of the site). 1,2 DCA in the downgradient, off-site well showed another slight increase in concentration. |
John Halverson |
8/4/1999 |
Update or Other Action |
ADEC received a draft revised groundwater monitoring plan for Wildwood AFS. ADEC responded with several comments on August 19, 1999. Corps will conduct one round of sampling, install the additional wells recommended, properly abandon wells that are no longer in use and then provide another draft monitoring plan, based on new information obtained in this initial sampling event. |
John Halverson |
9/3/1999 |
Update or Other Action |
ADEC received "Remedial Action Report, Phase II Remediation" by Harding and Lawson/Wilder, dated August 25, 1999. The report documents cleanup work done between June 1997 and November 1998. Main Complex drum storage area was cleaned up to levels specified in the contract. Operations Building - transformer area and drum storage area have residual DRO contamination; transformer casing and concrete sent to landfill. Rifle and firing ranges - lead contaminated soil was excavated and shipped to a TSDF; cleanup levels were achieved (<400 mg/kg Pb in soil). Landfill and disposal trenches were capped, graded and revegetated. Main Complex - air sparging/vest installed and operating at the former tank farm area. |
John Halverson |
10/6/1999 |
Update or Other Action |
ADEC received the Operations and Maintenance Manual AS/VE Remediation System Wildwood AFS, dated October 6, 1999 (HLA/Wilder). It documents that construction of the air sparging and vapor extraction system along with the operations and maintenance requirements. |
John Halverson |
6/30/2000 |
Update or Other Action |
ADEC received a Semi-Annual Interim Report - November 1999 through April 2000. It describes the operations and maintenance work conducted. It also notes that 11 additional monitoring wells (MW 17- MW 27) were installed earlier in 1999, however, the details on those wells is not included in this report. Respiration testing showed biodegradation is occurring, but at a low rate. Vapor monitoring from the VES and calculations indicate ~3,200 gallons of fuel were removed between startup and April 2000 through vapor extraction. |
John Halverson |
7/5/2001 |
Update or Other Action |
ADEC received the Former Wildwood Air Force Station October 1999 - December 2000 Groundwater Monitoring Report, dated June 29, 2001, by E&E. It documents six quarterly sampling events, installation of 10 monitoring wells (MW 8 -MW 16) in September and October 1999 at and downgradient from the former tank farm and two additional wells (MW 28 - MW 29) installed in July 2000. The laboratory results indicate GRO/BTEX concentrations have decreased significantly in the plume from the former tank farm. The DRO concentrations have not decreased as significantly and its plume size has been pretty stable. Concentrations of 1,2-DCA in downgradient wells also have to have decreased. Measurable free product appears to have reduced to the area around MW-5, which has been connected to the treatment system and was not monitored for product after July 2000. |
John Halverson |
9/12/2002 |
Site Number Identifier Changed |
Workplan changed from X1 to X9. Sequence Number changed to 04 from 01 to accommodate changing the Workplan. The DBA pointed out to the project manager that despite this site being listed as a petroleum site, DCA appears to be another major chemical of concern. |
John Halverson |
4/5/2004 |
Update or Other Action |
Staff reviewed the January 2004 groundwater monitoring report and requested the Corp provide an engineering evaluation of the effectiveness on shutting the system down over the winter. |
Debra Caillouet |
5/25/2004 |
Update or Other Action |
Staff reviewed a work plan for redevelopment of the sparge points. |
Debra Caillouet |
2/3/2005 |
Update or Other Action |
File number issued 2320.38.051 |
Aggie Blandford |
6/2/2005 |
Site Characterization Workplan Approved |
A work plan for Site Characterization and Attenuation Monitoring was approved with minor comments. The work plan describes the planned investigation to delineate further the locations of remaining NAPL at the various source areas within the former Wildwood AFS using the Rapid Optical Screening Tool (ROST), Laser-Induced Fluorescence (LIF). It includes sampling and analysis to calibrate the results of the ROST LIF work and to further characterize contaminant nature and obtain data with which to evaluate the status of each source area using current Method II and III tools, and possibly a 4-phase partitioning model. Sampling and analysis will also obtain data with which to evaluate natural attenuation occurrence at each source area. |
