Action Date |
Action |
Description |
DEC Staff |
12/13/1993 |
Site Added to Database |
Chlorinated solvents, metals, diesel, gasoline and waste oil. |
Former Staff |
12/21/1994 |
Update or Other Action |
(Old R:Base Action Code = RPL2 - Site Information Request Letter). |
Former Staff |
2/7/1995 |
Update or Other Action |
(Old R:Base Action Code = SA2 - Phase II Site Assessment (General)). Review of "Compliance Investigation Report" --ADEC had no comment except that it was looking forward to work plan submittal. |
Randy Rice |
11/28/1997 |
Site Ranked Using the AHRM |
Initial ranking. |
Sally Schlichting |
2/18/2000 |
Meeting or Teleconference Held |
Met with FAA and contractor to discuss file, ADEC requirements for additional characterization, and target cleanup levels. |
Eileen Olson |
2/28/2000 |
Update or Other Action |
Issued file review letter outlining alternatives for developing cleanup levels and requesting additional investigation and monitoring. |
Eileen Olson |
3/23/2000 |
Site Ranked Using the AHRM |
Reranked site to reflect the presence of contamination in groundwater monitoring wells (Groundwater Exposure Index Value went from 0 to 1) and existence of on-site water well (groundwater Exposure went from 0.1 to 0.8)--the well is used for bathing and other purposes, but drinking water is brought in. Site was a high priority before changes were made and still is. |
Eileen Olson |
6/29/2000 |
Site Characterization Workplan Approved |
Letter sent: Staff conditionally approved a release investigation work plan for additional characterization of soil and groundwater contamination at this remote facility, to begin by mid-July. FAA plans to construct several monitoring wells in highly contaminated areas, and several sentinel wells to determine whether groundwater contaminants are migrating off-site into the adjacent marine environment or other surface waters. FAA also plans to construct a lined and covered passive biocell to contain about 60 cubic yards of diesel contaminated soil. The soil will be placed in the cell in an 18-inch-thick lift. Soil type is primarily sandy gravel. |
Eileen Olson |
11/16/2000 |
Meeting or Teleconference Held |
Meeting at FAA to discuss the findings of the Cape Yakataga investigation. Free product present. Requested table showing screened intervals correlated with water depths in monitoring wells. |
Eileen Olson |
9/18/2002 |
Update or Other Action |
Sent letter requesting groundwater monitoring for all existing wells on site, with a schedule of monitoring to be submitted by March 31, 2003 and the monitoring to be complete by June 30, 2003. |
Elizabeth Stergiou |
9/19/2002 |
Update or Other Action |
Sent letter requesting FAA submit the following documents by October 1, 2002: Environmental Compliance Investigation Report, the final release investigation report from 2000, status of free product and status of the all contaminated sites at the station. |
Elizabeth Stergiou |
9/4/2003 |
Update or Other Action |
ADEC approved the workplan for the Fall 2003 Sampling and Analysis Plan for various sites. |
Deborah Williams |
5/7/2004 |
Site Number Identifier Changed |
Region changed from 11 to 24. |
Former Staff |
2/23/2007 |
Update or Other Action |
comment letter sent on the scope of work for landfill removal |
Debra Caillouet |
4/10/2007 |
Update or Other Action |
Staff provided expedited comment on the draft landfill removal work plan |
Debra Caillouet |
4/30/2007 |
Cleanup Plan Approved |
Plan to remove contents of landfill eroding into the Duktoth and charcterize and dispose was approved |
Debra Caillouet |
8/20/2007 |
Cleanup Plan Approved |
The Phase II removal action work plan addendum was approved. The FAA will remove the top half of the landfill during August-September 2007 and store equipment at the site over winter. Another work plan will be provided for Phase III which will occur next spring to complete the removal of the contaminated soil. |
Debra Caillouet |
10/12/2007 |
Exposure Tracking Model Ranking |
|
Debra Caillouet |
3/7/2008 |
Update or Other Action |
Comments on the draft Phase I/II removal report were sent to the FAA. |
Debra Caillouet |
3/24/2008 |
Update or Other Action |
Comments were sent on the Phase III landfill removal work plan. |
Debra Caillouet |
11/20/2008 |
Document, Report, or Work plan Review - other |
Staff reviewed and prepared comment on the Cape Yakataga Debris Removal, Phase III Report, Revision 0, October 2008 |
Debra Caillouet |
11/20/2008 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 78271 landfill. |
Debra Caillouet |
1/9/2009 |
Interim Removal Action Approved |
Staff approved the PhaseI/II landfill removal report |
Debra Caillouet |
1/12/2009 |
Site Added to Database |
A new site has been added to the database |
Mitzi Read |
1/12/2009 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed for source area id: 78680 name: Former Quarters Area |
Debra Caillouet |
3/28/2012 |
Document, Report, or Work plan Review - other |
Draft Work Plan, Federal Aviation Administration Release Investigation, FAA Station Cape Yakataga, March 9, 2012 |
Debra Caillouet |
10/29/2013 |
Site Characterization Report Approved |
The 2012 Release Investigation defined the extent of the plume. DRO was found at a max of 1.4 mg/l in the groundwater. DRO contamination in soil is in the smear zone, 18-22 feet bgs with a max found of 7600 mg/kg. |
Debra Caillouet |
11/20/2013 |
Cleanup Complete Determination Issued |
Final Release Investigation and Hydrocarbon Risk Calculator Report, FAA Station Cape Yakataga, September 2013
Former Quarters Area/Station Yard (Hazard ID 25324)
This AOC includes the former School Building 303. During the 2012 RI, 129 UVOST probes were advanced to investigate the extent of contamination at the Station Yard AOC, extending from the roadway north of the Station Yard to the vegetated section between the Station Yard and the airstrip. A total of 21 soil borings were advanced and 26 soil samples were collected for laboratory analysis.
DRO concentrations in soil were greater than ADEC Method Two, Over 40-Inch Zone, Migration to Groundwater cleanup levels in 19 of the 26 soil samples analyzed for DRO. DRO concentrations in these samples ranged from 350 to 7,600 mg/kg. All BTEX, GRO, and RRO concentrations were less than the applicable ADEC Method Two cleanup levels.
Ten wells were sampled and the groundwater analyzed for DRO, GRO, RRO and BTEX. No contaminants were detected at concentrations greater than ADEC Table C Groundwater cleanup levels.
Based on the HRC calculations, the Station Yard AOC at the FAA Station Cape Yakataga is eligible for a Cleanup Complete determination. It is recommended that ADEC grant the Station Yard AOC a Cleanup Complete determination with no ICs. ADEC concurs and is listing this site as Cleanup Complete in the Contaminated Sites Database.
|
Debra Caillouet |