Site Report: FAA Gulkana Bldg 400 AST 32-D-005
Site Name: | FAA Gulkana Bldg 400 AST 32-D-005 |
---|---|
Address: | Gulkana Airport Building 400, Glennallen, AK 99588 |
File Number: | 140.38.002 |
Hazard ID: | 25301 |
Status: | Cleanup Complete |
Staff: | No Longer Assigned, 9074655229 dec.icunit@alaska.gov |
Latitude: | 62.158092 |
Longitude: | -145.457295 |
Horizontal Datum: | WGS84 |
We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.
Problems/Comments
During the FY92 SI, a heating oil AST was located adjacent to the southeast wall of Building 400. In FY98, a release investigation was conducted and observed the AST currently in use; however, the AST was scheduled for replacement because a valve located on the fill end of the tank was potentially leaking. Sample results from the release investigation indicated that diesel was detected below Method 1 matrix category C cleanup levels. However, due to the presence of structures and utilities, undetected contaminated soil may be present under the AST. The 2006 investigation found that field observations and laboratory results indicate that petroleum contamination is concentrated in soil located at the east end of the AST to a depth of at least six feet bgs. The source of contamination in this area is most likely heating oil that leaked from the valve on the fill end of the former heating oil AST. The estimated volume of soil with contaminant concentrations exceeding ADEC Method Two cleanup levels within this area is approximately 55 cy.
Action Information
Action Date | Action | Description | DEC Staff |
---|---|---|---|
9/20/1993 | Site Added to Database | A new site has been added to the database (Date adjusted from 12/30/2008 for report/query consistency. (Reese)) | Mitzi Read |
9/20/1993 | Site Added to Database | Former Staff | |
10/20/1993 | Site Ranked Using the AHRM | Initial ranking. | Former Staff |
8/20/1998 | Update or Other Action | Site work done in August 1998 for "Final Release Investigation Work Plan, Federal Aviation Administration Gulkana Station" dated July 28, 1998. Staff did not have time to complete plan review before work was done. | Eileen Olson |
2/20/2003 | Update or Other Action | Anchorage office rec'd from the Fairbanks DEC office an ECIR (Environmental Compliance Investigation Report) dated November 1992 and a DEC review letter for that document dated June 11, 1993. The letter requests additional investigation of petroleum hydrocarbon contamination and notes that regulated USTs need to come into compliance with State UST regs. | Eileen Olson |
1/26/2006 | Update or Other Action | All work performed for the Federal Aviation Administration (FAA) requires completion and approval of a Project Environmental and Occupational Safety and Health Worksheet (EOSH Worksheet). The EOSH Worksheet is a tool that allows project managers to identify potential hazards and contamination, take appropriate measures to avoid hazards and manage contamination appropriately, to minimize environmental impacts, determine whether environmental assessment is required prior to beginning work, and to minimize fines and/or penalties associated with non-compliance with federal and state regulations. It also acts a mechanism to identify when outside agency permits are necessary. Specific portions of the EOSH Worksheet address: the presence/absence of endangered species, activities conducted in wetlands or anadromous streams, whether work will occur on a contaminated site or involve activities associated with fuel tanks, fuel distribution lines, oil-containing transformers, groundwater monitoring wells, floor drains, and generation and handling of hazardous waste. To ensure all issues are appropriately considered, the worksheet is to be reviewed after each phase of project development and implemenation. This form is to be kept with project progress documents throughout the project. | Sharon Richmond |
3/27/2007 | Update or Other Action | Received Draft Site Investigation Report | Colin Craven |
5/8/2007 | Update or Other Action | Lisa Maserjian assigned as Project Manager. Completed review and comments on Draft Site Investigation report and mail out comments letter to FAA. Main issues are that they did not propose a cleanup level, and specific remediation actions but proposed many ideas. Some problems with the data validation. They also asked that the site be given a 350 Determination. DEC does not agree with this as there are domestic wells in the area and asked them to better define the hydrogeology showing how the shallow site water is not connected to the aquifers used for domestic purposes. | Lisa Maserjian |
5/29/2007 | Exposure Tracking Model Ranking | Initial ranking for all sites. | Lisa Maserjian |
12/30/2008 | Site Characterization Report Approved | Staff reviewed the Final Site Investigation Report, Federal Aviation Administration, Gulkana Airport Site Investigation, Gulkana Alaska, April 25, 2008. The report accurately presents the results of the site characterization activities that took place during the summer of 2006 at the Gulkana Airport. Based on the information in this report DEC has determined that Building 102 is eligible for closure and a cleanup complete determination will be sent in a separate letter. The report provides an estimate of the volume of soil above the Method 2 migration to groundwater cleanup level of 250 mg/kg for diesel range organics by site/building. It also recommends the implementation of Interim Removal Actions (IRAs) at Buildings 600, 603 & 604, 601, 303, the former tank farm and Building 400. DEC recommends that the Federal Aviation Administration propose cleanup levels for each site for DEC concurrence and then proceed with remedial actions that will achieve cleanup complete for each site, rather than IRAs that would not completely mitigate the risk at each site. DEC also recommends removal of the buried drums at the RCAG and characterization of any remaining contamination. DEC also requests characterization at Building 605 Sewage Treatment and Lift Station to determine if there is contamination present. The contaminated sites database has maintained one entry for the FAA Gulkana Station. The database is being revised to show separate entries for each of the above sites so that each one can be tracked and closed separately. | Debra Caillouet |
11/21/2012 | Cleanup Complete Determination Issued | The FAA requested a Cleanup Complete determination for this site. ADEC determined the site met the requirements for a Cleanup Complete determination. | Debra Caillouet |
Contaminant Information
Name | Level Description | Media | Comments |
---|---|---|---|
DRO | Between Method 2 Migration to Groundwater and Human Health/Ingestion/Inhalation | Soil |
Control Type
Type | Details |
---|---|
No ICs Required |
Requirements
Description | Details |
---|---|
Advance approval required to transport soil or groundwater off-site. |
No associated sites were found.