Debra Caillouet |
6/21/2005 |
Meeting or Teleconference Held |
Staff visited all of the Wildwood sites with the new project manager and the environmental engineer for the site. Staff also observed the ROST/LIF in operation. |
Debra Caillouet |
5/15/2006 |
Update or Other Action |
Groundwater monitoring report for Jan 06 approved |
Debra Caillouet |
5/25/2006 |
Cleanup Plan Approved |
Staff approved the groundwater monitoring plan for the former tank farm area for 06-08 |
Debra Caillouet |
1/29/2007 |
Site Characterization Report Approved |
Staff approved the Draft Report, Soil Sampling, October 2006, Former Wildwood Air Force Station. The report presents the results of soil sampling at the former tank farm. Sample locations were chosen based on the highest responses from the characterization that was done with the ROST/LIF. Contamination remains at the smear zone in the center of the site up to 5000 mg/kg DRO. The correlation with the ROST/LIF results was excellent. |
Debra Caillouet |
6/15/2007 |
Update or Other Action |
The Declaration of Project Closure Decison for the CON/HTRW project at Wildwood was signed. |
Debra Caillouet |
9/5/2007 |
Site Characterization Report Approved |
The ROST/LIF Investigation, Former Wildwood Air Force Station, Revision 1, April 2007 Report was reviewed and approved. The report presents the results of the investigation at multiple areas within the former Wildwood AFS during the summer of 2005. The logs from the ROST/LIF are presented along with laboratory analysis results. The report provides valuable site characterization data to support future decisions and generally meets the requirements of 18 AAC 75.335 Site Characterization.
|
Debra Caillouet |
11/8/2007 |
Site Characterization Report Approved |
Staff approved the May05-May06 Groundwater monitoring report |
Debra Caillouet |
11/16/2007 |
Exposure Tracking Model Ranking |
|
Debra Caillouet |
1/25/2008 |
Site Characterization Report Approved |
The 04-05 Groundwater Monitoring report was approved |
Debra Caillouet |
6/6/2008 |
Site Characterization Report Approved |
Staff approved the Gw Annual Report, Fall 2006/Spring 2007, Wildwood AS/VE System |
Debra Caillouet |
7/31/2008 |
Update or Other Action |
Staff reviewed the Draft Annual Groundwater Monitoring Report, Fall 2007-Spring 2008, Former Wildwood Air Force Station, Kenai, Alaska. DEC did not receive a copy of the laboratory data packages that are necessary to complete the review and approve the report. The well purging logs indicate that several wells are experiencing bio-fouling. Staff requested the Corps provide for redevelopment of these wells before the next sampling event and if possible treatment of these wells to remove the fouling.
|
Debra Caillouet |
8/19/2008 |
Update or Other Action |
comments were sent to the corp on the well decommisionin plan |
Debra Caillouet |
9/23/2008 |
Site Added to Database |
A new site has been added to the database |
Mitzi Read |
9/26/2008 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed for source area id: 78514 name: Former Tank Farm, USTs 5-1 & 5-2 |
Debra Caillouet |
3/27/2009 |
Update or Other Action |
Minor comment was sent to the Corps on the Draft Work Plan, Groundwater Monitoring, Former Wildwood Air Force Station |
Debra Caillouet |
4/3/2009 |
Update or Other Action |
The final 07-08 groundwater monitoring report was approved. |
Debra Caillouet |
6/5/2009 |
Document, Report, or Work plan Review - other |
The Final Work Plan, Groundwater Monitoring Former Wildwood Air Force Station, Kenai Alaska was approved. |
Debra Caillouet |
8/11/2009 |
Document, Report, or Work plan Review - other |
Staff sent a comment letter to the USACE on the draft system decommissioning report. |
Debra Caillouet |
1/4/2010 |
Document, Report, or Work plan Review - other |
The draft 2009 groundwater monitoring report was reviewed with no comment/ |
Debra Caillouet |
5/21/2010 |
Document, Report, or Work plan Review - other |
The final 2009 groundwater monitoring report was approved. |
Debra Caillouet |
11/1/2010 |
Document, Report, or Work plan Review - other |
Draft 2010 Annual Report, Groundwater Monitoring Tank Farm Site, Former Wildwood Air Force Station, October 2010 was approved. |
Debra Caillouet |
5/2/2011 |
Document, Report, or Work plan Review - other |
Final 2010 Annual Report, Groundwater Monitoring Tank Farm Site
Former Wildwood Air Force Station, April 2011
The report recommends properly decommissioning a monitoring well located near MW-16 that apparently abandoned without removal of the casing, DEC concurs. It also recommends the addition of MW-3 to the monitoring program, DEC has no objection.
|
Debra Caillouet |
10/31/2011 |
Document, Report, or Work plan Review - other |
2011 Annual Report, Groundwater Monitoring and Former Operations Building Facility Soil Assessment, Former Wildwood Air Force Station, The report adequately documents the results of the sampling and analysis that occurred during 2011 and is approved. The report documents the decommissioning of a monitoring well located near MW-16 that apparently had been abandoned without removal of the casing, The groundwater elevations have continued to lower and the DRO concentrations have risen at the Tank Farm. The soil sampled at the Operations Building showed no exceedances of the most stringent cleanup levels.
|
Debra Caillouet |
1/25/2012 |
Document, Report, or Work plan Review - other |
Work Plan, Groundwater Monitoring Former Wildwood Air Force Station, January 2012 and Waiver of Third Party Sampler Requirement approved. |
Debra Caillouet |
11/21/2013 |
CERCLA ROD Approved |
The Corps provided a copy of the signed Decision Document |
Debra Caillouet |
4/20/2015 |
Site Characterization Workplan Approved |
Follow-up Investigation Work Plan, Additional UVOST Delineation, Soil Sampling and Well Installation, Wildwood Partly Mitigated Sites Project 04 was approved. Additional characterization will be performed to support site closure decisions. |
Debra Caillouet |
7/10/2017 |
Document, Report, or Work plan Review - other |
Received the Summer 2016 Groundwater Sampling Report, dated January 2017 for the Wildwood Former Air Force Station Tank Farm Formerly Used Defense Site – F10AK025105. The described field effort was completed in August 2016 and generally consisted of collecting water samples from 8 of 9 planned monitoring wells (MW-3, MW-4, MW-6, MW-11, MW-23, MW-24, MW-30, and AP-397). Well MW-16 was not sampled because of a thin layer of free product (0.03 inches). The samples collected from Wells MW-3, MW-4, MW-6, and MW-11 exhibited concentrations of diesel range organics (DRO) above the Table C groundwater cleanup level of 1.5 mg/l. ADEC identified several issues in the report, as listed in the table below. Revised report requested by September 2017. |
Joshua Barsis |
7/10/2017 |
Document, Report, or Work plan Review - other |
Reviewed the Groundwater Sampling Work Plan Addendum, dated June 2017. This work plan covers the planned groundwater monitoring at the Wildwood Former Air Force Station Tank Farm Formerly Used Defense Site – F10AK025105 and the Wildwood Former Air Force Station Operation Facility Formerly Used Defense Site – F10AK025104. Proposed activities mainly include sampling nine wells (MW-3, MW-4, MW-6, MW-11, MW-16, MW-23, MW-24, MW-30, and AP-397) at the tank farm site and three wells (MW01, MW02, and MW03) at the operations building facility former storage tanks location. |
Joshua Barsis |
10/25/2017 |
Document, Report, or Work plan Review - other |
Received the final versions of two reports; the Annual 2016 Groundwater Sampling Report for the Operations Facility (F10AK025104) and the Annual 2016 Groundwater Sampling Report for the Tank Farm (F10AK025105), both dated October 2017. |
Joshua Barsis |
2/6/2018 |
Document, Report, or Work plan Review - other |
Reviewed the 2017 Groundwater Sampling Report, dated December 2017 for the Wildwood Former Air Force Station Tank Farm Formerly Used Defense Site – F10AK025105. The described field effort was completed in August 2017 and consisted of collecting water samples from 8 of 9 planned monitoring wells (MW-3, MW-4, MW-6, MW-11, MW-23, MW-24, MW-30, and AP-397). Well MW-16 was not sampled because of a thin layer of free product (0.02 feet). The samples collected from Wells MW-3, MW-4, MW-6, and MW-11 exhibited concentrations of diesel range organics (DRO) above the Table C groundwater cleanup level of 1.5 mg/l. ADEC identified several minor issues in the report, as listed in the table below. ADEC requested a revised report by May 1, 2018. |
Joshua Barsis |
2/12/2018 |
Document, Report, or Work plan Review - other |
Reviewed the Groundwater Sampling Work Plan Addendum, dated February 2018. This work plan covers the planned groundwater monitoring at the Wildwood Former Air Force Station Tank Farm Formerly Used Defense Site – F10AK025105 and the Wildwood Former Air Force Station Operation Facility Formerly Used Defense Site – F10AK025104. Proposed activities mainly include sampling nine wells (MW-3, MW-4, MW-6, MW-11, MW-16, MW-23, MW-24, MW-30, and AP-397) at the tank farm site and three wells (MW01, MW02, and MW03) at the operations building facility former storage tanks location. |
Joshua Barsis |
7/11/2018 |
Document, Report, or Work plan Review - other |
Reviewed the Groundwater Sampling Work Plan Addendum, dated February 2018. This work plan covers the planned groundwater monitoring at the Wildwood Former Air Force Station Tank Farm Formerly Used Defense Site – F10AK025105 and the Wildwood Former Air Force Station Operation Facility Formerly Used Defense Site – F10AK025104. Proposed activities mainly include sampling nine wells (MW-3, MW-4, MW-6, MW-11, MW-16, MW-23, MW-24, MW-30, and AP-397) at the tank farm site and three wells (MW01, MW02, and MW03) at the operations building facility former storage tanks location. |
Joshua Barsis |
11/14/2018 |
Document, Report, or Work plan Review - other |
Reviewed the 2018 Groundwater Sampling Report, dated September 2018, for the Wildwood Former Air Force Station Tank Farm Formerly Used Defense Site – F10AK025105. The described field effort was completed in August 2018, and consisted of collecting water samples from 8 of 9 planned monitoring wells (MW-3, MW-4, MW-6, MW-11, MW-23, MW-24, MW-30, and AP-397). Well MW-16 was not sampled because of a thin layer of free product (0.03 feet). The samples collected from Wells MW-3, MW-4, MW-6, and MW-11 exhibited concentrations of diesel range organics (DRO) above the Table C groundwater cleanup level of 1.5 mg/l. |
Joshua Barsis |
7/5/2019 |
Update or Other Action |
Site location was updated on this date. Coordinates for this site are used to determine the presence and position of the site on BLM’s ANCSA Conveyed Land web map. |
Rebekah Reams |
2/25/2020 |
Document, Report, or Work plan Review - other |
Reviewed the 2019 Groundwater Sampling Report, dated July 2019, for the Wildwood Former Air Force Station Tank Farm Formerly Used Defense Site – F10AK025105. The described field effort was completed in June 2019, and consisted of collecting water samples from 8 of 9 planned monitoring wells (MW-3, MW-4, MW-6, MW-11, MW-23, MW-24, MW-30, and AP-397). Well MW-16 was not sampled because of a thin layer of free product (0.032feet). The samples collected from Wells MW-4, MW-6, and MW-11 exhibited concentrations of diesel range organics (DRO) above the Table C groundwater cleanup level of 1.5 mg/l. This report is approved. |
Joshua Barsis |
6/16/2020 |
Site Characterization Workplan Approved |
The department approved a workplan to conduct groundwater sampling at the Former Tank Farm and Operations Building AST/UST, 12-acre landfill, and UST 502-1. Monitoring wells MW-3, MW-4, MW-6, MW-11, MW-16, MW-23, MW-24, 30, and APA-397 at the Former Tank Farm will be sampled and analyzed for DRO and DCA.
|
Lisa Krebs-Barsis |
8/20/2021 |
Site Characterization Report Approved |
ADEC reviewed the 2020 Groundwater Sampling Report for the Former Tank Farm, Operations Building Former ASTs/USTs, 12-acre landfill, and UST 502-1. At the Former Tank Farm wells MW30, AP397, MW11, MW23, MW24, MW6, MW4, and MW3 were sampled for DRO and DCA. DRO was detected in MW-3 at a concentration of 3.04 mg/L, MW-4 at 8.37mg/L, MW-6 at 3.12 mg/L and MW-11 at 9.39 mg/L, all exceeding the Decision Document criteria of 1.5 mg/L. Free product was measured in MW-16 at a thickness of 0.02 feet which is consistent with previous monitoring events. DCA was not detected above project screening criteria in any well and did not exceed the Decision Document specified cleanup level. A recommendation to reduce sampling to every two years was approved. |
Lisa Krebs-Barsis |
8/26/2021 |
Site Characterization Workplan Approved |
The 2021 and 2022 Groundwater Sampling Work Plan Addendum for the Former Tank Farm, Operations Building Former ASTs/USTs, 12-acre Landfill and UST 502-1 received on August 25, 2021 is approved. For the Former Tank Farm a visual inspection of the Former Tank Farm will be conducted in 2021. This will include inspecting the condition of the wells and confirming that no new building construction or water well installation has occurred in the area. For 2022, the following wells will be sampled and analyzed for DRO: MW-3, MW-4, MW-6, MW-11, MW-16, MW-23, MW-24, MW-30 and AP-397. A drawdown test will be conducted at MW-16 to demonstrate that free product has been recovered to the maximum extent possible. |
Lisa Krebs-Barsis |
7/19/2022 |
Update or Other Action |
Approved request for decommissioning of MW-30. The well will be demolished by the new property owner and the USACE proposed to decommission it appropriately. |
Lisa Krebs-Barsis |
4/5/2024 |
Document, Report, or Work plan Review - other |
DEC has reviewed 2022 Groundwater Sampling Report Wildwood AFS Formerly Used Defense Site (FUDS) Property F10AK0251 HTRW Project -05 Former Tank Farm, CON/HTRW Project -06 Operations Building Former ASTs/USTs, HTRW Project -07 12-acre Landfill, and CON/HTRW Project -08 UST 502-1 Kenai, AK, dated June 2023. The report describes the 2022 groundwater monitoring event at the former Tank Farm, 12-acre Landfill, Underground Storage Tank (UST) 502-1, and at the Operations Building Former Aboveground Storage Tanks (ASTs) /USTs sites located at the Wildwood Air Force Station, Alaska. The report recommends continued monitoring at the Operations Facility and 12-acre Landfill and project closeout for the UST-502-1 site. This report was received several months after the work plan for the 2023 and 2024 fieldwork was reviewed and approved. We have asked for the 2023 reporting and any updates to the 2024 work planned for the upcoming field season. Report is approved. |
Brian Watts |
7/9/2024 |
Site Visit |
DEC staff conducted a site visit to the Wildwood AFS area in Kenai, Alaska. The purpose of the site visit was to inspect multiple sites within the Wildwood Air Force Station and observe groundwater monitoring fieldwork. Sites inspected were; 12-acre Landfill, disposal trench area, Underground Storage Tank (UST) area near the Correctional Facility, and the Operations Maintenance Building. U.S. Army Corp of Engineers staff accompanied DEC staff around the facility for the inspection. |
Peter Campbell |
7/29/2024 |
Update or Other Action |
DEC provided the U.S. Army Corp of Engineers with a letter summarizing site inspection notes from a July 9, 2024 site visit at various Wildwood AFS sites. The letter described several deviations from the approved work plans (dated 2016 and 2023), and requested USACE discuss impacts of the deviations and issues in the reporting. |
Erica Blake |